How long planning decisions take in Moray
96 days.
In the year to December 2026, the median planning application decided by Moray took 96 days from submission to decision — 40 days beyond the eight week target. That is measured across 503 decisions where the council published both dates.
This council carries a figure but no rank
Not ranked yet: our records do not yet pass the historical coverage, monthly continuity, missing-date and refresh checks for this window. The figure above is still what the published dates say; it is left out of the league table so it cannot distort the ranking. See the methodology.
How Moray compares
Year to December 2026
Moray takes longer than the country as a whole: 39 days above the national median of 57 days. Nationally 49% of applications are decided within eight weeks; here it is 28%.
The average here is 118 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 224 days is the more useful number: nine applications in ten were decided inside it.
-
Within eight weeks the statutory target 140 28%
-
Eight to thirteen weeks the major development band 93 18%
-
Over thirteen weeks commonly an agreed extension 270 54%
The last few years
Each row is a full twelve months of decisions, ending in the quarter shown
Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.
| Twelve months to | Median days | UK rank |
|---|---|---|
| December 2024 | 78 | 54 of 57 |
By type of application
Year to December 2026 · types with at least ten decisions
The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.
-
Prior approval 43 decided 31 days
-
Heritage and listed buildings 58 decided 85 days
-
Full applications 361 decided 101 days
-
Lawful development 10 decided 111 days
-
Outline 12 decided 143 days
What Moray decides
Year to December 2026
Moray issued 503 decisions in the year to December 2026. Of the clear-cut outcomes, 97% were approvals: 448 granted against 12 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.
Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.
Common questions
How long does a planning decision take in Moray?
The median planning application decided by Moray in the year to December 2026 took 96 days from submission to decision, 40 days beyond the eight week target. That is measured across 503 decisions where the council published both a start date and a decision date.
Does Moray meet the eight week target?
28% of the 503 decisions Moray made in the year to December 2026 came within eight weeks of the application being received, and 46% within thirteen weeks. Nine in ten were decided within 224 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.
Is Moray faster or slower than average?
Moray is slower than average: its median of 96 days is 39 days above the national median of 57 days.
What proportion of applications does Moray approve?
97% of the clear-cut outcomes Moray issued in the year to December 2026 were approvals: 448 granted against 12 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.
Cite these figures
Click the text to select the whole citation.
Moray planning decision times, year to December 2026: median 96 days from application to decision (40 days beyond the eight week target), across 503 decisions with both dates published. 28% were decided within the eight week statutory target, 46% within thirteen weeks; nine in ten within 224 days. 97% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.
Or take the data itself: this council's history (CSV) or the full league table (CSV).
Embed these figures
Paste either snippet into your page. Click a snippet to select all of it. The credit line is part of the embed.
<script src="https://planindex.co.uk/embed/decision-times.js" data-council="moray" defer></script>
If your CMS strips scripts, use the frame directly:
<iframe src="https://planindex.co.uk/embed/decision-times/moray" title="Planning decision times in Moray" width="100%" height="215" loading="lazy" frameborder="0"></iframe>
<p>Data: <a href="https://planindex.co.uk/planning-decision-times/moray">Planning decision times, from PlanIndex</a></p>