Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

The Outline Application is for the creation of a mixed-use garden community comprising up to 3,700 dwellings (including affordable housing), three care homes, five Gypsy & Traveller pitches, secondary school with Community Sports Hub (including indoor and outdoor sports facilities), up to three primary schools with early years provision, Employment Hub plus childrens nursery/creche, Village Centre with market square, community building, mobility hub, retail, office, healthcare, place of worship, gym, childrens nursery/creche, public house, betting shops and hot food take away units, two Neighbourhood Hubs with public space, retail, office and childrens nursery/creche and hot food take-away units, cricket ground with pavilion, football hub with changing/social facilities, two all modes accesses from Tilbury Road - modified junction with Station Road/Tilbury Road to create a sustainable corridor connection, pedestrian/cycle connection to the A127, residential and non-residential vehicle and cycle parking with electric charging facilities, Green and Blue Infrastructure including sustainable urban drainage, play areas (MUGAs, LEAPs and LAPs), mobility routes (e.g. footways, cycleways and trim trail), community growing space, orchard, Village Green, biodiversity enhancement and landscaping; noise barrier, primary and secondary electricity sub stations together with foul and surface water pumping stations, and demolition of existing clubhouse with associated parking area, driving range and wind turbine and diversion of overhead powerlines. Phased development, each phase being a separate and severable part of the development

As published by the council, reference 21/01525/OUT

Application record

Reference
21/01525/OUT
Type
Outline Application
Status
Approved Subject to a S106 Agreement
Decision
Granted As published: Approve (Subject to Section 106)
Received
13 Sep 2021
Validated
13 Sep 2021
Decided
16 Jun 2026
Ward
Herongate, Ingrave And West Horndon
Parish
West Horndon
Decision by
Committee Decision

Site history

Applications at this address on the Brentwood register

This site has had 8 applications since 2021: 1 approved, 0 refused.

  • 26/01016/REM Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Advanced Infrastructure Works Reserved Matters Application pursuant to conditions 2 and 12 of outline planning permission 21/01525/OUT comprising: (1) detailed landscaping works, (2) access junction comprising reconfiguration of the means of access for buses, pedestrians, and cyclists, in accordance with the terms of condition 30, (3) highway infrastructure comprising mobility corridor, footways, and cycle paths, (4) drainage and utilities infrastructure.

    Submitted 10 Sep 2026 Reserved matters
  • 26/00868/MOD106 Decided

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Confirmation of Compliance of Outline Business Plan (as per requirements of paragraph 4.1 of Schedule 13 on Governance and Stewardship) from the Section 106 Agreement dated 11.06.2026 in reference to 21/01525/OUT

    Decided 11 Sep 2026
  • 21/01525/DHVCON/4 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to the requirements of pre-commencement Conditions 35 and 36 under LPA Ref: 21/01525/OUT for a Written Scheme of Investigation for Trial Trenching (within a phase) associated with the permission granted 16.06.2026

    Submitted 17 Jul 2026 Conditions
  • 26/00711/REM Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Reserved Matters Application for Advanced Infrastructure Works pursuant to requirements of conditions 2 and 12 of outline planning permission 21/01525/OUT comprising: (1) detailed landscaping works, (2) access junction comprising reconfiguration of the southern access roundabout, in accordance with the terms of condition 32, (3) highway infrastructure comprising spine road, footways, and cycle paths, (4) drainage and utilities infrastructure.

    Submitted 25 Jun 2026 Reserved matters
  • 21/01525/DHVCON/3 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to the requirements of pre-commencement Condition 15 under LPA Ref: 21/01525/OUT for a Construction Waste Management Plan (within a phase) associated with the permission granted 16.06.2026

    Submitted 23 Jun 2026 Conditions
  • 21/01525/DHVCON/2 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to pre-commencement requirements of Condition 9 under LPA Ref: 21/01525/OUT for the Site Wide Phasing and Implementation Plan associated with the permission granted 16.06.2026

    Submitted 19 Jun 2026 Conditions
  • 21/01525/DHVCON/1 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Tree works, site clearance and habitat creation to facilitate translocation of reptiles pursuant to pre-commencement requirements of Condition 11 under LPA Ref: 21/01525/OUT pertaining to implementation of Enabling Works (within a phase) associated with the outline permission granted 16.06.2026

