LAND AT LLETTYRYCHEN FAWR, CWM IFOR ROAD, BURRY PORT, LLANELLI, SA16 0ED

Granted Carmarthenshire S/35847 Electricity Notification

Permission granted. Work must normally begin within five years of the decision or the permission lapses.

Proposal

DISMANTLING TOWER EE8 AND CONSTRUCTING A NEW TOWER EE8 15 METERS FROM CURRENT LOCATION. TOWER EE7 TO BE REPLACED IN IT'S CURRENT LOCATION

As published by the council, reference S/35847

Application record

Reference
S/35847
Type
Electricity Notification
Status
Decision Made
Decision
Electricity Approval
Received
7 Jul 2017
Validated
19 Jul 2017
Decided
9 Aug 2017
Ward
Burry Port (Historical)
Parish
Pembrey and Burry Port Town
Decision by
Delegated
Postcode
SA16 0ED

Timeline

Dates from the published record

  1. 7 Jul 2017

    Received by Carmarthenshire

  2. 19 Jul 2017

    Validated

    Checked as complete and ready for consideration.

  3. 9 Aug 2017

    Decision issued: Electricity Approval

  4. 25 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Carmarthenshire granted permission on 9 August 2017, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

Nearby applications

Within 500 metres

In Carmarthenshire

  • PL/11028 Granted

    Land south of Maes Y Coed, Llanedi, Pontarddulais

    Upgrading existing 11kV overhead line to three phase

    12 Jun 2026 Other
  • PL/10861 Granted

    Land at Llwyn Jack, Llandovery

    33KV Poles Replacement

    7 May 2026 Other
  • PL/10871 Granted

    Fferm Y Graig, Nantgaredig

    Upgrading existing 11kV overhead line to three phase

    12 May 2026 Other
  • PL/10876 Granted

    Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH

    Section 37 Application for x2 new H poles and underground cabling works

    13 May 2026 Other
  • PL/10589 Withdrawn

    Land at Newcastle Emlyn

    Upgrading existing 11kV overhead line to three phase

    23 Feb 2026 Other