Awaiting decision Aberdeenshire ENQ/2022/1178 Notification under Electricity Act 1989

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Consultation Under Section 37 for High Voltage Overhead Supported by Wooden Poles (Retrospective)

As published by the council, reference ENQ/2022/1178

Application record

Reference
ENQ/2022/1178
Type
Notification under Electricity Act 1989
Status
Awaiting decision
Received
4 Aug 2022
Validated
4 Aug 2022
Ward
North Kincardine
Parish
Portlethen & District
Postcode
AB12 3LR

Timeline

Dates from the published record

  1. 4 Aug 2022

    Received by Aberdeenshire

  2. 1 Sep 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 29 September 2022, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Aberdeenshire took a median of 64 days over the applications it decided in the last year.

What happens while it is decided

This application is with Aberdeenshire for determination, against a statutory target of eight weeks. Over the last year Aberdeenshire decided less common application types in a median of 62 days. More in our guide to how long planning decisions take.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

Nearby applications

Within 500 metres

In Aberdeenshire

  • APP/2026/0761 Granted

    Glendronach Distillery Forgue Huntly AB54 6DB

    Erection of Overhead Line (Retrospective)

    6 May 2026 Other
  • APP/2024/2146 Granted

    Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD

    Storage of Hazardous Substances

    23 Dec 2024 Other
  • APP/2025/1786 Granted

    132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure

    31 Oct 2025 Other
  • APP/2025/1555 Granted

    Land Approximately 1.2 Km To The South Of A950 Longside Peterhead Aberdeenshire AB42 0LY

    Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with an Installed Capacity of up to 400MW and Associated Works

    19 Sep 2025 Other
  • APP/2026/0449 Granted

    The Forkins Midmar AB51 7NR

    Retrospective S37 Consent for Overhead Line

    17 Mar 2026 Other