    Submitted 19 Jun 2026 Conditions

Timeline

Dates from the published record

  1. 13 Sep 2021

    Received by Brentwood

  2. 16 Jun 2026

    Decision issued: Approve (Subject to Section 106)

  3. 30 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

7 later applications on the register refer to this one:

  • 26/01016/REM Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Advanced Infrastructure Works Reserved Matters Application pursuant to conditions 2 and 12 of outline planning permission 21/01525/OUT comprising: (1) detailed landscaping works, (2) access junction comprising reconfiguration of the means of access for buses, pedestrians, and cyclists, in accordance with the terms of condition 30, (3) highway infrastructure comprising mobility corridor, footways, and cycle paths, (4) drainage and utilities infrastructure.

    Reserved matters
  • 26/00868/MOD106 Decided

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Confirmation of Compliance of Outline Business Plan (as per requirements of paragraph 4.1 of Schedule 13 on Governance and Stewardship) from the Section 106 Agreement dated 11.06.2026 in reference to 21/01525/OUT

    Decided 11 Sep 2026
  • 21/01525/DHVCON/4 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to the requirements of pre-commencement Conditions 35 and 36 under LPA Ref: 21/01525/OUT for a Written Scheme of Investigation for Trial Trenching (within a phase) associated with the permission granted 16.06.2026

    Submitted 17 Jul 2026 Conditions
  • 26/00711/REM Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Reserved Matters Application for Advanced Infrastructure Works pursuant to requirements of conditions 2 and 12 of outline planning permission 21/01525/OUT comprising: (1) detailed landscaping works, (2) access junction comprising reconfiguration of the southern access roundabout, in accordance with the terms of condition 32, (3) highway infrastructure comprising spine road, footways, and cycle paths, (4) drainage and utilities infrastructure.

    Submitted 25 Jun 2026 Reserved matters
  • 21/01525/DHVCON/3 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to the requirements of pre-commencement Condition 15 under LPA Ref: 21/01525/OUT for a Construction Waste Management Plan (within a phase) associated with the permission granted 16.06.2026

    Submitted 23 Jun 2026 Conditions
  • 21/01525/DHVCON/2 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Approval of Details pursuant to pre-commencement requirements of Condition 9 under LPA Ref: 21/01525/OUT for the Site Wide Phasing and Implementation Plan associated with the permission granted 16.06.2026

    Submitted 19 Jun 2026 Conditions
  • 21/01525/DHVCON/1 Awaiting decision

    Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    Tree works, site clearance and habitat creation to facilitate translocation of reptiles pursuant to pre-commencement requirements of Condition 11 under LPA Ref: 21/01525/OUT pertaining to implementation of Enabling Works (within a phase) associated with the outline permission granted 16.06.2026

    Submitted 19 Jun 2026 Conditions

Who's behind it

Company information only, from the register and Companies House

Nexus Planning Ltd Agent, a planning consultancy registered in London

Active · incorporated 2013 · London

379 applications on PlanIndex · across 73 councils · 96% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

