Planning application
New Deer To Netherton Hub, Peterhead Tie-In
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Consultation under Section 37 of The Electricity Act 1989 for the Installation of 400KV Overhead Lines, 18 Steel Lattice Towers, 2 Temporary Towers and Associated Infrastructure
As published by the council, reference APP/2026/1343
Application record
- Reference
- APP/2026/1343
- Type
- Notification under Electricity Act 1989
- Status
- Awaiting decision
- Received
- 5 Aug 2026
- Validated
- 5 Aug 2026
- Ward
- Central Buchan
- Parish
- Longside & District
Timeline
Dates from the published record
-
5 Aug 2026
Received by Aberdeenshire
-
7 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 30 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Aberdeenshire took a median of 65 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
60 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Aberdeenshire for determination, against a statutory target of eight weeks. Over the last year Aberdeenshire decided less common application types in a median of 61 days. More in our guide to how long planning decisions take.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land To The South Of Netherton Peterhead
Consultation Request for Screening Opinion for 'Tie In' of Existing 400kV Overhead Line (OHL) to Proposed 400kV AC Substation
Decided Outline
Other less common application types
In Aberdeenshire
-
APP/2026/1317 Granted
Mains Of Cowie Stonehaven
Consultation under Section 37 of the Electricity Act 1989 for Change in Pole Height from 8.53m to 14m to Support 11kV Overhead Line
-
APP/2026/0761 Granted
Glendronach Distillery Forgue Huntly AB54 6DB
Erection of Overhead Line (Retrospective)
-
APP/2024/2146 Granted
Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD
Storage of Hazardous Substances
-
APP/2025/1786 Granted
132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation
Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure
-
APP/2025/1555 Granted
Land Approximately 1.2 Km To The South Of A950 Longside Peterhead Aberdeenshire AB42 0LY
Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with an Installed Capacity of up to 400MW and Associated Works