Tottenham Substation, Watermead Way, London, N17 0SG

Granted Haringey HGY/2026/1911 Approval of details reserved by a condition

Relates to HGY/2026/0364

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Approval in part (Phase 2) of Schedule 2 Requirement 14 (Archaeology) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

As published by the council, reference HGY/2026/1911

Application record

Reference
HGY/2026/1911
Type
Approval of details reserved by a condition
Status
Decision Made
Decision
Approve
Received
3 Jul 2026
Validated
3 Jul 2026
Decided
22 Jul 2026
Ward
Northumberland Park
Decision by
Delegated Decision
Postcode
N17 0SG

Site history

Applications at this address on the Haringey register

This site has had 11 applications since 2025: 10 approved, 0 refused.

  • HGY/2026/2409 Awaiting decision

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 10 (Surface Water) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Submitted 28 Aug 2026 Conditions
  • HGY/2026/2043 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 13 (CEMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 7 Sep 2026 Conditions
  • HGY/2026/1873 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval in part (Phase 2) of Schedule 2 Requirement 11 (1 and 2) (Contaminated Land and Groundwater) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 22 Jul 2026 Conditions
  • HGY/2026/1749 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval in part (Phase 1) of Schedule 2 Requirement 11(3) (Contaminated Land and Groundwater - verification) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 8 Jul 2026 Conditions
  • HGY/2026/1497 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 12 (Ecology Management Plan) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 24 Jun 2026 Conditions
  • HGY/2026/1371 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Non material change to National Grid (North London Reinforcement Project) Development Consent Order 2014 to change the bypass of Tottenham substation from underground cabling to a new Overhead Line and transmission pylon, changes to existing proposed transmission pylon, and minor extension to the Order Limits. (Note that Haringey Council is not the decision maker for the application.)

    Submitted 13 May 2026 Outline
  • HGY/2026/1294 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 11 (Contaminated Land and Groundwater) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 28 May 2026 Conditions
  • HGY/2026/0512 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 10 (Drainage) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 9 Mar 2026 Conditions
  • HGY/2025/3541 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 7 (Highways) & 9 (CTMP) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 26 Jan 2026 Conditions
  • HGY/2025/3516 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 12 (EMS) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 10 Feb 2026 Conditions

Timeline

Dates from the published record

  1. 3 Jul 2026

    Received by Haringey

  2. 22 Jul 2026

    Decision issued: Approve

  3. 24 Jul 2026

    Added to PlanIndex

Cases linked to this one on the register

  • HGY/2026/0364 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.

    Decided 25 Feb 2026 Conditions

Documents

Plans, drawings, consultee responses and the officer's report

16 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Haringey granted permission on 22 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2026/1294 Submitted 8 May 2026 0m away

    Approval of Schedule 2 Requirement 11 (Contaminated Land and Groundwater) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 9 docs
  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2026/2043 Submitted 18 Aug 2026 0m away

    Approval of Schedule 2 Requirements 13 (CEMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 5 docs
  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2025/3541 Submitted 24 Dec 2025 0m away

    Approval of Schedule 2 Requirements 7 (Highways) & 9 (CTMP) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 7 docs
  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2026/1749 Submitted 18 Jun 2026 0m away

    Approval in part (Phase 1) of Schedule 2 Requirement 11(3) (Contaminated Land and Groundwater - verification) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 38 docs
  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2026/1873 Submitted 3 Jul 2026 0m away

    Approval in part (Phase 2) of Schedule 2 Requirement 11 (1 and 2) (Contaminated Land and Groundwater) relating to Stage 3a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 16 docs
  • Tottenham Substation, Watermead Way, London, N17 0SG

    HGY/2025/3516 Submitted 18 Dec 2025 0m away

    Approval of Schedule 2 Requirement 12 (EMS) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 9 docs

In Haringey

  • HGY/2025/2722 Withdrawn

    47 Mount View Road, Hornsey, London, N4 4SS

    Approval of details pursuant to Condition 4 (Landscaping) attached to permission: HGY/2024/2771.

    10 Oct 2025 Conditions
  • HGY/2026/2215 Awaiting decision

    1, 15, 16, 18, 23, 25, 26, 31, 32, 34 Teynton Terrace, Tottenham, London, N17 7PZ

    Approval of details reserved by a condition 4 (window, door, and roof detail) to approved application HGY/2026/1938 (External repairs inclusive of roofing repairs and replacement of windows and doors)

    8 Sep 2026 Conditions
  • HGY/2026/2496 Awaiting decision

    Mayfield House, St Anns General Hospital, St Anns Road, Tottenham, London, N15 3TH

    Approval of details reserved condition 34 (non-residential hours of operation) attached to Planning Permission Ref: HGY/2022/1833 dated 10 July 2023.

    8 Sep 2026 Conditions
  • HGY/2026/2043 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 13 (CEMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    18 Aug 2026 Conditions
  • HGY/2026/1970 Granted

    Parma House, Clarendon Road Off Coburg Road, Wood Green, London, N22 6UL

    Approval of details pursuant to Condition 3 (balcony, window, and external door details) of planning permission ref. HGY/2025/3439, granted on 4 February 2026, for alterations to the building façades to incorporate balconies on the exterior of the building.

    13 Jul 2026 Conditions