Proposal
Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.
As published by the council, reference HGY/2026/0364
Application record
- Reference
- HGY/2026/0364
- Type
- Approval of details reserved by a condition
- Status
- Decision Made
- Decision
- Approve
- Received
- 11 Feb 2026
- Validated
- 11 Feb 2026
- Decided
- 25 Feb 2026
- Ward
- Northumberland Park
- Decision by
- Delegated Decision
- Postcode
- N17 0XD
Site history
Applications at this address on the Haringey register
This site has had 6 applications since 2025: 6 approved, 0 refused.
-
HGY/2026/2044 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601
-
HGY/2026/1744 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 13 (CEMP) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1712 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/0019 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2025/2787 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.
Timeline
Dates from the published record
-
11 Feb 2026
Received by Haringey
-
25 Feb 2026
Decision issued: Approve
-
24 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
11 later applications on the register refer to this one:
-
HGY/2026/2409 Awaiting decision
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirements 10 (Surface Water) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/2043 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirements 13 (CEMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/2044 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601
-
HGY/2026/1911 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval in part (Phase 2) of Schedule 2 Requirement 14 (Archaeology) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1873 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval in part (Phase 2) of Schedule 2 Requirement 11 (1 and 2) (Contaminated Land and Groundwater) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1749 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval in part (Phase 1) of Schedule 2 Requirement 11(3) (Contaminated Land and Groundwater - verification) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1744 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 13 (CEMP) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1712 Granted
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1497 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirement 12 (Ecology Management Plan) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1294 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirement 11 (Contaminated Land and Groundwater) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/0512 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirement 10 (Drainage) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
Documents
Plans, drawings, consultee responses and the officer's report
7 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Haringey granted permission on 25 February 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
Granted Conditions 14 docs -
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 13 (CEMP) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
Granted Conditions 9 docs -
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.
Granted Conditions 7 docs -
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
Granted Conditions 6 docs -
Tottenham Substation, Watermead Way, London, N17 0XD
Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601
Granted Conditions 8 docs -
Land to south east of, Bus Garage And Depot, Marsh Lane, London, N17 0UX
Use of land as an extension for the parking of electric buses and installation of related infrastructure.
Granted Full applications Extension 32 docs
Other condition discharge and variation applications
In Haringey
-
HGY/2025/2722 Withdrawn
47 Mount View Road, Hornsey, London, N4 4SS
Approval of details pursuant to Condition 4 (Landscaping) attached to permission: HGY/2024/2771.
-
HGY/2026/2215 Awaiting decision
1, 15, 16, 18, 23, 25, 26, 31, 32, 34 Teynton Terrace, Tottenham, London, N17 7PZ
Approval of details reserved by a condition 4 (window, door, and roof detail) to approved application HGY/2026/1938 (External repairs inclusive of roofing repairs and replacement of windows and doors)
-
HGY/2026/2496 Awaiting decision
Mayfield House, St Anns General Hospital, St Anns Road, Tottenham, London, N15 3TH
Approval of details reserved condition 34 (non-residential hours of operation) attached to Planning Permission Ref: HGY/2022/1833 dated 10 July 2023.
-
HGY/2026/2043 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirements 13 (CEMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.
-
HGY/2026/1970 Granted
Parma House, Clarendon Road Off Coburg Road, Wood Green, London, N22 6UL