Proposal

Submission of Construction Methodology and Construction Management Strategy pursuant to Condition 42 & 45 of planning permission 24/00836/FULEIA dated 28.10.2025.

As published by the council, reference 26/01551/MDC

Application record

Reference
26/01551/MDC
Status
Under Consideration
Received
30 Oct 2026
Validated
30 Oct 2026
Postcode
EC2M 3XD

Site history

Applications at this address on the City of London register

This site has had 13 applications since 2021: 8 approved, 0 refused.

  • 26/01663/PODC Awaiting decision

    99 Bishopsgate London EC2M 3XD

    Submission of Local Procurement Strategy and the Local Training Skills and Job Brokerage Strategy (Demolition) pursuant to Schedule 3 Paragraphs 2.1 and 3.2 of the Section 106 Agreement dated 27 October 2025 (Planning Application Ref: 24/00836/FULEIA).

    Submitted 16 Nov 2026
  • 26/01549/MDC Awaiting decision

    99 Bishopsgate London EC2M 3XD

    Submission of details of Site Condition and Proposed Ground Levels Plan pursuant to condition 80 of Planning Permission 24/00836/FULEIA dated 28.10.2025.

    Submitted 30 Oct 2026
  • 26/01519/NMA Awaiting decision

    99 Bishopsgate London EC2M 3XD

    Application for non-material amendments under Section 96A of the Town and Country Planning Act 1990 (as amended) to planning permission 24/00836/FULEIA (dated 28.10.2025) for the following works: (a) Amendment to condition 99 (Approved Drawings) for design changes including (i) adjustment to building location within the site (ii) changes to exit locations at ground level and associated alteration to City Market floorspace (iii) increase in height of cycle hub roof by 1.4m (iv) increase in height of main building by 400mm (v) removal of columns at ground floor (vi) introduction of new public route (vii) façade changes to structural beams, and (viii) other associated works; (b) Amendment to Description of Development to reflect proposed phasing of the development; (c) Introduction of new condition related to phasing of the development; (d) Amendment to Condition 3 (Servicing Bay Headroom) to reduce the headroom to 3.7m; (e) Amendment to Condition 61 (Building Height) to accommodate changes; (f) Amendment to Condition 87 (Fire Strategy) to update the document reference; (g) Amendment to Condition 88 (Approved Floorspace) to reflect the changes; and (h) Associated amendments to conditions 17, 20, 21, 22, 29, 34, 36, 37, 39, 40, 44, 45, 46, 48, 50, 52, 59, 73, 77, 78, 79, 80, 81, 82, 93, 94, and 95 to reflect the above changes.

    Submitted 26 Oct 2026 Amendments
  • 26/01473/PODC Granted

    99 Bishopsgate London EC2M 3XD

    Submission of Highway Schedule of Condition Survey pursuant to Schedule 3 Paragraphs 6.1 of the Section 106 Agreement dated 27 October 2025 (Planning Application Ref: 24/00836/FULEIA).

    Decided 6 Nov 2026
  • 26/01201/ADVT Granted

    99 Bishopsgate London EC2M 3XD

    Installation and display of external window vinyls in relation to the National Gallery Faces of a City Exhibition.

    Decided 16 Sep 2026
  • 26/00572/MDC Granted

    99 Bishopsgate London EC2M 3XD

    Submission of details of a written scheme of investigation pursuant to condition 36 of planning permission 24/00836/FULEIA dated 28.10.2025.

    Decided 20 May 2026 Conditions
  • 26/00564/MDC Granted

    99 Bishopsgate London EC2M 3XD

    Submission of details of a Desk Based Contamination Investigation and Factual Ground Investigation Report pursuant to condition 29 of planning permission 24/00836/FULEIA dated 28.10.2025.

    Decided 29 Jun 2026
  • 26/00563/MDC Granted

    99 Bishopsgate London EC2M 3XD

    Submission of details of a Pre-demolition Audit pursuant to condition 46(a) of Planning permission 24/00836/FULEIA dated 28.10.2025.

    Decided 12 Nov 2026
  • 26/00562/MDC Awaiting decision

    99 Bishopsgate London EC2M 3XD

    Submission of details of an Arboricultural Impact Assessment pursuant to condition 95 of planning permission 24/00836/FULEIA dated 28.10.2025.

    Submitted 20 Apr 2026 Conditions
  • 26/00629/PODC Granted

    99 Bishopsgate London EC2M 3XD

    Submission of Television Interference Survey and Survey Area Map pursuant to Schedule 3 Paragraphs 12.1.1 of the Section 106 Agreement dated 27 October 2025 (Planning Application Ref: 24/00836/FULEIA).

    Decided 23 Jun 2026

Timeline

Dates from the published record

  1. 30 Oct 2026

    Received by City of London

  2. 9 Nov 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 25 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    City of London took a median of 86 days over the applications it decided in the last year.

What happens while it is decided

This application is with City of London for determination, against a statutory target of eight weeks. Over the last year City of London's median decision took 86 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on City of London's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • 99 Bishopsgate London EC2M 3XD

    26/01663/PODC Submitted 16 Nov 2026 50 yards away

    99% historically approved · decision due ~11 Jan

    Submission of Local Procurement Strategy and the Local Training Skills and Job Brokerage Strategy (Demolition) pursuant to Schedule 3 Paragraphs 2.1 and 3.2 of the Section 106 Agreement dated 27 October 2025 (Planning Application Ref: 24/00836/FULEIA).

    Awaiting decision Demolition 3 docs
  • 99 Bishopsgate London EC2M 3XD

    26/01549/MDC Submitted 30 Oct 2026 50 yards away

    99% historically approved · decision due ~25 Dec

    Submission of details of Site Condition and Proposed Ground Levels Plan pursuant to condition 80 of Planning Permission 24/00836/FULEIA dated 28.10.2025.

    Awaiting decision
  • 99 Bishopsgate London EC2M 3XD

    26/01201/ADVT Submitted 20 Aug 2026 50 yards away

    Installation and display of external window vinyls in relation to the National Gallery Faces of a City Exhibition.

    Granted Windows or glazing
  • 99 Bishopsgate London EC2M 3XD

    26/00564/MDC Submitted 20 Apr 2026 50 yards away

    Submission of details of a Desk Based Contamination Investigation and Factual Ground Investigation Report pursuant to condition 29 of planning permission 24/00836/FULEIA dated 28.10.2025.

    Granted 16 docs
  • 99 Bishopsgate London EC2M 3XD

    26/00563/MDC Submitted 20 Apr 2026 50 yards away

    Submission of details of a Pre-demolition Audit pursuant to condition 46(a) of Planning permission 24/00836/FULEIA dated 28.10.2025.

    Granted Demolition 3 docs
  • 99 Bishopsgate London EC2M 3XD

    26/00629/PODC Submitted 17 Apr 2026 50 yards away

    Submission of Television Interference Survey and Survey Area Map pursuant to Schedule 3 Paragraphs 12.1.1 of the Section 106 Agreement dated 27 October 2025 (Planning Application Ref: 24/00836/FULEIA).