Tottenham Substation, Watermead Way, London, N17 0SG

Granted Haringey Approval of details reserved by a condition

Proposal

Approval of Schedule 2 Requirement 11 (Contaminated Land and Groundwater) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

As published by the council, reference HGY/2026/1294

Timeline

Dates from the published record

  1. 8 May 2026

    Received by Haringey

  2. 28 May 2026

    Decision issued: Approve

  3. 24 Jul 2026

    Added to PlanIndex

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About conditions applications

How this application type works

This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.

More on conditions applications in our guide

Nearby applications

Within 500 metres

  • HGY/2025/3541 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 7 (Highways) & 9 (CTMP) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    24 Dec 2025 0m away Conditions
  • HGY/2026/1749 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval in part (Phase 1) of Schedule 2 Requirement 11(3) (Contaminated Land and Groundwater - verification) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    18 Jun 2026 0m away Conditions
  • HGY/2026/1911 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval in part (Phase 2) of Schedule 2 Requirement 14 (Archaeology) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    3 Jul 2026 0m away Conditions
  • HGY/2026/1873 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval in part (Phase 2) of Schedule 2 Requirement 11 (1 and 2) (Contaminated Land and Groundwater) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    3 Jul 2026 0m away Conditions
  • HGY/2025/3516 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 12 (EMS) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    18 Dec 2025 0m away Conditions
  • HGY/2026/1497 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 12 (Ecology Management Plan) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    28 May 2026 0m away Conditions

In Haringey

  • HGY/2026/1712 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    16 Jun 2026 Conditions
  • HGY/2026/1510 Granted

    10 Ellington Road, Hornsey, London, N10 3DG

    Approval of details pursuant to condition (16) contamination risk model attached to ref: HGY/2023/1406

    24 Jun 2026 Conditions
  • HGY/2026/1634 Granted

    16 Stapleton Hall Road, Hornsey, London, N4 3QD

    Details pursuant to part of Condition 4 (front garden treatment including refuse & cycle storage) of planning permission reference HGY/2024/0811 (resubmission)

    9 Jun 2026 Conditions
  • HGY/2026/1516 Granted

    Langford, Maryland Road, Wood Green, London, N22 5AR

    Approval of details reserved by a condition 7 ( Non-Road Mobile Machinery (NRMM)) attached to planning application Ref: HGY/2025/1829.

    1 Jun 2026 Conditions
  • HGY/2026/1369 Granted

    108, Vale Road, London, N4 1TD

    Approval of details reserved by a condition 13b (Solar PV arrays) attached to planning reference HGY/2022/0044

    14 May 2026 Conditions