Proposal
Details to partially discharge condition 11 (Temporary land uses - Temporary Welfare Drawing Package), of planning permission 2018/02100/COMB dated 8 February 2019.
As published by the council, reference 2021/00210/DET
Application record
- Reference
- 2021/00210/DET
- Type
- Details to Meet Conditions Full/Outline
- Status
- Pending Consideration
- Received
- 22 Jan 2021
- Validated
- 25 Jan 2021
- Ward
- Parsons Green And Walham
- Decision by
- Delegated Decision
Site history
Applications at this address on the Hammersmith and Fulham register
This site has had 118 applications since 2017: 39 approved, 0 refused.
-
P/2026/02356/NMAT Awaiting decision
Fulham Gas Works Imperial Road London
Non-Material Amendment to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 (as amended by ref: 2024/00961/VAR dated 3 December 2024), in respect of the description of development to change it from "Planning Application (part-detailed, part-outline) for demolition of existing buildings and structures (excl. No.2 Gasholder, 1856 Chief Engineer's Office, 1927 Research Laboratory, 1920 WWI War Memorial and WW2 War Memorial) and redevelopment to provide a residential-led mixed use development comprising the erection of new buildings" to "Planning Application (part-detailed, part-outline) for demolition of selected existing buildings and structures and redevelopment to provide a residential-led mixed use development comprising the erection of new buildings", specifically allowing the insertion of "selected" and the deletion of "(excl. No.2 Gasholder, 1856 Chief Engineer's Office, 1927 Research Laboratory, 1920 WWI War Memorial and WW2 War Memorial)"
-
P/2026/02015/DET Awaiting decision
Fulham Gas Works Imperial Road London
Details to discharge Condition 62 (Road Safety Audit) for Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).
-
P/2026/01772/NMAT Awaiting decision
Fulham Gas Works,Imperial Road,London
Non-Material Amendment to Planning Permission (ref: 2018/02100/COMB ) dated 8 February 2019 (as amended by ref: 2024/00961/VAR dated 3 December 2024), in respect of Condition 73 (details and materials). The proposed amendment being the requirement of a mock up to be provided remotely for review by officers rather than on site.
-
P/2026/01754/DLBC Granted
Fulham Gas Works Imperial Road London
Details of paint finishes, in compliance with Condition 3 of Listed Building Consent (ref: 2025/00568/LBC) dated 23 July 2026.
-
P/2026/01473/DET Granted
Fulham Gas Works Imperial Road London
Details to discharge Condition 20 (Verification Report) for Phases 3b, 3c and 3d (Development Plots E1 and E2) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).
-
P/2026/01890/VAR Awaiting decision
Fulham Gas Works Imperial Road London
Variation of Condition 1 (Drawings) of reserved matters details relating to the approval of access; appearance; landscaping; layout and scale in respect of Phases 4b, 4c and 4d (Development Plots H1 and H2); for the erection of two buildings comprising residential and non-residential floorspace with associated landscaping approved under 2024/01420/RES granted 17 January 2025 of planning permission 2018/02100/COMB granted 8 February 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). As varied by 2024/00961/VAR variation of Condition 4 (Drawings) and Condition 5 (Design Codes and Parameter Plans) of planning permission 2018/02100/COMB granted 8 Feb 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). The proposed amendments to Phase 4b Development Plot H1 comprise: (a) revisions to tower and shoulder terrace heights within consented maximum parameter heights (comprising an increase in shoulder height and reduction in tower height); (b) changes to the arrangemen... read more
-
P/2026/01214/DET Awaiting decision
Fulham Gas Works Imperial Road London
Details to discharge Condition 16 (Preliminary Risk Assessment) for Development Phases 3a, 4a, 5a, 5b and 6 pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).
-
P/2026/01125/ADV Granted
Fulham Gas Works Imperial Road London
Display of 1no. internally illuminated fascia sign and 2no. non-illuminated projecting signs to Unit 4a, phase 1
-
P/2026/01024/DET Awaiting decision
Fulham Gas Works Imperial Road London
Details to discharge Condition 87 (Materials) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).
