Planning application
Land North Of The Ferry Terminal Colintraive Argyll And Bute
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Screening Opinion for proposed 33kV overhead line
As published by the council, reference 26/00659/SCREEN
Application record
- Reference
- 26/00659/SCREEN
- Type
- Screening Opinion
- Status
- Awaiting decision
- Received
- 20 Apr 2026
- Validated
- 20 Apr 2026
- Ward
- Cowal
- Parish
- Colintraive And Glendaruel CC
Timeline
Dates from the published record
-
20 Apr 2026
Received by Argyll and Bute
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 15 June 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Argyll and Bute took a median of 53 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
Documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Argyll and Bute for determination, against a statutory target of eight weeks. Over the last year Argyll and Bute decided outline applications in a median of 66 days. More in our guide to how long planning decisions take.
About outline applications
An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land At Colintraive Argyll And Bute
100% historically approved · decision due ~27 Aug
Installation of a new 33kV overhead spur
Awaiting decision Other -
Cul Mhor Colintraive Argyll And Bute PA22 3AR
Siting of self catering pod in place of existing domestic garage
Refused Full applications 20 docs -
Cul Mhor Colintraive Argyll And Bute PA22 3AR
97% historically approved · decision due ~1 Jul
Siting of self catering pod in place of existing domestic garage
Awaiting decision Full applications -
The Ferry Terminal Colintraive Argyll And Bute PA22 3AP
91% historically approved · decision due ~9 Dec
Non Material Amendment relatvie to Planning Permission 25/02132/PP (Erection of SSEN Substation and LV Switchgear room. Installation of 6 subsurface cable ducts and installation of a shore power arm to enable ferry charging) Various changes
Awaiting decision Amendments -
The Ferry Terminal Colintraive Argyll And Bute PA22 3AP
Erection of extension and alterations
Granted Full applications Extension 25 docs -
The Ferry Terminal Colintraive Argyll And Bute PA22 3AP
Erection of 8 metre high de mountable communications pole
Granted Full applications
Other outline applications
In Argyll and Bute
-
26/01279/CLWP Granted
Broomfield Glenburn Road Ardrishaig Argyll And Bute PA30 8EU
Certificate of lawfulness (Proposed) for alterations works to existing dwellinghouse, comprising the replacement of a living-room window with bi-fold doors and the construction of a new patio; the formation of a stepped landing and replacement of a bedroom window with a sliding door, and the repair and reinstatement of the existing chimney, internal wall removal and construction of a utility room.
-
26/01161/CLWP Granted
Darroch's Cottage Tarbert Isle Of Jura Argyll And Bute PA60 7XH
Erection of ancillary shed/storage to replace ruined stone built shed
-
26/01415/PPP Awaiting decision
Land To The North Of Kennacraig Farm Kennacraig By Tarbert Argyll And Bute
Renewal of planning permission in principle reference 23/01662/PPP (Site for the erection of dwellinghouse)
-
26/01310/FDP Decided
Knapdale Forest Achnamara Argyll And Bute
Land Management Plan
-
26/01266/FDP Decided
Upper Sonachan Forest Ardbrecknish Argyll And Bute
Long Term Forest Plan