Planning application
PL/10589
Land at Newcastle Emlyn
Proposal
Upgrading existing 11kV overhead line to three phase
As published by the council, reference PL/10589
Timeline
Dates from the published record
-
23 Feb 2026
Received by Carmarthenshire
-
6 Mar 2026
Validated
Checked as complete and ready for consideration.
-
2 Apr 2026
Decision issued: Withdrawn
-
28 Jul 2026
Added to PlanIndex
What withdrawal means
The process from here
The applicant withdrew this application before the council decided it, so it carries no planning weight and no fee refund is automatic. Withdrawal often follows officer feedback that a refusal was likely.
The applicant is free to submit a revised application at any time, and many withdrawn schemes return in amended form, so the site is worth watching if the proposal affected you.
About other applications
How this application type works
This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.
Other other applications
In Carmarthenshire
-
PL/10861 Granted
Land at Llwyn Jack, Llandovery
33KV Poles Replacement
-
PL/10871 Granted
Fferm Y Graig, Nantgaredig
Upgrading existing 11kV overhead line to three phase
-
PL/11028 Awaiting decision
Land south of Maes Y Coed, Llanedi, Pontarddulais
Upgrading existing 11kV overhead line to three phase
-
PL/10876 Granted
Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH
Section 37 Application for x2 new H poles and underground cabling works
-
PL/10570 Granted
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase