Sizewell C And Associated Development Sites

Granted East Suffolk DC/25/2665/CON Other Consultation

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Consultation - Marine Environmental Monitoring Plan (MEMP), pursuant to Condition 15(1) of the Sizewell C Deemed Marine License

As published by the council, reference DC/25/2665/CON

Application record

Reference
DC/25/2665/CON
Type
Other Consultation
Status
Responded
Decision
No Objections
Received
7 Jul 2025
Validated
7 Jul 2025
Decided
1 Aug 2025
Ward
Aldeburgh And Leiston
Parish
Leiston Cum Sizewell
Decision by
Delegated Decision

Site history

Applications at this address on the East Suffolk register

This site has had 17 applications since 2024: 15 approved, 0 refused.

  • DC/26/2447/DRR Awaiting decision

    Sizewell C And Associated Development Sites

    Development Consent Order Requirement 4 - Project wide: Terrestrial ecology monitoring and mitigation plan of the Sizewell C Development Consent Order

    Submitted 7 Jul 2026 Conditions
  • DC/26/1096/DRR42 Awaiting decision

    Sizewell C And Associated Development Sites

    Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order Application Type: discharge of requirement - 42 days (/DRR)

    Submitted 20 Mar 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Yoxford Roundabout (AD BMP 13 Rev 7), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order.

    Decided 5 Mar 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Rail Works March 2026 - November 2026 (AD BMP 14 Rev 4), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Decided 26 Feb 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Northern Park and Ride (AD BMP 4 Rev 5), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Decided 27 Feb 2026 Conditions
  • Sizewell C And Associated Development Sites

    Sizewell C Deed of Obligation, Noise Mitigation Scheme - Schedule 12 Annex W: Junction South of Bramfield, Refreshed Noise Assessment

    Decided 7 Jan 2026 Conditions
  • DC/25/3731/DRR Granted

    Sizewell C And Associated Development Sites

    Discharge of Requirement 26 (Main development site: Wet woodland) - Pakenham (Work No. 18) of the Sizewell C Development Consent Order

    Decided 24 Nov 2025 Conditions
  • Sizewell C And Associated Development Sites

    Development Consent Order Requirement 30 (Accommodation campus: Buildings and Structures) of the Sizewell C Development Consent Order

    Decided 1 Sep 2025 Conditions
  • DC/25/2591/CCC Granted

    Sizewell C And Associated Development Sites

    Consultation - DISCHARGE OF REQUIREMENT 23 MAIN DEVELOPMENT SITE HIGHWAY WORKS NO. 1C (LEISTON DRAIN BRIDLEWAY BRIDGE) IN RESPECT OF SZC Co. SIZEWELL C NUCLEAR POWER STATION

    Decided 29 Sep 2025 Outline
  • DC/25/2580/DRR Granted

    Sizewell C And Associated Development Sites

    Discharge of Requirement 5 (Project wide: Surface and Foul Water Drainage) Partial discharge for Southern Park and Ride (Work No. 10) of Sizewell C Development Consent Order

    Decided 1 Sep 2025 Conditions

Timeline

Dates from the published record

  1. 7 Jul 2025

    Received by East Suffolk

  2. 1 Aug 2025

    Decision issued: No Objections

  3. 2 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

East Suffolk granted permission on 1 August 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Sizewell C And Associated Development Sites

    DC/24/2929/CON Submitted 14 Aug 2024 0m away

    Consultation - Initial Programme of Works to the MMO for it's review and potential discharge relating to Condition 7(1) of the Deemed Marine Licence (DML).

    Granted Outline 3 docs
  • Sizewell C And Associated Development Sites Saxmundham To Leiston Branch Line And New Green Rail Route Leiston Suffolk

    DC/25/3244/DRR28 Submitted 20 Aug 2025 69m away

    Bespoke Mitigation Plan (Noise and Vibration) Rail Works September 2025 - February 2026 (AD BMP 14 - updated), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Granted Conditions 7 docs
  • Proposed Sizewell C Sizewell Power Station Road Sizewell Leiston Suffolk

    DC/25/4721/DRR42 Submitted 4 Dec 2025 77m away

    99% historically approved · decision due ~29 Jan

    Discharge of Requirement 31 (Rail infrastructure) - Green Rail Route of the Sizewell C Development Consent Order

    Awaiting decision Conditions 5 docs
  • Sizewell C And Associated Development Sites

    DC/25/2591/CCC Submitted 30 Jun 2025 82m away

    Consultation - DISCHARGE OF REQUIREMENT 23 MAIN DEVELOPMENT SITE HIGHWAY WORKS NO. 1C (LEISTON DRAIN BRIDLEWAY BRIDGE) IN RESPECT OF SZC Co. SIZEWELL C NUCLEAR POWER STATION

    Granted Outline 2 docs
  • Sizewell C And Associated Development Sites

    DC/25/2580/DRR Submitted 30 Jun 2025 82m away

    Discharge of Requirement 5 (Project wide: Surface and Foul Water Drainage) Partial discharge for Southern Park and Ride (Work No. 10) of Sizewell C Development Consent Order

    Granted Conditions 17 docs
  • Sizewell C And Associated Development Sites

    DC/26/1096/DRR42 Submitted 20 Mar 2026 82m away

    99% historically approved · decision due ~15 May

    Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order Application Type: discharge of requirement - 42 days (/DRR)

    Awaiting decision Conditions 5 docs

In East Suffolk

  • DC/26/3197/EIA Awaiting decision

    Part Land South East Of Grimseys Lane Leiston Suffolk

    EIA Screening Opinion - Reservoir Extension to Sizewell Estate

    10 Sep 2026 Outline
  • DC/26/2832/CON Granted

    Land To North Of Railway Line Henley Road Ipswich Suffolk

    Consultation - Submission of Reserved Matters (appearance, layout, landscaping, and scale) for part of Phase 4a and Phase 4b (Part of Phase 5 of approved Phasing Strategy) of the development at Henley Gate comprising 121 dwellings, roads, parking, open space, landscaping, drainage, and other associated works; pursuant to Outline Planning Permission IP/16/00608/OUT comprising up to 1,100 dwellings, local centre, country park, open space, sustainable urban drainage systems, access points from Henley Road and associated engineering works. IP/16/00608/OUT was an EIA development and an Environmental Statement was submitted with the application under the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 2011 (as amended).

    10 Aug 2026 Outline
  • DC/26/3120/CON Awaiting decision

    Suffolk Water Recycling Transfer And Storage Project Suffolk

    Consultation - Request for Scoping Opinion under Regulation 10 of The Infrastructure Planning (Environmental Impact Assessment) Regulations 2017 and Regulation 13 of The Marine Works (Environmental Impact Assessment) Regulations 2007 (as amended in 2017)

    4 Sep 2026 Outline
  • DC/26/2886/CON Granted

    Land At Silverlace Green Benhall Suffolk IP17 1JH

    Consultation - To facilitate a new connection it has become necessary for Eastern Power Networks plc to upgrade the existing pole mounted transformer to 50kVa.

    13 Aug 2026 Outline
  • DC/26/2965/CCC Granted

    Land At Foxburrow Farm Brightwell Suffolk

    County Council Consultation - Retrospective extension to an existing recycling facility for the importation, storage, treatment and recycling of inert waste and storage of building materials, with parking, office, storage facilities and associated infrastructure.

    21 Aug 2026 Outline