Fulham Gas Works Imperial Road London

Granted Hammersmith and Fulham 2020/03251/DET Details to Meet Conditions Full/Outline

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Details to construct a single storey temporary show apartment within Phase 1b (Development Plot A3) for a period of 18 months; in compliance with Condition 11 (Temporary Land Uses) of planning permission (ref: 2018/02100/COMB) dated 8 February 2019.

As published by the council, reference 2020/03251/DET

Application record

Reference
2020/03251/DET
Type
Details to Meet Conditions Full/Outline
Status
Application Approved
Decision
Application Approved
Received
7 Dec 2020
Validated
8 Dec 2020
Decided
2 Feb 2021
Ward
Parsons Green And Walham
Decision by
Delegated Decision

Site history

Applications at this address on the Hammersmith and Fulham register

This site has had 110 applications since 2020: 31 approved, 0 refused.

  • P/2026/02015/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 62 (Road Safety Audit) for Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 5 Aug 2026 Conditions
  • P/2026/01772/NMAT Awaiting decision

    Fulham Gas Works,Imperial Road,London

    Non-Material Amendment to Planning Permission (ref: 2018/02100/COMB ) dated 8 February 2019 (as amended by ref: 2024/00961/VAR dated 3 December 2024), in respect of Condition 73 (details and materials). The proposed amendment being the requirement of a mock up to be provided remotely for review by officers rather than on site.

    Submitted 13 Jul 2026 Amendments
  • P/2026/01754/DLBC Awaiting decision

    Fulham Gas Works Imperial Road London

    Details of paint finishes, in compliance with Condition 3 of Listed Building consent 2025/00568/LBC dated 23 July 2026.

    Submitted 10 Jul 2026 Conditions
  • Fulham Gas Works Imperial Road London

    Details to discharge Condition 20 (Verification Report) for Phases 3b, 3c and 3d (Development Plots E1 and E2) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Decided 21 Jul 2026 Conditions
  • P/2026/01890/VAR Awaiting decision

    Fulham Gas Works Imperial Road London

    Variation of Condition 1 (Drawings) of reserved matters details relating to the approval of access; appearance; landscaping; layout and scale in respect of Phases 4b, 4c and 4d (Development Plots H1 and H2); for the erection of two buildings comprising residential and non-residential floorspace with associated landscaping approved under 2024/01420/RES granted 17 January 2025 of planning permission 2018/02100/COMB granted 8 February 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). As varied by 2024/00961/VAR variation of Condition 4 (Drawings) and Condition 5 (Design Codes and Parameter Plans) of planning permission 2018/02100/COMB granted 8 Feb 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). The proposed amendments to Phase 4b Development Plot H1 comprise: (a) revisions to tower and shoulder terrace heights within consented maximum parameter heights (comprising an increase in shoulder height and reduction in tower height); (b) changes to the arrangemen... read more

    Submitted 15 May 2026 Amendments
  • P/2026/01214/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 16 (Preliminary Risk Assessment) for Development Phases 3a, 4a, 5a, 5b and 6 pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 6 May 2026 Conditions
  • Fulham Gas Works Imperial Road London

    Display of 1no. internally illuminated fascia sign and 2no. non-illuminated projecting signs to Unit 4a, phase 1

    Decided 3 Jul 2026 Advertising
  • P/2026/01024/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 87 (Materials) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 16 Apr 2026 Conditions
  • P/2026/01008/DET Awaiting decision

    Fulham Gas Works,Imperial Road,London

    Details to discharge Condition 74 (1:20 details) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024)

    Submitted 14 Apr 2026 Conditions
  • P/2026/01009/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 89 (Secured by Design - Ground Level) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 14 Apr 2026 Conditions

Timeline

Dates from the published record

  1. 7 Dec 2020

    Received by Hammersmith and Fulham

  2. 8 Dec 2020

    Validated

    Checked as complete and ready for consideration.