LIH Dunton Hills Ltd Applicant, registered in London

Active · incorporated 2025 · London

3 applications on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

268 documents on file for this application

  • COVER LETTER- COMMENCEMENT Supporting Documents · 17 Aug 2026
  • PART 1 Section 106/UU · 15 Jun 2026
  • PART 2 Section 106/UU · 15 Jun 2026
  • PART 3 Section 106/UU · 15 Jun 2026
  • PART 4 Section 106/UU · 15 Jun 2026
  • S106 Draft Legal Agreement · 11 May 2026
  • CANGE OF APPLICANT & AGENT DETAILS Correspondence - Public · 28 Jan 2026
  • DIANE MIDDLETON Correspondence - Public · 27 May 2025
  • ISSUE SHEET 05.02.25 Drawing · 10 Feb 2025
  • 10352-HL-16P Drawing · 10 Feb 2025
  • 10352-HL-15K Drawing · 10 Feb 2025
  • 10352-HL-14K Drawing · 10 Feb 2025
  • 10352-HL-13M Drawing · 10 Feb 2025
  • 10352-HL-12L Drawing · 10 Feb 2025
  • 10352-HL-13K STATION ROAD -A128 JUNCTION IMPROVEMENTS Drawing · 30 Jan 2025
  • 10352-HL-14J SOUTHERN SITE ACCESS Drawing · 30 Jan 2025
  • 10352-HL-15I FOOTWAY-CYCLEWAY Drawing · 30 Jan 2025
  • 10352-HL-16M A127-A128 JUNCTION IMPROVEMENTS Drawing · 30 Jan 2025
  • ISSUE SHEET 160125 Drawing · 30 Jan 2025
  • 10352-HL-12L NORTHERN SITE ACCESS. Drawing · 30 Jan 2025
  • 10352-HL-11M SITE ACCESS Drawing · 30 Jan 2025
  • REV K - 10352 HL 13 - STATION RD/A128 JUNCTION IMPROVEMENTS AND CENTRAL SITE A Drawing · 17 Jan 2025
  • REV L -10352 HL 12 - NORTHERN SITE ACCESS Drawing · 17 Jan 2025
  • REV M - 10352 HL 11 - A127/A128 JUNCTION, SITE ACCESSES AND STATION RD IMPROVEME Drawing · 17 Jan 2025
  • REV I - 10352 HL 15 - PROPOSED FOOTWAY/CYCLEWAY AND STATION RD IMPROVEMENTS Drawing · 17 Jan 2025
  • REV M - 10352 HL 16 - A127/A128 JUNCTION IMPROVEMENTS Drawing · 17 Jan 2025
  • REV J - 10352 HL 14 - SOUTHEREN SITE ACCESS Drawing · 17 Jan 2025
  • COVERING LETTER STAR PLANNING 17.07.24 Supporting Documents · 30 Jul 2024
  • 10352-HL-16 REV N A127-A128 JUNCTION IMPROVEMENTS Drawing · 25 Jul 2024
  • 10352-HL-15 REV J FOOTWAY-CYCLEWAY & STATION ROAD IMPROVEMENTS. Drawing · 25 Jul 2024
  • 10352-HL-14 REV J SOUTHERN SITE ACCESS. Drawing · 25 Jul 2024
  • 10352-HL-13 REV L STATION ROAD- A128 JUNCTION IMPROVEMENT Drawing · 25 Jul 2024
  • 10352-HL-12 REV L NORTHERN SITE ACCESS Drawing · 25 Jul 2024
  • 10352-HL-11 REV N SITE ACCESS AND JUNCTIONS IMPROVEMENTS Drawing · 25 Jul 2024
  • 101 REV G SITE LOCATION PLAN Drawing · 25 Jul 2024
  • VIABILITY REVIEW Supporting Documents · 03 Jul 2024
  • CONSILIDATED FINAL ES REVIEW REPORT Correspondence - Public · 29 Nov 2023
  • REV-H)-PARAMETER PLAN ACCESS FOR APPROVAL 29112023 Correspondence - Public · 29 Nov 2023
  • DRAWING NO. 10352-HL-12F NORTHERN SITE ACCESS FOR APPROVAL 29112023. Correspondence - Public · 29 Nov 2023
  • REV-H)-PARAMETER PLAN HEIGHTS FOR APPROVAL 29112023. Correspondence - Public · 29 Nov 2023
  • DRAWING NO. 10352-HL-14E SOUTHERN SITE ACCESS FOR APPROVAL 29112023 Correspondence - Public · 29 Nov 2023
  • REV-H)-PARAMETER PLAN LAND USE FOR APPROVAL 29112023 Correspondence - Public · 29 Nov 2023
  • DRAWING NO. 10352-HL- 13F CENTRAL SITE ACCESS FOR APPROVAL 29112023 Correspondence - Public · 29 Nov 2023
  • CARTER JONAS VIABILITY REPORT Correspondence - Public · 28 Nov 2023
  • REVISED FRAMEWORK MASTERPLAN PART 9 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 8 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 7 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 6 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 5 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 4 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 3 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 29 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 28 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 27 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 26 