Proposal

Discharge of Requirement 26 (Main development site: Wet woodland) - Pakenham (Work No. 18) of the Sizewell C Development Consent Order

As published by the council, reference DC/25/3731/DRR

Application record

Reference
DC/25/3731/DRR
Type
Discharge of Requirements (56 days)
Status
Permitted
Decision
Application Permitted
Received
29 Sep 2025
Validated
29 Sep 2025
Decided
24 Nov 2025
Ward
Aldeburgh And Leiston
Parish
Leiston Cum Sizewell
Decision by
Delegated Decision

Site history

Applications at this address on the East Suffolk register

This site has had 17 applications since 2024: 15 approved, 0 refused.

  • DC/26/2447/DRR Awaiting decision

    Sizewell C And Associated Development Sites

    Development Consent Order Requirement 4 - Project wide: Terrestrial ecology monitoring and mitigation plan of the Sizewell C Development Consent Order

    Submitted 7 Jul 2026 Conditions
  • DC/26/1096/DRR42 Awaiting decision

    Sizewell C And Associated Development Sites

    Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order Application Type: discharge of requirement - 42 days (/DRR)

    Submitted 20 Mar 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Yoxford Roundabout (AD BMP 13 Rev 7), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order.

    Decided 5 Mar 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Rail Works March 2026 - November 2026 (AD BMP 14 Rev 4), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Decided 26 Feb 2026 Conditions
  • Sizewell C And Associated Development Sites

    Bespoke Mitigation Plan (Noise and Vibration) Northern Park and Ride (AD BMP 4 Rev 5), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Decided 27 Feb 2026 Conditions
  • Sizewell C And Associated Development Sites

    Sizewell C Deed of Obligation, Noise Mitigation Scheme - Schedule 12 Annex W: Junction South of Bramfield, Refreshed Noise Assessment

    Decided 7 Jan 2026 Conditions
  • Sizewell C And Associated Development Sites

    Development Consent Order Requirement 30 (Accommodation campus: Buildings and Structures) of the Sizewell C Development Consent Order

    Decided 1 Sep 2025 Conditions
  • DC/25/2665/CON Granted

    Sizewell C And Associated Development Sites

    Consultation - Marine Environmental Monitoring Plan (MEMP), pursuant to Condition 15(1) of the Sizewell C Deemed Marine License

    Decided 1 Aug 2025 Outline
  • DC/25/2591/CCC Granted

    Sizewell C And Associated Development Sites

    Consultation - DISCHARGE OF REQUIREMENT 23 MAIN DEVELOPMENT SITE HIGHWAY WORKS NO. 1C (LEISTON DRAIN BRIDLEWAY BRIDGE) IN RESPECT OF SZC Co. SIZEWELL C NUCLEAR POWER STATION

    Decided 29 Sep 2025 Outline
  • DC/25/2580/DRR Granted

    Sizewell C And Associated Development Sites

    Discharge of Requirement 5 (Project wide: Surface and Foul Water Drainage) Partial discharge for Southern Park and Ride (Work No. 10) of Sizewell C Development Consent Order

    Decided 1 Sep 2025 Conditions

Timeline

Dates from the published record

  1. 29 Sep 2025

    Received by East Suffolk

  2. 24 Nov 2025

    Decision issued: Application Permitted

  3. 9 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

9 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

East Suffolk granted permission on 24 November 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Sizewell C And Associated Development Sites

    DC/25/2591/CCC Submitted 30 Jun 2025 0m away

    Consultation - DISCHARGE OF REQUIREMENT 23 MAIN DEVELOPMENT SITE HIGHWAY WORKS NO. 1C (LEISTON DRAIN BRIDLEWAY BRIDGE) IN RESPECT OF SZC Co. SIZEWELL C NUCLEAR POWER STATION

    Granted Outline 2 docs
  • Sizewell C And Associated Development Sites

    DC/25/2580/DRR Submitted 30 Jun 2025 0m away

    Discharge of Requirement 5 (Project wide: Surface and Foul Water Drainage) Partial discharge for Southern Park and Ride (Work No. 10) of Sizewell C Development Consent Order

    Granted Conditions 17 docs
  • Sizewell C And Associated Development Sites

    DC/26/1096/DRR42 Submitted 20 Mar 2026 0m away

    99% historically approved · decision due ~15 May

    Discharge of Requirement 9 (Main development site: Site clearance) of the Sizewell C Development Consent Order Application Type: discharge of requirement - 42 days (/DRR)

    Awaiting decision Conditions 5 docs
  • Sizewell C And Associated Development Sites

    DC/25/2516/DRR28 Submitted 24 Jun 2025 0m away

    Bespoke Mitigation Plan (Noise and Vibration) ACA/LEEIE Works (MDS BMP 6), secured by the Noise Monitoring and Management Plan under Requirement 2 (Code of Construction Practice) of the Sizewell C Development Consent Order

    Granted Conditions 7 docs
  • Sizewell C And Associated Development Sites

    DC/25/2790/DRR42 Submitted 16 Jul 2025 0m away

    Development Consent Order Requirement 30 (Accommodation campus: Buildings and Structures) of the Sizewell C Development Consent Order

    Granted Conditions 16 docs
  • Sizewell C And Associated Development Sites

    DC/25/2066/DRR Submitted 23 May 2025 0m away

    Partial Discharge of Requirement 36 Associated Developments: Highway Landscape Works - Friday Street Roundabout (Work No. 11b) of the Sizewell C Development Consent Order

    Granted Conditions 21 docs

In East Suffolk

  • DC/26/2035/DRC Split decision

    The Old Rectory The Street South Elmham St Margaret Harleston Suffolk IP20 0PJ

    Discharge of Condition Nos. 4, 5, 6, 7, 10, 11, 12, 13, 14, 16, 17, 18, 19, 20, 21, 22, 23, 24, 27, 28 and 30 of DC/24/4379/LBC - Listed Building Consent - Partial Demolition, extension and internal reordering, plus conversion and repair of outbuildings - Supporting Statement and Drawings submitted

    2 Jun 2026 Conditions
  • DC/26/2017/DRC Granted

    Hand Car Wash Montrose Service Garage London Road Beccles Suffolk NR34 9YU

    Discharge of Condition No. 3 of DC/25/3495/FUL - Erection of a two-storey, 66-bed care home for the elderly with associated access, parking, landscaping, and ancillary buildings, following the demolition of existing garages and associated structures - Fuel Tank and Canopy Removal

    1 Jun 2026 Conditions
  • DC/26/3060/DRC Awaiting decision

    25 Cotmer Road Lowestoft Suffolk NR33 9PN

    Discharge of Condition No. 14 of DC/24/1151/FUL - Sub division of gardens to create 2 plots and construction of 2 detached bungalows with integral garages - Water Calculations

    28 Aug 2026 Conditions
  • DC/26/2904/DRC Granted

    North Suffolk Skills Academy Harrisons Lane Halesworth Suffolk IP19 8PY

    Discharge of Condition No. 3 of DC/21/0007/FUL - Change of use to sports facilities comprising new grass football pitch adjacent to Harrisons Lane and construction of a new artificial football pitch with associated parking, access, lighting, acoustic fencing and drainage adjacent to the Apollo Youth Centre and adjacent field to the south - Demolition and Construction Management Strategy

    14 Aug 2026 Conditions
  • DC/26/3028/DRR42 Awaiting decision

    Sizewell C And Associated Development Sites Sizewell Leiston Suffolk

    Development Consent Order Requirement 9 - Main Development Site: Site Clearance of the Sizewell C Development Consent Order

    26 Aug 2026 Conditions