140 Aldersgate Street London EC1A 4HY

Awaiting decision City of London 26/00748/FULMAJ

Works: Extension Demolition

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Extensions to the existing building, involving the partial demolition and construction at Levels 7 and 8 to provide additional office floorspace (Use Class E (g)(i)), including alterations to the external amenity terrace at Level 3, new rooftop plant, alterations to the lower levels including the provision of retail (Use Class E (a/b)) at ground floor level and flexible office / retail floorspace (Class E (a/b/g(i)) at lower ground floor level (basement 1), relocation of the primary building entrance, elevational alterations, re-provision of a public toilet and all associated works.

As published by the council, reference 26/00748/FULMAJ

Application record

Reference
26/00748/FULMAJ
Status
Under Consideration
Received
22 May 2026
Validated
29 May 2026
Ward
Farringdon Within
Decision by
Delegated
Postcode
EC1A 4HY

Timeline

Dates from the published record

  1. 22 May 2026

    Received by City of London

  2. 29 May 2026

    Validated

    Checked as complete and ready for consideration.

  3. 24 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 24 July 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    City of London took a median of 78 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

DP9 Ltd Agent

Active · incorporated 2004

2,250 applications on PlanIndex · across 36 councils · 98% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

140A Investments S.Á.R.L Applicant

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

142 documents on file for this application

  • ARBORICULTURAL DEVELOPMENT STATEMENT Other · 24 Aug 2026
  • ABORICULTURAL DEVELOPMENT STATEMENT Accompanying report · 10 Aug 2026
  • SUPPLEMENTARY DLSL RESULTS Other · 03 Aug 2026
  • BUILDING LOADS DIFFERENTIAL Other · 29 Jul 2026
  • INDEPENDENT REVIEW OF DAYLIGHT AND SUNLIGHT ASSESSMENT Accompanying letters · 21 Jul 2026
  • PROPOSED WEST ELEVATION Drawing · 09 Jul 2026
  • PROPOSED PLAN LEVEL 00 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 01 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 02 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 03 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 04 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 05 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 06 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 07 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL 08 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL B1 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL B2 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL R1 Drawing · 06 Jul 2026
  • PROPOSED PLAN LEVEL R2 Drawing · 06 Jul 2026
  • REPRESENTATION - GEORGIA HOUSE Public Comment · 05 Jul 2026
  • COMMENTS - TRANSPORT FOR LONDON Consultee Comment · 02 Jul 2026
  • AIR QUALITY ASSESSMENT Accompanying report · 24 Jun 2026
  • PROPOSED PLAN - LEVEL 00 Superseded drawing · 23 Jun 2026
  • COMMENTS - TRANSPORT FOR LONDON Consultee Comment · 19 Jun 2026
  • INDOOR AIR QUALITY PLAN Accompanying report · 11 Jun 2026
  • WIND MICROCLIMATE - WINDIEST SEASON Accompanying report · 09 Jun 2026
  • COMMENTS - THAMES WATER Consultee Comment · 08 Jun 2026
  • COMMENTS - HISTORIC ENGLAND Consultee Comment · 05 Jun 2026
  • COMMENTS - TFL Consultee Comment · 05 Jun 2026
  • COMMENTS - HISTORIC ENGLAND Consultee Comment · 04 Jun 2026
  • SUPERSEDED GA WEST ELEVATION Superseded drawing · 29 May 2026
  • DESIGN & ACCESS STATEMENT - CHAPTER 01 Report - Design & Access Statement/Report · 29 May 2026
  • DESIGN & ACCESS STATEMENT - CHAPTER 16 Report - Design & Access Statement/Report · 29 May 2026
  • LIGHTING STRATEGY Accompanying report · 29 May 2026
  • 140 ALDERSGATE COVER LETTER Cover Letter · 22 May 2026
  • 140 ALDERSGATE ACOUSTIC REPORT Report - Acoustic/Noise Report · 22 May 2026
  • 140 ALDERSGATE CIL FORM 1 Other · 22 May 2026
  • 140 ALDERSGATE CMP PART 1 Accompanying report · 22 May 2026
  • 140 ALDERSGATE CMP PART 2 Accompanying report · 22 May 2026
  • 140 ALDERSGATE CMP PART 3 Accompanying report · 22 May 2026
  • 140 ALDERSGATE FIRE STATEMENT Other · 22 May 2026
  • 140 ALDERSGATE FLOOD RISK ASSESSMENT Accompanying report · 22 May 2026
  • 140 ALDERSGATE DSMP Report - Transport Statement/Report · 22 May 2026
  • 140 ALDERSGATE ECOLOGY APPRAISAL Accompanying report · 22 May 2026
  • 140 ALDERSGATE EQUALITY IMPACT ASSESSMENT Accompanying report · 22 May 2026
  • 140 ALDERSGATE DRAINAGE REPORT Accompanying report · 22 May 2026
  • 140 ALDERSGATE DLSL REPORT Accompanying report · 22 May 2026
  • 140 ALDERSGATE PS APPENDIX 2 PLANNING POLICY AUDIT. Report - Planning Statement/Report · 22 May 2026
  • 140 ALDERSGATE HEALTH IMPACT ASSESSMENT Accompanying report · 22 May 2026
  • 140 ALDERSGATE HTVIA LR _PART 1 OF 2 Accompanying report · 22 May 2026
  • 140 ALDERSGATE HTVIA LR _PART 2 OF 2 Accompanying report · 22 May 2026
  • 140 ALDERSGATE TRANSPORT ASSESSMENT PART 2 Report - Transport Statement/Report · 22 May 2026
  • 140 ALDERSGATE TRANSPORT ASSESSMENT PART 3 Report - Transport Statement/Report · 22 May 2026
  • 140 ALDERSGATE TRAVEL PLAN - PART 1 OF 3 Report - Travel Plan · 22 May 2026
  • 140 ALDERSGATE TRAVEL PLAN - PART 2 OF 3 Report - Travel Plan · 22 May 2026
  • 140 ALDERSGATE TRAVEL PLAN - PART 3 OF 3 Report - Travel Plan · 22 May 2026
