Proposal
Proposed wind farm comprising of up to 6 turbines 200m in height each with a generating capacity of up to 7.2MW associated infrastructure and BESS with 20MW capacity giving a total site capacity of up to approximately 63.2 MW at
As published by the council, reference 25/00965/S36
Application record
- Reference
- 25/00965/S36
- Type
- Dealt With By Scottish Executive
- Status
- Awaiting decision
- Received
- 8 Aug 2025
- Validated
- 8 Aug 2025
- Ward
- Fochabers Lhanbryde
- Parish
- Innes
- Decision by
- Committee - Other/Scheme of Delegation
Site history
Applications at this address on the Moray register
This site has had 2 applications since 2025.
-
25/00965/S36CON Awaiting decision
Blackhills Windfarm Rothes Moray
Proposed wind farm comprising of up to 6 turbines 200m in height each with a generating capacity of up to 7.2MW associated infrastructure and BESS with 20MW capacity giving a total site capacity of up to approximately 63.2 MW at
Timeline
Dates from the published record
-
8 Aug 2025
Received by Moray
-
27 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 3 October 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Moray took a median of 82 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
152 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Moray for determination, against a statutory target of eight weeks. Over the last year Moray's median decision took 82 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Moray's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
Blackhills Windfarm Rothes Moray
96% historically approved · decision due ~3 Oct
Proposed wind farm comprising of up to 6 turbines 200m in height each with a generating capacity of up to 7.2MW associated infrastructure and BESS with 20MW capacity giving a total site capacity of up to approximately 63.2 MW at
Awaiting decision 152 docs