Planning application

Tottenham Substation, Watermead Way, London, N17 0XD

Granted Haringey HGY/2025/2787 Approval of details reserved by a condition

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.

As published by the council, reference HGY/2025/2787

Application record

Reference
HGY/2025/2787
Type
Approval of details reserved by a condition
Status
Decision Made
Decision
Approve
Received
6 Nov 2025
Validated
6 Nov 2025
Decided
21 Nov 2025
Ward
Northumberland Park
Decision by
Delegated Decision
Postcode
N17 0XD

Site history

Applications at this address on the Haringey register

This site has had 6 applications since 2025: 6 approved, 0 refused.

  • HGY/2026/2044 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601

    Decided 29 Jul 2026 Conditions
  • HGY/2026/1744 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirement 13 (CEMP) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 22 Jul 2026 Conditions
  • HGY/2026/1712 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 29 Jul 2026 Conditions
  • HGY/2026/0364 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.

    Decided 25 Feb 2026 Conditions
  • HGY/2026/0019 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 28 Jan 2026 Conditions

Timeline

Dates from the published record

  1. 6 Nov 2025

    Received by Haringey

  2. 21 Nov 2025

    Decision issued: Approve

  3. 10 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

3 later applications on the register refer to this one:

  • HGY/2026/0019 Granted

    Tottenham Substation, Watermead Way, London, N17 0XD

    Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 28 Jan 2026 Conditions
  • HGY/2025/3541 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirements 7 (Highways) & 9 (CTMP) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 26 Jan 2026 Conditions
  • HGY/2025/3516 Granted

    Tottenham Substation, Watermead Way, London, N17 0SG

    Approval of Schedule 2 Requirement 12 (EMS) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Decided 10 Feb 2026 Conditions

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Haringey granted permission on 21 November 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Tottenham Substation, Watermead Way, London, N17 0XD

    HGY/2026/1712 Submitted 16 Jun 2026 0m away

    Approval of Schedule 2 Requirements 7 (Highway Access) and 9 (CTMP) relating to Stage 4a (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 14 docs
  • Tottenham Substation, Watermead Way, London, N17 0XD

    HGY/2026/1744 Submitted 18 Jun 2026 0m away

    Approval of Schedule 2 Requirement 13 (CEMP) relating to Stage 5h (as approved under HGY/2026/0364), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 9 docs
  • Tottenham Substation, Watermead Way, London, N17 0XD

    HGY/2026/0364 Submitted 11 Feb 2026 0m away

    Approval of Requirement 3 (Stages of authorised development) of the North London Reinforcement Order 2014 (The Order) attached to development consent order HGY/2014/3601 to account for amending staging plan.

    Granted Conditions 7 docs
  • Tottenham Substation, Watermead Way, London, N17 0XD

    HGY/2026/0019 Submitted 8 Jan 2026 0m away

    Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 5h (as approved under HGY/2025/2787), of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601.

    Granted Conditions 6 docs
  • Tottenham Substation, Watermead Way, London, N17 0XD

    HGY/2026/2044 Submitted 20 Jul 2026 0m away

    Approval of Schedule 2 Requirement 14 (Archaeology) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601

    Granted Conditions 8 docs
  • Land to south east of, Bus Garage And Depot, Marsh Lane, London, N17 0UX

    HGY/2021/2774 Submitted 23 Sep 2021 264m away

    Use of land as an extension for the parking of electric buses and installation of related infrastructure.

    Granted Full applications Extension 32 docs

In Haringey

  • HGY/2026/1979 Awaiting decision

    Ground Floor Flat, 29 Ferme Park Road, Hornsey, London, N4 4EB

    Approval of details reserved by condition 3 (CMP) attached to permission ref: HGY/2025/2196

    4 Sep 2026 Conditions
  • HGY/2026/0592 Granted

    810-812 High Road, Tottenham, London, N17 0DH

    Submission of details for the discharge of Condition 5 (Landscaping) attached to Planning Permission HGY/2017/1181 approved on 08/06/2017, in relation to 810-812 High Road, Tottenham, N17

    3 Mar 2026 Conditions
  • HGY/2026/2388 Awaiting decision

    8 Middle Lane, Hornsey, London, N8 8PL

    Approval of details reserved by of Condition 3 (materials) and condition 4 (Construction management) attached to planning permission ref: HGY/2025/2512

    31 Aug 2026 Conditions
  • HGY/2026/1392 Granted

    Civic Centre, High Road, Wood Green, London, N22 9SB

    Approval of details reserved by condition 7b (Ceiling cross section) of Listed Building Consent HGY/2023/1044 for "the refurbishment and extension of the Civic Centre"

    15 May 2026 Conditions
  • HGY/2026/2064 Granted

    44-46, Hampstead Lane, London, N6 4LL

    Approval of details reserved condition 9 (SBD) of planning permission HGY/2022/2731 for demolition of the existing dwellings and erection of new care home (Use Class C2)

    20 Jul 2026 Conditions