Hammersmith Pumping Station Chancellors Road London W6 9RR

Granted Hammersmith and Fulham 2018/03208/TTT Thames Tideway Tunnel

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Partial discharge of Schedule 3 Requirements PW6 and HAMPS1 (Air Quality Management Plan - Phase 2) relating to compliance with the Code of Construction Practice Part A Section 7.1.2, at the worksite known as Hammersmith Pumping Station.

As published by the council, reference 2018/03208/TTT

Application record

Reference
2018/03208/TTT
Type
Thames Tideway Tunnel
Status
Application Approved
Decision
Granted As published: Application Approved
Received
1 Oct 2018
Validated
1 Oct 2018
Decided
24 Jan 2019
Ward
Fulham Reach
Decision by
Delegated Decision
Postcode
W6 9RR

Site history

Applications at this address on the Hammersmith and Fulham register

This site has had 6 applications since 2018: 3 approved, 0 refused.

  • 2020/03124/FUL Awaiting decision

    Hammersmith Pumping Station Chancellors Road London W6 9RR

    Erection of an electrical equipment kiosk at the Hammersmith Pumping Station worksite.

    Submitted 26 Nov 2020 Full applications
  • 2019/00445/TTT Granted

    Hammersmith Pumping Station Chancellors Road London W6 9RR

    Partial discharge of Schedule 3 Requirements HAMPS 6 (Specification of Access) & 8 (Detailed Design) and Full discharge of Schedule 3 Requirements HAMPS 7 (Surface Water Drainage) & 9 (Heritage Interpretation), at the worksite known as Hammersmith Pumping Station.

    Decided 26 Apr 2019
  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    Draft submission for the discharge of Requirement HAMPS 6, 7, 8 & 9 relating to the Specification of accesses (operational), Surface water drainage, Detailed design approval for permanent above ground structures and Heritage interpretation.

    Decided 30 Nov 2018
  • 2018/03156/TTT Granted

    Hammersmith Pumping Station Chancellors Road London W6 9RR

    Partial discharge of Schedule 3 Requirements PW6 and HAMPS1 (Noise and Vibration Management Plan - Phase 2) relating to compliance with the Code of Construction Practice Part A Section 6, at the worksite known as Hammersmith Pumping Station.

    Decided 17 Dec 2018
  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    Draft submission for the partial discharge of Requirement PW6 (Code of Construction Practice Part A) of Schedule 3 of the Thames Water Utilities Ltd (Thames Tideway Tunnel) Order 2014 (as amended) relating to the approval of the Noise and Vibration Management Plan at Hammersmith Pumping Station.

    Decided 19 Sep 2018

Timeline

Dates from the published record

  1. 1 Oct 2018

    Received by Hammersmith and Fulham

  2. 24 Jan 2019

    Decision issued: Application Approved

  3. 21 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

5 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Hammersmith and Fulham granted permission on 24 January 2019, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Hammersmith and Fulham's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    2018/03465/TTTDR Submitted 23 Oct 2018 50 yards away

    Draft submission for the discharge of Requirement HAMPS 6, 7, 8 & 9 relating to the Specification of accesses (operational), Surface water drainage, Detailed design approval for permanent above ground structures and Heritage interpretation.

    Decided 28 docs
  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    2018/03156/TTT Submitted 26 Sep 2018 50 yards away

    Partial discharge of Schedule 3 Requirements PW6 and HAMPS1 (Noise and Vibration Management Plan - Phase 2) relating to compliance with the Code of Construction Practice Part A Section 6, at the worksite known as Hammersmith Pumping Station.

    Granted 7 docs
  • Riverside Worksite Carnwath Road London

    2018/03174/TTT Submitted 26 Sep 2018 50 yards away

    Partial discharge of Schedule 3 Requirements PW6 and CARRR2 (Noise and Vibration Management Plan - Phase 2) relating to compliance with the Code of Construction Practice Part A Section 6, at the worksite known as Carnwath Road Riverside.

    Granted 4 docs
  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    2018/02629/TTTDR Submitted 17 Aug 2018 50 yards away

    Draft submission for the partial discharge of Requirement PW6 (Code of Construction Practice Part A) of Schedule 3 of the Thames Water Utilities Ltd (Thames Tideway Tunnel) Order 2014 (as amended) relating to the approval of the Noise and Vibration Management Plan at Hammersmith Pumping Station.

    Decided 4 docs
  • Hammersmith Pumping Station Chancellors Road London W6 9RR

    2020/03124/FUL Submitted 26 Nov 2020 50 yards away

    98% historically approved · decision due ~22 Jan

    Erection of an electrical equipment kiosk at the Hammersmith Pumping Station worksite.

    Awaiting decision Full applications 30 docs
  • Carnwath Road Riverside Worksite London SW6

    2019/01687/TTTDR Submitted 12 Jun 2019 50 yards away

    Partial discharge of the Schedule 3 Requirements CARRR 9 (Specification of accesses (operational)) and the FULL discharge of CARRR 1 (Detailed design approval for permanent above ground structures), CARRR 5 (Landscaping works), CARRR 10 (Surface water drainage) and CARRR 11(Lighting (Operational)).

    Decided 63 docs