  • 140 ALDERSGATE WLCA REPORT Accompanying report · 22 May 2026
  • 140 ALDERSGATE CES PART 1 Accompanying report · 22 May 2026
  • 140 ALDERSGATE CES PART 2 Accompanying report · 22 May 2026
  • 140 ALDERSGATE SUSTAINABILITY STMNT Accompanying report · 22 May 2026
  • LVL 3 LANDSCAPE PLAN Other · 22 May 2026
  • ROOF LANDSCAPE PLAN Other · 22 May 2026
  • 140 ALDERSGATE UGF CALCULATOR Other · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 08 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL B1 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 00 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 00 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 02 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 02 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 02 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 03 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 03 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 03 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 04 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 04 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 04 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 05 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 05 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 05 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 06 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 06 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 06 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 07 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 07 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 07 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL 08 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 08 Drawing · 22 May 2026
  • EXISTING PLAN - LEVEL B1 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL B1 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL B2 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL B2 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL B2 Drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL R1 Superseded drawing · 22 May 2026
  • PROPOSED PLAN - LEVEL R2 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL RF Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL RF Drawing · 22 May 2026
  • GA EAST ELEVATION Drawing · 22 May 2026
  • EXISTING EAST ELEVATION Drawing · 22 May 2026
  • DECONSTRUCTION EAST ELEVATION Drawing · 22 May 2026
  • GA NORTH ELEVATION Drawing · 22 May 2026
  • EXISTING NORTH ELEVATION Drawing · 22 May 2026
  • DECONSTRUCTION NORTH ELEVATION Drawing · 22 May 2026
  • EXISTING WEST ELEVATION Drawing · 22 May 2026
  • DECONSTRUCTION WEST ELEVATION Drawing · 22 May 2026
  • GA SECTION AA Drawing · 22 May 2026
  • EXISTING SECTION AA Drawing · 22 May 2026
  • DECONSTRUCTION SECTION AA Drawing · 22 May 2026
  • GA SECTION BB Drawing · 22 May 2026
  • EXISTING SECTION BB Drawing · 22 May 2026
  • DECONSTRUCTION SECTION BB Drawing · 22 May 2026
  • GA SECTION CC Drawing · 22 May 2026
  • EXISTING SECTION CC Drawing · 22 May 2026
  • DECONSTRUCTION SECTION CC Drawing · 22 May 2026
  • 140ALD-GEN-XX-XX-L-A-DIR000 Drawings Schedule · 22 May 2026
  • 140ALD-GEN-ZZ-00-D-A-020110 Site Plan · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 02 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 04 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 05 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 06 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 07 (PART 1 OF 3) Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 07 (PART 2 OF 3) Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 07 (PART 3 OF 3) Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 08 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 09 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 10 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 12 (PART 2 OF 2) Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 13 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 14 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 15 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 03_COMPRESSED Report - Design & Access Statement/Report · 22 May 2026
  • APPLICATIONFORMREDACTED Application Form · 22 May 2026
  • 140 ALDERSGATE PLANNING STATEMENT Report - Planning Statement/Report · 22 May 2026
  • 140 ALDERSGATE SCI Other · 22 May 2026
  • 140 ALDERSGATE UTILITIES STATEMENT Accompanying report · 22 May 2026
  • 140 ALDERSGATE WIND MICROCLIMATE ASSESSMENT Accompanying report · 22 May 2026
  • 140 ALDERSGATE TRANSPORT ASSESSMENT PART 1 Report - Transport Statement/Report · 22 May 2026
  • KEY LOCATION PLAN Site Plan · 22 May 2026
  • PROPOSED PLAN - LEVEL 01 Superseded drawing · 22 May 2026
  • EXISTING PLAN - LEVEL 01 Drawing · 22 May 2026
  • DECONSTRUCTION PLAN - LEVEL 01 Drawing · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 11 Report - Design & Access Statement/Report · 22 May 2026
  • 260515_GENSLER_DESIGNACCESSSTATEMENT_CHAPTER 12 (PART 1 OF 2) Report - Design & Access Statement/Report · 22 May 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with City of London for determination, against a statutory target of eight weeks. Over the last year City of London's median decision took 78 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on City of London's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Retail Unit 1 140 Aldersgate Street London EC1A 4HY

    25/00224/ADVT Submitted 11 Feb 2025 0m away

    Installation and display of: (i) two internally illuminated fascia signage measuring (a) 1.83m in width and 0.25m in height at a height above ground of 2.35m and (b) 1.65m in width and 0.06m in height at a height above ground of 2.43m; and (ii) one internally illuminated projecting sign measuring 0.75m in width and 0.75m in height at a height above ground of 2.75m.

    Granted Advertising 8 docs
  • 352 Lauderdale Tower Lauderdale Place Barbican City of London EC2Y 8NA

    23/00282/LBC Submitted 16 Mar 2023 48m away

    Removal of kitchen wall and living room sliding door.

    Granted Heritage and listed buildings 4 docs
  • 253 Lauderdale Tower Barbican London EC2Y 8BY

    26/00228/LBC Submitted 11 Feb 2026 48m away

    Removal of glazing and reinstatement of external balcony.

    Granted Heritage and listed buildings Windows or glazing 8 docs
  • 341 Lauderdale Tower Barbican London EC2Y 8NA

    26/00600/LBC Submitted 23 Apr 2026 48m away

    Internal alterations including removal of non-structural partitions, reconfiguration of layout, new bathrooms and kitchen and new suspended ceiling.

    Granted Heritage and listed buildings 13 docs
  • 253 Lauderdale Tower Barbican London EC2Y 8BY

    25/01187/LBC Submitted 29 Aug 2025 48m away

    Internal alterations comprising the demolition of stud walls between living room, hallway and bedroom four in addition to sliding doors between living and dining areas to create an enlarged open plan living space & demolition and refurbishment works to the kitchen, bathroom, utility room, WC and bedrooms.

    Granted Heritage and listed buildings Demolition 9 docs
  • 401 Lauderdale Tower Barbican London EC2Y 8NA

    24/00898/LBC Submitted 20 Aug 2024 48m away

    Internal alterations including removal and replacement of internal walls; refitting the kitchen, utility room, bathroom and ensuite shower room; removal and replacement of existing internal doors and frames with full height doors and frames; installation of false ceiling to all areas excluding entrance hall

    Granted Heritage and listed buildings 12 docs