LAND NEAR WHITE LION, WHITLAND, SA34 0PA

Granted Carmarthenshire W/28862 Electricity Notification

Permission granted. Work must normally begin within five years of the decision or the permission lapses.

Proposal

UPGRADE 3.25KM OF EXISTING 11KV OVERHEAD LINE TO 3 X 32HDC. CONSTRUCT 1 ADDITIONAL SPAN OF 3 WIRE O/H LINE AT C (ON PLAN). RENEWING / INSTALLING ADDITIONAL / RESITING VARIOUS POLES. UPGRADE 3 PHASE AND 1 PHASE CONDUCTORS AND RUNNING ADDITIONAL CONDUCTOR FOR 3 PHASE CONNECTION FOR A NEW 3 PHASE WIND TURBINE

As published by the council, reference W/28862

Application record

Reference
W/28862
Type
Electricity Notification
Status
Decision Made
Decision
Electricity Approval
Received
5 Sep 2013
Validated
13 Sep 2013
Decided
15 Oct 2013
Ward
Laugharne Township (Historical)
Parish
Eglwyscummin
Decision by
Delegated
Postcode
SA34 0PA

Timeline

Dates from the published record

  1. 5 Sep 2013

    Received by Carmarthenshire

  2. 13 Sep 2013

    Validated

    Checked as complete and ready for consideration.

  3. 15 Oct 2013

    Decision issued: Electricity Approval

  4. 5 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

5 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Carmarthenshire granted permission on 15 October 2013, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

Nearby applications

Within 500 metres

In Carmarthenshire

  • PL/11028 Granted

    Land south of Maes Y Coed, Llanedi, Pontarddulais

    Upgrading existing 11kV overhead line to three phase

    12 Jun 2026 Other
  • PL/10861 Granted

    Land at Llwyn Jack, Llandovery

    33KV Poles Replacement

    7 May 2026 Other
  • PL/10871 Granted

    Fferm Y Graig, Nantgaredig

    Upgrading existing 11kV overhead line to three phase

    12 May 2026 Other
  • PL/10876 Granted

    Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH

    Section 37 Application for x2 new H poles and underground cabling works

    13 May 2026 Other
  • PL/10589 Withdrawn

    Land at Newcastle Emlyn

    Upgrading existing 11kV overhead line to three phase

    23 Feb 2026 Other