Skip to content
PlanIndex Get alerts
Menu

Planning application

Hutton Country Park Wash Road Hutton Essex

Decided Brentwood 20/01846/EIASO EIA Screening or Scoping Opinion

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Installation of a 49.9MW battery energy storage system and associated infrastructure

As published by the council, reference 20/01846/EIASO

Application record

Reference
20/01846/EIASO
Type
EIA Screening or Scoping Opinion
Status
Decided
Decision
Not EIA Development
Received
4 Dec 2020
Validated
4 Dec 2020
Decided
16 Dec 2020
Ward
Hutton East

Timeline

Dates from the published record

  1. 4 Dec 2020

    Received by Brentwood

  2. 16 Dec 2020

    Decision issued: Not EIA Development

  3. 21 Nov 2026

    Added to PlanIndex

Documents

2 documents on file for this application

A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

Working a patch? Trade sends you every new job in your area each morning. 14 days free.

After the decision

Brentwood has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Battery Energy Storage East Of Wash Road Wash Road Hutton Essex

    20/01800/FUL Submitted 15 Dec 2020 150 yards away

    Installation of a 49.9MW battery energy storage system and associated infrastructure

    Granted Full applications Drawings (5) 24 docs
  • Battery Energy Storage East Of Wash Road Wash Road Mountnessing Essex CM13 1DL

    20/01800/NON/3 Submitted 12 Sep 2022 150 yards away

    Non material amendment to application 20/01800/FUL (Installation of a 49.9MW battery energy storage system and associated infrastructure) for the amendment to the landscaping plan and an amendment to the CTMP.

    Granted Amendments 8 docs
  • Battery Energy Storage East Of Wash Road Wash Road Hutton Essex

    20/01800/NON/2 Submitted 17 May 2022 150 yards away

    Non material amendment to application 20/01800/FUL (Installation of a 49.9MW battery energy storage system and associated infrastructure) to allow for an amendment to the layout of the of the customer substation orientation and fence line amendment.

    Granted Amendments 4 docs
    Small domestic
  • Battery Energy Storage East Of Wash Road Wash Road Hutton Essex

    20/01800/COND/1 Submitted 1 Nov 2021 150 yards away

    Discharge of conditions 4 (Construction Method Statement), 5 (Scheme of hard and soft landscaping), 6 (Detailed surface water drainage scheme), 7 (Scheme to minimise the risk of offsite flooding), 8 (Detailed maintenance plan), and 11 (Details of the security systems) of application 20/01800/FUL (Installation of a 49.9MW battery energy storage system and associated infrastructure).

    Granted Conditions 12 docs
  • Battery Energy Storage East Of Wash Road Wash Road Hutton Essex

    20/01800/NON/1 Submitted 14 Feb 2022 150 yards away

    Non material amendment to application 20/01800/FUL (Installation of a 49.9MW battery energy storage system and associated infrastructure) to allow for an amendment to the number of Energy Storage System Units from 28 to 15 and reduction of transformers on site from 28 to 11 and alterations to colour from green to white/grey.

    Granted Amendments 16 docs
  • Battery Energy Storage East Of Wash Road Wash Road Hutton Essex

    20/01800/COND/2 Submitted 5 May 2022 250 yards away

    Discharge of condition 5 (Landscaping Scheme) of application 20/01800/FUL (Installation of a 49.9MW battery energy storage system and associated infrastructure)

    Granted Conditions 5 docs

In Brentwood

  • 26/00769/OUT Awaiting decision

    Land To Rear Of 1-6 Woodfield Cottages High Street Ingatestone CM4 0DY

    Outline planning application for the erection of up to 216 dwellings and provision of up to 2,000sqm gross internal floorspace of non-residential development, comprising up to 1,500sqm of community facilities within Use Class F2 and up to 500sqm of retail floorspace within Use Class E(a), with access sought for approval and appearance, landscaping, layout and scale reserved.

    8 Oct 2026 Outline
  • 26/01146/OUT Awaiting decision

    Land Adjacent To 1 Highfield Cottage Blackmore Road Blackmore CM4 0JT

    Outline planning permission for the erection of two dwellings, comprising one four-bedroom dwelling and one three-bedroom dwelling. (With matters of Access, Appearance, Landscaping, Layout and Scale to be considered).

    Received 6 Oct, published by the council 21 Nov 2026 Outline
  • 26/00755/OUT Awaiting decision

    Land At Eagle Field Ongar Road Kelvedon Hatch Essex

    Outline application for the provision of up to 49 dwellings (Class C3), including vehicular access, landscaping, public open space, drainage and associated infrastructure (Appearance, Landscaping, Layout and Scale reserved matters)

    Received 3 Jul, published by the council 8 Aug 2026 Outline
  • 21/01525/OUT Granted

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    The Outline Application is for the creation of a mixed-use garden community comprising up to 3,700 dwellings (including affordable housing), three care homes, five Gypsy & Traveller pitches, secondary school with Community Sports Hub (including indoor and outdoor sports facilities), up to three primary schools with early years provision, Employment Hub plus childrens nursery/creche, Village Centre with market square, community building, mobility hub, retail, office, healthcare, place of worship, gym, childrens nursery/creche, public house, betting shops and hot food take away units, two Neighbourhood Hubs with public space, retail, office and childrens nursery/creche and hot food take-away units, cricket ground with pavilion, football hub with changing/social facilities, two all modes accesses from Tilbury Road - modified junction with Station Road/Tilbury Road to create a sustainable corridor connection, pedestrian/cycle connection to the A127, residential and non-residential vehicle and cycle parking with electric charging facilities, Green and Blue Infrastructure including sustainable urban drainage, play areas (MUGAs, LEAPs and LAPs), mobility routes (e.g. footways, cycleways and trim trail), community growing space, orchard, Village Green, biodiversity enhancement and landscaping; noise barrier, primary and secondary electricity sub stations together with foul and surface water pumping stations, and demolition of existing clubhouse with associated parking area, driving range and wind turbine and diversion of overhead powerlines. Phased development, each phase being a separate and severable part of the development

    Received 13 Sep, published by the council 30 Aug 2026 Outline
  • 26/00242/EIASO Decided

    Brentwood Centre Doddinghurst Road Pilgrims Hatch Essex CM15 9NN

    Environmental Impact Assessment screening opinion for the redevelopment of The Brentwood Centre, including partial demolition, a new extension and external material alterations of the Brentwood Centre alongside a comprehensive redevelopment of outdoor sports facilities (including associated sports infrastructure, parking and landscaping).

    Received 21 Apr, published by the council 9 Aug 2026 Outline