County Council Consultation - Discharge of Requirement 10 project wide: Public Rights Of Way implementation plan for coast path (MBIF) in respect of SZC Co. Sizewell C Nuclear Power Station
As published by the council, reference DC/25/4283/CCC
Application record
- Reference
- DC/25/4283/CCC
- Type
- Consultation by County Council
- Status
- Responded
- Decision
- No Objections
- Received
- 6 Nov 2025
- Validated
- 6 Nov 2025
- Decided
- 18 Nov 2025
- Ward
- Aldeburgh And Leiston
- Parish
- Leiston Cum Sizewell
- Decision by
- Delegated Decision
Timeline
Dates from the published record
-
6 Nov 2025
Received by East Suffolk
-
18 Nov 2025
Decision issued: No Objections
-
9 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
2 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Nearby applications
Within 500 metres
-
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 13 (Main development site: Temporary construction-related development) of the Sizewell C Development Consent Order - LEEIE Revised Construction Use
Withdrawn Conditions 18 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order
Granted Conditions 6 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
99% historically approved · decision due ~28 Aug
Development Consent Order Requirement 27 - Main development site: Marsh harrier of the Sizewell C Development Consent Order
Awaiting decision Conditions 5 docs -
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Consultation - Review and potential discharge relating to Condition 17(1) of the Deemed Marine Licence (DML) DCO/2013/00021. As per Condition 17(1), No licensed activity must commence until a FLCP has been submitted to and approved by the MMO in writing.
Granted Outline 4 docs -
Sizewell C And Associated Development Sites Sizewell Leiston Suffolk
99% historically approved · decision due ~27 Oct
Development Consent Order Requirement 9 - Main Development Site: Site Clearance of the Sizewell C Development Consent Order
Awaiting decision Conditions 2 docs -
Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk
Discharge of Requirements (42 days) - Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order
Granted Conditions 6 docs
Other outline applications
In East Suffolk
-
DC/26/2769/EIA Decided
Land Off Ringsfield Road Beccles Suffolk
EIA Screening Opinion - Residential development of up to 270 dwellings, together with public open space, suitable alternative natural greenspace (SANG) and associated infrastructure.
-
DC/26/2834/CON Granted
Land To South Of Railway Line Westerfield Road Ipswich Suffolk
Consultation - Part discharge of condition 28 of outline planning permission IP/14/00638/OUTFL in relation to the Community Development Strategy and the full details of projects and measures for the pre-occupancy and early occupancy phase.
-
DC/26/3025/CON Awaiting decision
The Crown Hotel Market Hill Framlingham Woodbridge Suffolk IP13 9AP
Consultation - Renewal of pavement licence for 4 tables each with 3 chairs at the front of the premises, covering an area of left of the door (when facing premises) 11m in length & 1.5m wide and right of the door 8m in length & 1.5m wide. Between the hours of 07:30-23:00 Monday to Saturday and 8:00 to 18:00 Sunday.
-
DC/26/3031/CON Awaiting decision
79 Hamilton Road Felixstowe Suffolk IP11 7BE
Consultation - Renewal of pavement licence: 6 tables and 12 chairs Area in front of premises - 6m x 3.4m Tables 1 to 4 (located on pavement) - Monday to Sunday 08:00 to 16:00 Tables 5 and 6 (located on Hamilton Road) - Monday to Sunday 10:00 to 16:00
-
DC/26/2758/CON Granted
Garland Park Garland Park Avenue Rendlesham Woodbridge Suffolk
Consultation - Variation to Advanced Water Infrastructure Networks Limited, to allow it to supply Water and Sewerage services to a site called Garland Park, Woodbridge.