Planning application
PL/10871
Fferm Y Graig, Nantgaredig
Proposal
Upgrading existing 11kV overhead line to three phase
As published by the council, reference PL/10871
Timeline
Dates from the published record
-
12 May 2026
Received by Carmarthenshire
-
16 Jun 2026
Decision issued: Electricity Approval
-
28 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About other applications
How this application type works
This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.
Nearby applications
Within 500 metres
-
PL/10590 Granted
Y Graig, Nantgaredig, Carmarthen, SA32 7PF
Erection of an agricultural portal framed building for storing muck and associated works
Other other applications
In Carmarthenshire
-
PL/10861 Granted
Land at Llwyn Jack, Llandovery
33KV Poles Replacement
-
PL/11028 Awaiting decision
Land south of Maes Y Coed, Llanedi, Pontarddulais
Upgrading existing 11kV overhead line to three phase
-
PL/10876 Granted
Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH
Section 37 Application for x2 new H poles and underground cabling works
-
PL/10589 Withdrawn
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase
-
PL/10570 Granted
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase