Planning application
LAND AT LLETTYRYCHEN FAWR, CWM IFOR ROAD, BURRY PORT, LLANELLI, SA16 0ED
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
DISMANTLING TOWER EE8 AND CONSTRUCTING A NEW TOWER EE8 15 METERS FROM CURRENT LOCATION. TOWER EE7 TO BE REPLACED IN IT'S CURRENT LOCATION
As published by the council, reference S/35847
Application record
- Reference
- S/35847
- Type
- Electricity Notification
- Status
- Decision Made
- Decision
- Granted As published: Electricity Approval
- Received
- 7 Jul 2017
- Validated
- 19 Jul 2017
- Decided
- 9 Aug 2017
- Ward
- Burry Port (Historical)
- Parish
- Pembrey and Burry Port Town
- Decision by
- Delegated
- Postcode
- SA16 0ED
Timeline
Dates from the published record
-
7 Jul 2017
Received by Carmarthenshire
-
19 Jul 2017
Validated
Checked as complete and ready for consideration.
-
9 Aug 2017
Decision issued: Electricity Approval
-
25 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Carmarthenshire granted permission on 9 August 2017, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
ST HELENA, BURRY PORT, GRAIG, LLANELLI, CARMS, SA16 0ED
DEMOLISH EXISTING CONSERVATORY AND REPLACE WITH 2 STOREY SIDE EXTENSION
Granted Householder Extension Demolition 7 docsSmall domestic -
BLAEN Y MOR, GRAIG, BURRY PORT, SA16 0ED
EXTENSION TO DWELLING TO INCLUDE AREA OF PREVIOUSLY BUILT GARAGE. EXTENDED BUILDING WILL HOUSE TWO ROOMS AND CAR GARAGE (PERSONAL USE)
Granted Householder Extension 5 docsDomestic -
131 DOLAU FAN ROAD, BURRY PORT, SA16 0RP
1. GROUND AND FIRST FLOOR EXTENSION TO THE NORTH-EASTERN SIDE ON SITE OF EXISTING GARAGE. 2. SMALL PORCH EXTENSION TO THE FRONT (SOUTH-EAST) OF THE PROPERTY
Granted Householder Extension 10 docsSmall domestic -
Plot 8 and 9 Dolau Fan Road, Burry Port, SA16 0RG
Non Material Amendment (to S/37798)
Granted Amendments 10 docs -
139 DOLAU FAN ROAD, BURRY PORT, CARMARTHENSHIRE, SA16 0RP
FIRST FLOOR SIDE EXTENSION
Granted Householder Extension 13 docsDomestic -
Other less common application types
In Carmarthenshire
-
PL/11028 Granted
Land south of Maes Y Coed, Llanedi, Pontarddulais
Upgrading existing 11kV overhead line to three phase
-
PL/10861 Granted
Land at Llwyn Jack, Llandovery
33KV Poles Replacement
-
PL/10871 Granted
Fferm Y Graig, Nantgaredig
Upgrading existing 11kV overhead line to three phase
-
PL/10876 Granted
Coleg Sir Gar Pibwrlwyd Campus, Pibwrlwyd Lane, Pibwrlwyd, Carmarthen, SA31 2NH
Section 37 Application for x2 new H poles and underground cabling works
-
PL/10589 Withdrawn
Land at Newcastle Emlyn
Upgrading existing 11kV overhead line to three phase