-
P/2026/01008/DET Awaiting decision
Fulham Gas Works,Imperial Road,London
Details to discharge Condition 74 (1:20 details) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024)
Timeline
Dates from the published record
-
22 Jan 2021
Received by Hammersmith and Fulham
-
25 Jan 2021
Validated
Checked as complete and ready for consideration.
-
15 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 22 March 2021, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Hammersmith and Fulham took a median of 80 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Hammersmith and Fulham for determination, against a statutory target of eight weeks. Over the last year Hammersmith and Fulham decided condition discharge and variation applications in a median of 102 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Fulham Gas Works Imperial Road London
Details to construct a single storey temporary show apartment within Phase 1b (Development Plot A3) for a period of 18 months; in compliance with Condition 11 (Temporary Land Uses) of planning permission (ref: 2018/02100/COMB) dated 8 February 2019.
Granted Conditions 8 docsSmall domestic -
Fulham Gas Works Imperial Road London
95% historically approved · decision due ~30 Mar
Details to discharge conditions 74 (1:20 Details) and condition 75 (A1/A3 1:20 Details) of planning permission 2018/02100/COMB dated
Awaiting decision Conditions 14 docs -
Fulham Gasworks Imperial Road London
Reserved Matters Application (access, appearance, landscaping, layout and scale) in respect of Phase 2a (Development Plot B1) for the erection of a single storey pavilion-style building comprising 205sqm of flexible floorspace (Use Classes A1, A2, A3, A4 and B1) with associated landscaping pursuant to planning application 2018/02100/COMB granted 8 February 2019 (comprehensive residential led mixed use redevelopment of the former Gasworks Site).
Granted Reserved matters 31 docsSmall domestic -
30 - 32 Bradmore Park Road London W6 0DT
Details of demolition notice, in compliance with condition 3 of planning permission (ref: 2017/03836/FUL) dated 22nd December 2017.
Granted Conditions Demolition 13 docs -
Fulham Gasworks Imperial Road London
Details of Air Quality Assessment, in compliance with condition 41 of planning permission 2018/02100/COMB dated 8th February 2019.
Awaiting decision Conditions 5 docs -
Fulham Gasworks Imperial Road London
Details to discharge Condition 27 (Flood Risk Assessment); Condition 28i (Outline Drainage Strategy); and Condition 32 (Site Wide Drainage Strategy) for all Phases; plus details to discharge Condition 28ii (Detailed Drainage Strategy) for Phases 1a, 1b, 1c and Phase 2a of planning permission 2018/02100/COMB dated 8 February 2019.
Granted Conditions 20 docs
Other condition discharge and variation applications
In Hammersmith and Fulham
-
P/2026/01352/DET Granted
50 Brook Green, London, W6 7BJ
Submission of a Demolition Logistics Plan, pursuant to Condition 4; a Construction Logistics Plan, pursuant to Condition 5; an updated Arboricultural Impact Assessment and Tree Protection Plan, pursuant to Condition 17; details of accessible units, pursuant to Condition 23; and details of Air Quality Emissions Control of Non-Road Mobile Machinery (NRMM), pursuant to Conditions 35 and 36 of the planning permission reference: 2025/00492/VAR dated 5th May 2026.
-
P/2026/01398/DET Granted
574 - 580 King's Road, London, SW6 2DY
Submission of details of a Ventilation Strategy Report, pursuant to Condition 16 of the planning permission reference: 2025/01090/FUL dated 27th November 2025.
-
P/2026/02566/DET Awaiting decision
Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12
Details to discharge Condition 12 (temporary fencing and/or enclosure) relating to Development Zone 3 ('DZ3') of planning planning permission 2025/02724/VAR dated 9 September 2026.
-
P/2026/02562/DET Awaiting decision
Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12
Details to discharge Condition 21 (Piling Method Statement) relating to Development Zone 3 ('DZ3') of planning planning permission 2025/02724/VAR dated 9 September 2026.
-
P/2026/02563/DET Awaiting decision
Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12
Details to discharge Condition 10 (Construction Management Plan (CMP)) of planning planning permission 2025/02724/VAR dated 9 September 2026.