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 25 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 24 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 23 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 22 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 21 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 20 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 2 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 19 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 18 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 17 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 16 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 15 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 14 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 13 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 12 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 11 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 10 Supporting Documents · 31 Oct 2023
  • REVISED FRAMEWORK MASTERPLAN PART 1 Supporting Documents · 31 Oct 2023
  • ADDITIONAL INFORMATION Supporting Documents · 11 Jan 2023
  • ADDITIONAL INFORMATION NATIONAL ENGLAND Supporting Documents · 14 Dec 2022
  • THORNDON SSSI Supporting Documents · 14 Dec 2022
  • SUPLEMENTARY ENV STATEMENT - NON TECHNICAL SUMMARY Supporting Documents · 22 Sep 2022
  • SUPLEMENTARY ENV STATEMENT - APPENDIX 01.1 Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 02.1 31057-320-1-REV H Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 02.1 31057-320-2-REV H Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 02.1 320-4 REV H PARAMETER PLAN BUILDING HEIGHTS Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 02.1 31057-400 REV H ILLUSTRATIVE MASTER PLAN Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 02.2 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 03.1 ZONE OF THEORETICAL VISIBILITY Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 4.1 UPDATED TRAFFIC DATA Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 05.1 AIR QUALITY MODEL VERIFICATION Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.1 BASE NOISE LEVELS Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.2 NOISE LEVELS WITH 7.5M MITIGATION Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.3 FUTURE YEAR NOISE LEVELS WITHOUT MITIGATION Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.4 BACKGROUND NOISE ASSESSMENT Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.5 VIBRATION ASSESSMENT Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 06.6 CRTN MODELLING RESULTS Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 12.1 ARCHAEOLOGICAL DESK BASED ASSESSMENT ADDENDUM Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES APPENDIX 14.1 APPROXIMATE LOCATION OF CUMULATIVE SITES Supporting Documents · 22 Sep 2022
  • SUPPLEMENTARY ES AUG 20222 MAIN TEXT Supporting Documents · 22 Sep 2022
  • 31057-320-1-H PARAMETER PLAN 01 LAND USE Drawing · 12 Sep 2022
  • PARAMETER PLAN 02A ACCESS AND MOVEMENT Drawing · 12 Sep 2022
  • PARAMETER PLAN 03 BUILDING HEIGHTS Drawing · 12 Sep 2022
  • 60416 DHGV COVERING LETTER Supporting Documents · 12 Sep 2022
  • 31057 400 REV H ILLUSRATIVE MASTEPLAN Drawing · 12 Sep 2022
  • DH SUPPLEMENTARY ES APPENDIX 13.1 SOIL MANAGEMENT STRATEGY Drawing · 12 Sep 2022
  • DHGV STAGE 2 ES REVIEW FINAL Supporting Documents · 25 Jul 2022
  • COVERING LETTER Supporting Documents · 25 Jul 2022
  • STAGE 1 ROAD SAFETY AUDIT Supporting Documents · 11 May 2022
  • STAGE 1 RESPONSE REPORT TN18 Supporting Documents · 11 May 2022
  • 11D A127/A128 JUNCTION SITE ACCESSES AND STATION ROAD IMPROVEMENTS Drawing · 11 May 2022
  • 10352-HL-12D NORTHERN SITE ACCESS Drawing · 11 May 2022
  • 10352-HL-13D STATION ROAD/A128 JUNCTION IMPROVEMENTS AND CENTRAL SITE ACCESS Drawing · 11 May 2022
  • 14A SOUTHERN SITE ACCESS Drawing · 11 May 2022
  • 10352-HL-14D SOUTHERN SITE ACCESS Drawing · 11 May 2022
  • 10352-HL-15D PROPOSED FOOTWAY/CYLEWAY Drawing · 11 May 2022
  • 10352-HL-16D A127/A128 JUNCTION IMPROVEMENTS Drawing · 11 May 2022
  • 31057 400 REV F ILLUSTRATIVE MASTERPLAN Drawing · 25 Feb 2022
  • 31057 320-1 REV G PARAMETER PLAN 01 LAND USE Superseded Drawing · 25 Feb 2022
  • SUPPLEMENTARY ENVIRONMENTAL STATEMENT MAIN TEXT Supporting Documents · 03 Feb 2022
  • SUPPLEMENTARY ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY Supporting Documents · 03 Feb 2022
  • COVERING LETTER Supporting Documents · 24 Jan 2022
  • DESIGN AND ACCESS ADDENDUM Design and Access Statement · 24 Jan 2022
  • ILLUSTRATIVE MASTERPLAN REF 31057-400-F Superseded Drawing · 24 Jan 2022
  • PARAMETERS PLANN ACCESS AND MOVEMENT REF 31057-320-2-G Superseded Drawing · 24 Jan 2022
  • PARAMETERS PLAN BUILDING HEIGHTS REF 31057-320-4-G Drawing · 24 Jan 2022
  • PARAMETERS PLAN LAND USE REF 31057-320-1-G Superseded Drawing · 24 Jan 2022
  • SCHOOL SITE COMPLIANCE STATEMENT Supporting Documents · 24 Jan 2022
  • SES APPENDIX 1.1 REGULATION 25 REQUEST Supporting Documents · 24 Jan 2022
  • SES APPENDIX 2.1 UPDATED KEY PLANS Drawing · 24 Jan 2022
  • SES APPENDIX 2.2 CEMP Supporting Documents · 24 Jan 2022
  • SES APPENDIX 3.1 ZONE OF THEORETICAL VISABILITY Drawing · 24 Jan 2022
  • SES APPENDIX 4.1 UPDATED TRAFFIC DATA Supporting Documents · 24 Jan 2022
  • SES APPENDIX 6.1 BASE NOISE LEVELS Drawing · 24 Jan 2022
  • SES APPENDIX 6.2 NOISE LEVELS WITH 7.5M MITIGATION Drawing · 24 Jan 2022
  • SES APPENDIX 6.3 FUTURE YEAR NOISE LEVELS WITHOUT MITIGATION Drawing · 24 Jan 2022
  • SES APPENDIX 6.4 BACKGROUND NOISE ASSESSMENT Supporting Documents · 24 Jan 2022
  • SES APPENDIX 6.5 VIBRATION ASSESSMENT Supporting Documents · 24 Jan 2022
  • SES APPENDIX 8.2 DESIGNATED SITES IMPACT ASSESSMENT Supporting Documents · 24 Jan 2022
  • SES APPENDIX 12.1 ARCHAEOLOGICAL DBA ADDENDUM Supporting Documents · 24 Jan 2022
  • SES APPENDIX 13.1 SOIL MANAGEMENT STRATEGY Supporting Documents · 24 Jan 2022
  • SES APPENDIX 14.1 APPROXIMATE LOCATION OF CUMULATIVE SITES Supporting Documents · 24 Jan 2022
  • SUPPLEMENTARY ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY Supporting Documents · 24 Jan 2022
  • ENVIRONMENTAL IMPACT ASSESSMENT REVIEW Supporting Documents · 20 Dec 2021
  • SPORT ENGLAND MODEL PLANNING CONDITIONS Supporting Documents · 20 Oct 2021
  • ES VOL2 APPX C1 KEY PLANS PART 1 Drawing · 02 Sep 2021
  • ES VOL2 APPX C1 KEY PLANS PART 2.1 Drawing · 02 Sep 2021
  • ES VOL2 APPX C1 KEY PLANS PART 2.2 Drawing · 02 Sep 2021
  • ES VOL2 APPX C1 KEY PLANS PART 2.3 Drawing · 02 Sep 2021
  • ES VOL2 APPX C2 WASTE MANAGEMENT STRATEGY Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX C4 SUSTAINABILITY STATEMENT Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX C5 ENERGY STATEMENT Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX C6 PHASING PLAN Drawing · 02 Sep 2021
  • ES VOL2 APPX C7 CEMP Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX C8 LEVELS AND EARTHWORKS STRATEGY Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D2 LVIA SCOPING PHOTO VIEW POINT PLANS Drawing · 02 Sep 2021
  • ES VOL2 APPX D3 LANDSCAPE CHARACTER ASSESSMENTS REVIEW Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D4 LCA D2 BRENTWOOD HILLS D2 Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D7 SITE SPECIFIC LANDSCAPE VALUE INDICATORS Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D9 FMD EXTRACTS Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D10 LANDSCAPE CHARACTER ASSESSMENT TABLES Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D11 VISUAL ASSESSMENT TABLES Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX D12 DSM VERIFIED STANDARD PHOTOMONTAGE NON TECHNICAL METHODOLOGY Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX F3 MODEL VERIFICATION Supporting Documents · 02 Sep 2021
