Planning application
PL/11028
Land south of Maes Y Coed, Llanedi, Pontarddulais
Proposal
Upgrading existing 11kV overhead line to three phase
As published by the council, reference PL/11028
Timeline
Dates from the published record
-
12 Jun 2026
Received by Carmarthenshire
-
15 Jun 2026
Validated
Checked as complete and ready for consideration.
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Carmarthenshire for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About other applications
How this application type works
This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.
Other other applications
In Carmarthenshire
-
PL/10861 Granted
Land at Llwyn Jack, Llandovery
33KV Poles Replacement
-
PL/10871 Granted
Fferm Y Graig, Nantgaredig
Upgrading existing 11kV overhead line to three phase
-
PL/10876 Granted
Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH
Section 37 Application for x2 new H poles and underground cabling works
-
PL/10589 Withdrawn
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase
-
PL/10570 Granted
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase