25/0536/COND

Mynydd Eglwysilan Common Bwlch Carnygelli Road Llanfabon

Decided Caerphilly Condition Discharge

Proposal

Discharge condition 11 (Construction Transport Management Plan) of planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture)

As published by the council, reference 25/0536/COND

Timeline

Dates from the published record

  1. 31 Jul 2025

    Received by Caerphilly

  2. 4 Aug 2025

    Validated

    Checked as complete and ready for consideration.

  3. 9 Sep 2025

    Decision issued: Decided - Discharge of Conditions

  4. 28 Jul 2026

    Added to PlanIndex

After the decision

The process from here

The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.

If permission was granted, work must normally begin within five years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.

About conditions applications

How this application type works

This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.

More on conditions applications in our guide

Nearby applications

Within 500 metres

  • 25/0655/NMA Granted

    Twyn Hywel Energy Park Mynydd Eglwysilan Common Bwlch Carnygelli Road Llanfabon

    Seek approval of a non material amendment to planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture) to amend the wording of Condition 28 (Television Signals) to ensure that the condition does not delay the commencement of the construction works on the site as a whole

    17 Sep 2025 0m away Amendments
  • 25/0839/NMA Awaiting decision

    Twyn Hywel Energy Park Land North-West Of Caerphilly

    Seek approval of a non material amendment to planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture) to vary the wording of condition 18 (Habitat Management Plan) to change the trigger point

    27 Nov 2025 21m away Amendments
  • 25/0842/COND Awaiting decision

    Twyn Hywel Energy Park Land North-West Of Caerphilly

    Discharge conditions 06 (CEMP) and 07 (CWMP) of planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture)

    26 Nov 2025 21m away Conditions
  • 25/0568/COND Decided

    Mynydd Eglwysilan Common Bwlch Carnygelli Road Llanfabon

    Discharge condition 17 (Details of means of access ) of planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture)

    13 Aug 2025 21m away Conditions
  • 25/0849/COND Decided

    Twyn Hywel Energy Park Land North-West Of Caerphilly

    Discharge conditions 06 (CEMP) and 07 (CWMP) of planning consent 25/0342/NCC (Vary condition 2 of 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture) to amend the approved plans to increase the rotor diameter of the wind turbines, increase the height of the on-site transformer, and enlarge the grid connection corridor)

    26 Nov 2025 21m away Conditions
  • 25/0541/NMA Granted

    Twyn Hywel Energy Park Land North-West Of Caerphilly

    Seek approval of a non material amendment to planning consent 23/0427/DNS (Construct and operate up to 14 wind turbines and associated infrastructure including: hardstanding areas to include turbine foundations, crane hardstanding and laydown/storage area with associated micrositing allowances; electrical substation and control building with underground power cables; new access route connecting onto the A472; onsite access tracks, with pipeline and watercourse crossings; borrow pit(s); anemometer mast; temporary construction and storage compound with associated lay down areas near to the Site entrance; Habitat Management Area; and offsite works to facilitate the movement of abnormal loads such as the construction of over-run areas and temporary modifications to street furniture) to amend the wording of condition 22 (Borrow Pit Restoration Plan) to allow the construction works which would not impact upon the borrow pits to commence

    4 Aug 2025 21m away Amendments

In Caerphilly

  • 26/0493/COND Awaiting decision

    Tredegar Junction Hotel Commercial Street Pontllanfraith Blackwood NP12 2JY

    Discharge condition 04 (Soft Landscaping Scheme) of planning consent 25/0814/FULL (Erect residential development consisting of 36 affordable apartments, landscaping, car parking, drainage and associated works)

    24 Jul 2026 Conditions
  • 26/0113/COND Decided

    Gwent Tertiary College - Coleg Gwent Cross Keys Campus Risca Road Crosskeys Newport NP11 7ZA

    Discharge condition 08 (Contamination - soil import testing) of planning consent 25/0088/OUT (Hybrid application for the redevelopment of Coleg Gwent, Crosskeys Campus comprising: Full planning application for Phase 1 including the construction of a three-storey teaching building and a single-storey energy centre, together with associated access, parking, and landscaping works, Outline planning application for Phases 2-4, comprising the phased demolition of existing buildings and their replacement with new buildings, along with associated access, parking and landscaping across the campus site)

    18 Feb 2026 Conditions
  • 26/0372/COND Granted

    23 Quantock Close Trenewydd Park Risca Newport NP11 6QW

    Discharge conditions 04 (GIS) and 05 (Structural calcs) of planning consent 26/0158/HH (Create hardstanding) in order to commense work

    22 May 2026 Conditions
  • 26/0474/COND Awaiting decision

    Trinant Sports And Social Club CIO Conway Road Trinant Newport NP11 3JP

    Discharge conditions 8 (Contamination - scheme to treat), 13 (Habitat Management Plan), 14 (Biodiversity Drainage Scheme), 16 (Biodiversity Strategy) and 18 (Japanese Knotweed) of planning consent 22/0718/OUT (Erect residential development along with associated infrastructure in order to facilitate improvement of the club)

    15 Jul 2026 Conditions
  • 26/0156/COND Decided

    Cilfynydd Substation Craig-evan-leyshon Common Road Llanfabon

    Discharge condition 11 (Noise Complaints) of planning consent 25/0243/FULL (Install and operate electrical infrastructure and associated infrastructure, including a grid connection)

    5 Mar 2026 Conditions