  • ES VOL2 APPX G1 BASE DAYTIME NOISE LEVELS Drawing · 02 Sep 2021
  • ES VOL2 FIGURE 14 DESIGNATED SITES Drawing · 02 Sep 2021
  • ES VOL2 FIGURE 14.2 PHASE 1 HABITAT MAP Drawing · 02 Sep 2021
  • ES VOL2 FIGURES D1 TO D6 Drawing · 02 Sep 2021
  • ES VOL2 FIGURES D9 TO D16 Drawing · 02 Sep 2021
  • NOTICE 1 Supporting Documents · 01 Sep 2021
  • NOTICE COVERING LETTER Supporting Documents · 01 Sep 2021
  • NOTICE COVERING LETTER 2 Supporting Documents · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 1 Design and Access Statement · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 2 Design and Access Statement · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 3 Design and Access Statement · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 4 Design and Access Statement · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 5 Design and Access Statement · 01 Sep 2021
  • DESIGN AND ACCESS STATEMENT PART 6 Design and Access Statement · 01 Sep 2021
  • 10352-HL-15 REV B STATION ROAD Superseded Drawing · 01 Sep 2021
  • 10352-HL-11 REV B OVERVIEW OF HIGHWAY WORKS Drawing · 01 Sep 2021
  • 10352-HL-16 REV B A127/A128 JUNCTION IMPROVEMENTS Superseded Drawing · 01 Sep 2021
  • 184427/A/03 A127/B148 JUNCTION IMPROVEMENT Drawing · 01 Sep 2021
  • 10352-HL-12 REV B NORTHERN SITE ACCESS Superseded Drawing · 01 Sep 2021
  • 10352-HL-13 REV B IMPOVEMENTS AND CENTRAL SITE ACCESS Superseded Drawing · 01 Sep 2021
  • 10352-HL-14 REV B SOUTHERN SITE ACCESS Superseded Drawing · 01 Sep 2021
  • 31057-320-5 REV D EXISTING SITE PLAN Site Plan · 01 Sep 2021
  • 31057-321-1 REV B DEMOLITION PLAN Drawing · 01 Sep 2021
  • 31057-322-REV A TOPOGRAPHIC PLAN Drawing · 01 Sep 2021
  • 31057-400 REV A ILLUSTRATIVE MASTERPLAN Superseded Drawing · 01 Sep 2021
  • 31057-401 REV A PHASING PLAN Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 1 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 2 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 3 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 4 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 5 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 6 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 7 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 8 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 9 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 10 Superseded Drawing · 01 Sep 2021
  • FRAMEWORK MASTERPLAN PART 11 Superseded Drawing · 01 Sep 2021
  • TRANSPORT ASSESSMENT APPENDICES A TO H Supporting Documents · 01 Sep 2021
  • TRANSPORT ASSESSMENT APPENDICES I TO L Supporting Documents · 01 Sep 2021
  • TRANSPORT ASSESSMENT MAIN TEXT Supporting Documents · 01 Sep 2021
  • AFFORDABLE HOUSING SCHEME Supporting Documents · 01 Sep 2021
  • COMMUNITY MANAGEMENT STATEMENT Supporting Documents · 01 Sep 2021
  • DELIVERY STATEMENT Supporting Documents · 01 Sep 2021
  • EMPLOYMENT STRATEGY Supporting Documents · 01 Sep 2021
  • ES NON TECHNICAL SUMMARY Supporting Documents · 01 Sep 2021
  • ENVIRONMENTAL STATEMENT VOL 1 CHAPTERS Supporting Documents · 01 Sep 2021
  • HERITAGE STATEMENT Supporting Documents · 01 Sep 2021
  • HEALTH IMPACT STATEMENT Supporting Documents · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 1 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 9 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 2 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 3 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 4 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 5 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 6 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 8 OF 9 Drawing · 01 Sep 2021
  • HILLS-19-08-21-TREE CONSTRAINTS 7 OF 9 Drawing · 01 Sep 2021
  • MOBILITY PLAN Supporting Documents · 01 Sep 2021
