Planning application
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Requirement 21 (Main Development Site: Sizewell Marshes SSSI Method Statement) of the Sizewell C Development Consent Order
As published by the council, reference DC/25/4388/DRR
Application record
- Reference
- DC/25/4388/DRR
- Type
- Discharge of Requirements (56 days)
- Status
- Permitted
- Decision
- Application Permitted
- Received
- 13 Nov 2025
- Validated
- 13 Nov 2025
- Decided
- 22 Dec 2025
- Ward
- Aldeburgh And Leiston
- Parish
- Leiston Cum Sizewell
- Decision by
- Delegated Decision
Site history
Applications at this address on the East Suffolk register
This site has had 13 applications since 2024: 10 approved, 0 refused.
-
DC/26/2639/DRR42 Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Discharge of Requirements (42 days) - Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order
-
DC/26/2576/DRR Awaiting decision
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Discharge of Requirement 19 (Main development site: Marine infrastructure) - Temporary Hard Coastal Defence Feature (part of Work No. 1A(n)) of the Sizewell C Development Consent Order
-
DC/26/1777/DRR28 Awaiting decision
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Bespoke Mitigation Plan (Noise and Vibration) Temporary Construction Area (MDS BMP 7), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order
-
DC/26/0327/CON Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Consultation - Nearshore Infrastrcuture Pre-Installation Bathymetry
-
DC/26/0158/CON Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
MMO Consultation - Deemed Marine Licence condition 14(3) - Sizewell C CPMMP Notification: TMBIF Pre-installation Topography Monitoring Report
-
DC/25/4721/DRR42 Awaiting decision
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Discharge of Requirement 31 (Rail infrastructure) - Green Rail Route of the Sizewell C Development Consent Order
-
DC/25/4674/CON Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Consultation - Condition Coastal Processes Monitoring and Mitigation Plan monitoring reports - DML condition 14(3)
-
DC/25/4283/CCC Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
County Council Consultation - Discharge of Requirement 10 project wide: Public Rights Of Way implementation plan for coast path (MBIF) in respect of SZC Co. Sizewell C Nuclear Power Station
-
DC/25/2644/DRR28 Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Bespoke Mitigation Plan (Noise and Vibration) - Sizewell Link Road Main Works (AD BMP 16), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order
-
DC/25/2407/DRR Granted
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Development Consent Order Requirement 21 - Main development site: Sizewell Marshes SSSI Method Statements (Partial Discharge, Methodology for SSSI Southern Abutment) of the Sizewell C Development Consent Order
Timeline
Dates from the published record
-
13 Nov 2025
Received by East Suffolk
-
22 Dec 2025
Decision issued: Application Permitted
-
9 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
8 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
East Suffolk granted permission on 22 December 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 5 (Main Development Site: Surface and Foul Water Drainage) Partial discharge for Main Development Site Roads Scheme (Work No. 1A(gg), 1A(hh), 1B and 1C) of Sizewell C Development Consent Order
Granted Conditions 22 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 5 (Project Wide: Surface and Foul Water Drainage) - Various Main Development Site Works, Phase 9
Granted Conditions 13 docs -
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Development Consent Order Requirement 21 - Main development site: Sizewell Marshes SSSI Method Statements (Partial Discharge, Methodology for SSSI Southern Abutment) of the Sizewell C Development Consent Order
Granted Conditions 10 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Consultation application - MMO-SZC-21987N - Sizewell C Temporary Marine Bulk Import Facility Construction Method Statement and associated Marine Mammal Mitigation Protocol and Southern North Sea Special Area of Conservation Site Integrity Plan, pursuant to Condition 36 of Deemed Marine Licence DCO/2013/00021
Granted Outline 6 docs -
Green Rail Route Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 31 (Rail infrastructure) - Green Rail Route of the Sizewell C Development Consent Order
Granted Conditions 12 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order
Granted Conditions 6 docs
Other condition discharge and variation applications
In East Suffolk
-
DC/26/2035/DRC Split decision
The Old Rectory The Street South Elmham St Margaret Harleston Suffolk IP20 0PJ
Discharge of Condition Nos. 4, 5, 6, 7, 10, 11, 12, 13, 14, 16, 17, 18, 19, 20, 21, 22, 23, 24, 27, 28 and 30 of DC/24/4379/LBC - Listed Building Consent - Partial Demolition, extension and internal reordering, plus conversion and repair of outbuildings - Supporting Statement and Drawings submitted
-
DC/26/2017/DRC Granted
Hand Car Wash Montrose Service Garage London Road Beccles Suffolk NR34 9YU
Discharge of Condition No. 3 of DC/25/3495/FUL - Erection of a two-storey, 66-bed care home for the elderly with associated access, parking, landscaping, and ancillary buildings, following the demolition of existing garages and associated structures - Fuel Tank and Canopy Removal
-
DC/26/3060/DRC Awaiting decision
25 Cotmer Road Lowestoft Suffolk NR33 9PN
Discharge of Condition No. 14 of DC/24/1151/FUL - Sub division of gardens to create 2 plots and construction of 2 detached bungalows with integral garages - Water Calculations
-
DC/26/2904/DRC Granted
North Suffolk Skills Academy Harrisons Lane Halesworth Suffolk IP19 8PY
Discharge of Condition No. 3 of DC/21/0007/FUL - Change of use to sports facilities comprising new grass football pitch adjacent to Harrisons Lane and construction of a new artificial football pitch with associated parking, access, lighting, acoustic fencing and drainage adjacent to the Apollo Youth Centre and adjacent field to the south - Demolition and Construction Management Strategy
-
DC/26/3028/DRR42 Awaiting decision
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Development Consent Order Requirement 9 - Main Development Site: Site Clearance of the Sizewell C Development Consent Order