  3. 2 Feb 2021

    Decision issued: Application Approved

  4. 15 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

8 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Hammersmith and Fulham granted permission on 2 February 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Fulham Gas Works Imperial Road London

    2021/00320/DET Submitted 1 Feb 2021 0m away

    95% historically approved · decision due ~30 Mar

    Details to discharge conditions 74 (1:20 Details) and condition 75 (A1/A3 1:20 Details) of planning permission 2018/02100/COMB dated

    Awaiting decision Conditions 14 docs
  • Fulham Gas Works Imperial Road London

    2021/00210/DET Submitted 22 Jan 2021 0m away

    95% historically approved · decision due ~22 Mar

    Details to partially discharge condition 11 (Temporary land uses - Temporary Welfare Drawing Package), of planning permission 2018/02100/COMB dated 8 February 2019.

    Awaiting decision Conditions 4 docs
  • Fulham Gasworks Imperial Road London

    2020/00525/DET Submitted 21 Feb 2020 0m away

    95% historically approved · decision due ~20 Apr

    Details of ventilation strategy, in compliance with condition 42 (a) & (b); details of combustion plant, in compliance with condition 45 (a) & (b) in relation to Development Plots A1, A2 & A3 (Phase 1a, 1b & 1c) of planning permission 2018/02100/COMB dated 8 February 2019.

    Awaiting decision Conditions 13 docs
  • Fulham Gas Works Imperial Road London

    2020/01595/DET Submitted 24 Jun 2020 15m away

    95% historically approved · decision due ~20 Aug

    Details to partially discharge Condition 20 (Contamination - Verification Report) for Plot B1 Phase 2a of planning permission 2018/02100/COMB dated 8 February 2019.

    Awaiting decision Conditions 7 docs
  • Fulham Gas Works Imperial Road London

    2020/00900/DET Submitted 3 Apr 2020 15m away

    95% historically approved · decision due ~29 May

    Detail to partially discharge Condition 12 (Retail Amalgamation); Condition 55 (Extraction & Odour control); Condition 56 (Cleaning Schedule); Condition 58 (Outdoor Seating); Condition 59 (Outside Seating (Operating Hours)); Condition 60 (Operating Hours); Condition 100 (Lifts), relating to development Plot B1 (Phase 2a) of planning permission 2018/02100/COMB dated 8 February 2019.

    Awaiting decision Conditions 4 docs
  • Fulham Gas Works Imperial Road London

    2020/00899/DET Submitted 3 Apr 2020 15m away

    95% historically approved · decision due ~29 May

    Detail to partially discharge condition 43 (Low emissions - Air quality) relating to development Plot B1 (Phase 2a) of planning permission 2018/02100/COMB dated 8 February 2019.

    Awaiting decision Conditions 5 docs

In Hammersmith and Fulham

  • 25 St Peter'S Square, London, W6 9NW

    Submission of details of Full details, including photographs of physical samples, of materials to be used on the external surfaces of the building, boundary walls and ground surfaces pursuant to condition 3 of planning application ref: 2025/02038/LBC granted 2nd July 2026.

    3 Jul 2026 Conditions
  • 517-523 Fulham Road, London, SW6 1HD

    Submission of details pursuant to Condition 7 (Anti-Vibration) of the planning permission reference: 2024/02201/FUL dated 24th September 2025.

    18 Jun 2026 Conditions
  • 3 Shortlands, London, W6 8DA

    Submission of details of secured by design pursuant to condition 31 of planning permission ref: 2025/01723/FUL granted 1st July 2026.

    7 Jul 2026 Conditions
  • 11 Farm Lane, London, SW6 1PU

    Submission of details of a post installation compliance report of the approved ventilation strategy, pursuant to Condition 17 of the planning permission reference: 2022/03329/FR3 dated 19th July 2023.

    6 Jul 2026 Conditions
  • 20 Avonmore Road, London, W14 8RR

    Submission of details on the use of tall plant/scaffolding, in consultation with TFL Infrastructure Protection, pursuant to Condition 19 of planning permission reference: 2024/01752/FUL dated 10th December 2025.

    22 Jun 2026 Conditions