  • PLANNING APPLICATION SUMMARY DOCUMENT Supporting Documents · 01 Sep 2021
  • PLANNING OBLIGATION HEADS OF TERMS Supporting Documents · 01 Sep 2021
  • PLANNING STATEMENT Supporting Documents · 01 Sep 2021
  • RETAIL AND COMMERCIAL LEISURE ASSESSMENT Supporting Documents · 01 Sep 2021
  • SCHOOL SITE COMPLIANCE STATEMENT Supporting Documents · 01 Sep 2021
  • TREE SURVEY SCHEDULE Supporting Documents · 01 Sep 2021
  • STATEMENT OF COMMUNITY INVOLEMENT Supporting Documents · 01 Sep 2021
  • SERVICES SUPPLY STATEMENT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX B1 JULY 2018 SCOPING REQUEST REPORT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX B4A RE SCOPING OPINION NOV 2019 ENCL 2 LIST OF CONSULTEES Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX B4C RE SCOPING OPINION NOV 2019 ENCL 3 CONSULTATION RESPONSES Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX H1 HERITAGE ASSET PLAN Drawing · 01 Sep 2021
  • ES VOL2 APPX J1 PHASE 1 DESK STUDY Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX H2 HERITAGE STATEMENT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX K1 C HYDRAULIC MODELLING Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX K1 E GROUNDWATER MAP Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX H5 NATIONAL HERITAGE LIST DESCRIPTION Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX G3 FUTURE YEAR NOISE LEVELS NO MITIGATION Drawing · 01 Sep 2021
  • ES VOL2 APPX H3 ZTV Drawing · 01 Sep 2021
  • ES VOL2 APPX K1 B APPENDICES TO FRAFRA AND DS Drawing · 01 Sep 2021
  • ES VOL2 APPX H4 HERITAGE RECEPTORS SCOPED OUT AT BASELINE STAGE Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX K1 D REVIEW NOTE Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX G2 NOISE LEVELS WITH 7.5M MITIGATION Drawing · 01 Sep 2021
  • ES VOL2 APPX K1 A FRA AND DS Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX N2 SOIL MANAGEMENT STRATEGY Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX 01 EIA CUMULATIVE ASSESSMENT SCOPE NOTE Supporting Documents · 01 Sep 2021
  • ES VOL2 FIGURE D7 Drawing · 01 Sep 2021
  • ES VOL2 APPX K2A ESSEX AND SUFFOLK WATER PRE-DEVELOPMENT CONSULTATION Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX 13 STATUTORY SITES IMPACT ASSESSMENT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX M2 ARCHAEOLOGICAL GEOPHYSICAL SURVEY PART 1 Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX M2 ARCHAEOLOGICAL GEOPHYSICAL SURVEY PART 2 Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX K2 B ESSEX & SUFFOLK WATER Drawing · 01 Sep 2021
  • ES VOL2 APPX 12 HRA SCREENING REPORT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX L1 BACKGROUND SOCIO ECONOMIC DATA Drawing · 01 Sep 2021
  • ES VOL2 APPX M1 HERITAGE ARCHAEOLOGY DESK BASED ASSESSMENT Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX N1 ALC MARCH 21 Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX F1 AIR QUALITY OBJECTIVES Supporting Documents · 01 Sep 2021
  • ES VOL2 FIGURE D8 Photo · 01 Sep 2021
  • ES VOL2 APPX F2 TRAFFIC DATA Supporting Documents · 01 Sep 2021
  • ES VOL2 FIGURE D17 PHOTO MONTAGES PART 1 Photo · 01 Sep 2021
  • ES VOL2 FIGURE D17 PHOTO MONTAGES PART 2 Photo · 01 Sep 2021
  • ES VOL2 APPX D8 COMPOSITION OF VIEWS Drawing · 01 Sep 2021
  • ES VOL2 APPX C3 LIGHTING ASSESSMENT AND STRATEGY Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX D6 LANDSCAPE CAPACITY STUDY Supporting Documents · 01 Sep 2021
  • ES VOL2 APPX D5 LCA G1 HORNDON FENLAND Supporting Documents · 01 Sep 2021
  • 31057-101-REV F SITE LOCATION PLAN Site Plan · 31 Aug 2021
  • 31057-320-1-REV D LAND USE 01 Superseded Drawing · 31 Aug 2021
  • 31057-320-4-REV D BUILDING HEIGHTS 03 Drawing · 31 Aug 2021
  • 31057-320-2-REV D ACCESS AND MOVEMENT PLAN 02 Superseded Drawing · 31 Aug 2021
  • COVERING LETTER Supporting Documents · 31 Aug 2021
  • APPLICATION FORM Application Form · 31 Aug 2021

