Conversion of garage into a habitable space including alterations to existing pitched roof to create roof extension including installation of two dormer windows to the front elevation and two dormer windows with infill roof slope to the rear elevation. (Retrospective and includes amendments to works approved under application 24/04993/FULL including resolving of discrepancies in the front and rear elevations including modifications to windows, dormer design, and materials).
As published by the council, reference 26/01678/FULL
Timeline
Dates from the published record
-
16 Mar 2026
Received by Westminster
-
24 Apr 2026
Validated
Checked as complete and ready for consideration.
-
21 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Westminster for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/00463/FULL Awaiting decision
Second Floor And Third Floor Maisonette 1 Castellain Road London W9 1EY
Alterations to rear roof dormer and windows, to enlarge dormer and install new bifold doors and create balcony space.
-
26/01595/TCA Awaiting decision
28 Formosa Street London W9 2QA
1 x bay: fell
-
25/06168/ADFULL Refused
7A Pindock Mews London W9 2PY
Detail elevation drawings, section drawings of the new windows and doors and a sample of the glass (at least 300mm square) and window restrictors to allow maximum opening of 20cm pursuant to condition 4 and 5 of planning permission dated 28th July 2025 (RN:25/03892/FULL)
-
26/01581/ADFULL Awaiting decision
11 Pindock Mews London W9 2PY
Details of sample of the glass (at least 300mm square) for all windows and provide a manufacturer's specification or drawing of the restrictors to be fitted to the dormer windows to prevent them being fully openable pursuant to condition 5 of planning permission dated 31st October 2024 (RN: 24/04993/FULL).
-
26/00746/FULL Granted
76 Warwick Avenue London W9 2PU
Installation of a metal handrail to entrance steps up to the main front door.
-
25/06143/TPO Granted
9 Warrington Gardens London W9 2QB
1x London plane (T1, Front); Reduce crown back to most recent reduction points leaving suitable shortened soft furnishing growth with a natural balanced canopy
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.