Planning application
26/02902/FULL
Development Site At 105-106 New Bond Street And 18 Haunch Of Venison Yard London
Proposal
Variation/removal of Conditions 1, 5, 19, 22, and 23 of planning permission 2nd October 2025 (RN: 25/04904/FULL), which itself varied Condition 1 of planning permission dated 4th June 2025 (RN: 25/01184/FULL), which itself varied Conditions 1 and 6 of planning permission dated 11th September 2020 (RN:19/06794/FULL) for demolition behind the retained New Bond Street facade and erection of a new building comprising sub-basement, basement, ground and six upper storeys for use as retail (Class E( a)) at basement, part ground and mezzanine floors; offices (Class E(g)(i)) at part ground, third to sixth floors; and dual/alternative use of the first and second floor as either offices (Class E(g)(i)) and/or retail (Class E(a)). Office access to be via Haunch of Venison Yard. Installation of plant at sub-basement and roof levels, terraces at upper floors and cycle storage and waste stores within basement level; NAMELY, to incorporate design amends at Level 06 roof to accommodate terrace, reconfigure the basement layout, inclusion of structural panel to glazing at Level 04, and increase lift overrun.
As published by the council, reference 26/02902/FULL
Timeline
Dates from the published record
-
1 May 2026
Received by Westminster
-
21 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Westminster for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
25/08050/NMA Awaiting decision
Development Site At 105-106 New Bond Street And 18 Haunch Of Venison Yard London
Amendments to planning permission dated 2nd October 2025 (RN 25/04904/FULL) for the Variation of Condition 1 of planning permission dated 4th June 2025 (RN: 25/01184/FULL), which itself varied Conditions 1 and 6 of planning permission dated 11th September 2020 (RN:19/06794/FULL) for, 'Demolition behind the retained New Bond Street facade and erection of a new building comprising sub-basement, basement, ground and six upper storeys for use as retail (Class A1) at basement, part ground and mezzanine floors; offices (Class 81) at part ground, third to sixth floors; and dual/alternative use of the first and second floor as either offices (Class 81) and/or retail (Class A1). Office access to be via Haunch of Venison Yard. Installation of plant at sub-basement and sixth floor levels, terraces at third to fifth floor levels and cycle storage and waste stores at sub basement level' NAMELY, to amend the description of develpoment and wording of condition 6.
-
25/07922/ADV Awaiting decision
106 New Bond Street London W1S 1SY
Display of a scaffold shroud to the front elevation of 105-106 New Bond Street and 18 Haunch of Venison Yard for temporary period between 01 November 2025 to 28 February 2027 incorporating a static, non-illuminated advertisement measuring approximately 9.0m wide by 3.5m high.
-
25/05338/FULL Refused
26 Brook Street West End London W1K 5DQ
Variation of Condition 1 of planning permission dated 3rd October 2024 (RN:24/03691/FULL) for, 'External alterations including replacement windows and doors, infilling three windows and one infilled door opening to the rear, relocation of condenser units and screening to main roof level, installation of a replacement shopfront and erection of an awning'; Namely, changes to the shopfront, which will be extended further along Haunch of Venison Yard, with the large section of curved glass previously proposed, now squared off and replaced with one single pane facing Brook Street and two panes facing the Yard and to introduce a skylight on the roof above the stair core. (Application under Section 73 of the Act).
-
25/05619/ADV Awaiting decision
20 Brook Street West End London W1K 5DE
Display of non illuminated fascia sign measuring 4.77m X 0.46m and internally illuminated projecting sign measuring 0.15m X 0.65m
-
25/05618/FULL Awaiting decision
20 Brook Street West End London W1K 5DE
Replacement shopfront, replacement roof light on the third floor roof facing North, minor internal alterations, installation of secondary glazing on the second and third and floor, replacement air conditioning for the ground and basement floor, alterations of the basement tea point and WC area and replacement fire doors at main escape core. (Linked to 25/05616/LBC)
-
25/05616/LBC Awaiting decision
20 Brook Street West End London W1K 5DE
Replacement shopfront, replacement roof light on the third floor roof facing North. Minor internal alterations, installation of secondary glazing on the second and third and floor, replacement air conditioning for the ground and basement floor, alterations of the basement tea point and WC area and replacment fire doors at main escape core. (Linked to 25/05618/FULL)
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.