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Brentwood granted permission on 16 June 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    21/01525/DHVCON/1 Submitted 19 Jun 2026 400 yards away

    99% historically approved · decision due ~14 Aug

    Tree works, site clearance and habitat creation to facilitate translocation of reptiles pursuant to pre-commencement requirements of Condition 11 under LPA Ref: 21/01525/OUT pertaining to implementation of Enabling Works (within a phase) associated with the outline permission granted 16.06.2026

    Awaiting decision Conditions Trees 16 docs
  • Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    21/01525/DHVCON/3 Submitted 23 Jun 2026 450 yards away

    99% historically approved · decision due ~18 Aug

    Approval of Details pursuant to the requirements of pre-commencement Condition 15 under LPA Ref: 21/01525/OUT for a Construction Waste Management Plan (within a phase) associated with the permission granted 16.06.2026

    Awaiting decision Conditions 7 docs
  • Entire Land East Of A128 South Of A127 Tilbury Road West Horndon Essex

    21/01525/DHVCON/4 Submitted 17 Jul 2026 0.3 miles away

    99% historically approved · decision due ~11 Sep

    Approval of Details pursuant to the requirements of pre-commencement Conditions 35 and 36 under LPA Ref: 21/01525/OUT for a Written Scheme of Investigation for Trial Trenching (within a phase) associated with the permission granted 16.06.2026

    Awaiting decision Conditions 4 docs
  • Dunton Hills Farm Tilbury Road West Horndon Brentwood Essex CM13 3LT

    21/01981/COND/1 Submitted 9 Aug 2022 0.3 miles away

    Discharge of conditions 4 (Schedule of drawings for windows, doors etc) and 5 (Schedule of external finish materials including roof and wall material) of application 22/01981/HHA (Single storey rear extension).

    Granted Conditions Extension Windows or glazing 5 docs
    Small domestic
  • Dunton Hills Farm Tilbury Road West Horndon Brentwood Essex CM13 3LT

    22/00181/COND/1 Submitted 9 Aug 2022 0.3 miles away

    Discharge of conditions 4 (Schedule of drawings for windows, doors etc) and 5 (Schedule of external finish materials including roof and wall material) of application 22/00181/LBC (Single storey rear extension).

    Granted Conditions Extension Windows or glazing 5 docs
    Small domestic

In Brentwood

  • 26/00769/OUT Awaiting decision

    Land To Rear Of 1-6 Woodfield Cottages High Street Ingatestone CM4 0DY

    Outline planning application for the erection of up to 216 dwellings and provision of up to 2,000sqm gross internal floorspace of non-residential development, comprising up to 1,500sqm of community facilities within Use Class F2 and up to 500sqm of retail floorspace within Use Class E(a), with access sought for approval and appearance, landscaping, layout and scale reserved.

    Outline
  • 26/00755/OUT Awaiting decision

    Land At Eagle Field Ongar Road Kelvedon Hatch Essex

    Outline application for the provision of up to 49 dwellings (Class C3), including vehicular access, landscaping, public open space, drainage and associated infrastructure (Appearance, Landscaping, Layout and Scale reserved matters)

    Received 3 Jul, published by the council 8 Aug 2026 Outline
  • 26/00242/EIASO Decided

    Brentwood Centre Doddinghurst Road Pilgrims Hatch Essex CM15 9NN

    Environmental Impact Assessment screening opinion for the redevelopment of The Brentwood Centre, including partial demolition, a new extension and external material alterations of the Brentwood Centre alongside a comprehensive redevelopment of outdoor sports facilities (including associated sports infrastructure, parking and landscaping).

    Received 21 Apr, published by the council 9 Aug 2026 Outline
  • 25/01260/OUT Refused

    Adj Grassmere Horseman Side Navestock Essex

    Outline application for construction of a single family dwelling (appearance and Landscaping reserved matters) (Self Build)

    Received 14 Nov, published by the council 9 Aug 2026 Outline
  • 26/00376/EIASO Decided

    Land West Of Honeypot Lane Honeypot Lane Brentwood Essex CM14 4QX

    Environmental Impact Assessment screening opinion for the development of up to 150 residential units (Use Class C3), vehicle and pedestrian access and associated infrastructure

    Received 26 Mar, published by the council 9 Aug 2026 Outline