Planning application
Land 2430M SW Of Loch Buidhe Bonar Bridge
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Carnaig Substation - Construction and operation of a 400kV substation and associated infrastructure, site access, and landscaping
As published by the council, reference 24/05062/FUL
Application record
- Reference
- 24/05062/FUL
- Type
- Full Application
- Status
- Under Consideration
- Received
- 4 Dec 2024
- Validated
- 13 Jan 2025
- Ward
- North, West And Central Sutherland
- Parish
- Creich Community Council
- Decision by
- Delegated Decision
Site history
Applications at this address on the Highland register
This site has had 5 applications since 2024: 1 approved, 0 refused.
-
26/00739/SCOP Decided
Land 2430M SW Of Loch Buidhe Bonar Bridge
EIA Scoping Request for the construction and operation of a new 132kV overhead line (OHL) connection between Shin Substation and a proposed cable sealing end (CSE) compound approximately 2 km west of Loch Buidhe Substation, and the dismantling of the existing 132kV OHL connection between Shin Substation and Loch Buidhe Substation
-
25/03629/SCRE Decided
Land 2430M SW Of Loch Buidhe Bonar Bridge
EIA Screening Opinion Request for the construction and operation of a new 132kV overhead line (OHL) connection between Shin Substation and a proposed cable sealing end (CSE) compound approximately 2 km west of Loch Buidhe Substation, and the dismantling of the existing 132kV OHL connection between Shin Substation and Loch Buidhe Substation
-
25/03420/FUL Granted
Land 2430M SW Of Loch Buidhe Bonar Bridge
Formation of access and 2.6km private way.
-
25/03311/S37 Decided
Land 2430M SW Of Loch Buidhe Bonar Bridge
Spittal to Beauly 400 kV OHL - Install, operate and keep installed 173km of new 400 kV overhead electricity line, supported on steel lattice tower structures, between proposed new substations at Banniskirk (ND 15905 56823) in the area of Spittal, and Fanellan (NH 48534 43208) in the area of Beauly, with a connection via a proposed new substation at Carnaig (NH 65053 97458) near to the existing substation at Loch Buidhe, in the area of Bonar Bridge; associated permanent diversion works to 18km of existing 132 kV and 275 kV overhead electricity lines, including the temporary diversion works, and ancillary development and associated works. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00006008
Timeline
Dates from the published record
-
4 Dec 2024
Received by Highland
-
13 Jan 2025
Validated
Checked as complete and ready for consideration.
-
8 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 10 March 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Highland took a median of 67 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
185 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Highland for determination, against a statutory target of eight weeks. Over the last year Highland decided full applications in a median of 71 days. More in our guide to how long planning decisions take.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Other full applications
In Highland
-
26/00375/FUL Granted
Land 160M NE Of Blairstarn 424 Clashmore Lochinver
Erection of house and garage
-
26/00373/FUL Granted
Land 360M NW Of Parkhouse Clashmore Lochinver
Erection of house for short term letting and outbuilding
-
26/03064/FUL Granted
Land 200M East Of 23 Willow Avenue Slackbuie Inverness
Erection of sprinkler pump and tank enclosure
-
25/03170/FUL Granted
Land 25M NE Of Fishers Brook Morar
Erection of house
-
26/03160/FUL Granted
Tigh-Na-Coille Nethy Bridge PH25 3DR
Erection of extension