Proposal

Retention of decking, balustrade, two bridges, lighting and other associated fixed items, and use of the jetty as flexible class E(a), F1, F2, drinking establishment, hot-food takeaway and cinema (sui generis) uses for a temporary period of two years. (See related listed building consent application ref. 2025/4021.)

As published by the council, reference 2025/4019

Application record

Reference
2025/4019
Status
Pending As published: REGISTERED
Received
29 Jun 2026
Postcode
SW8 5BX

Site history

Applications at this address on the Wandsworth register

This site has had 2 applications since 2026.

  • 2025/4021 Awaiting decision

    Battersea Power Station Kirtling Street SW8 5BX

    Listed building consent application for the retention of decking, balustrades, two bridges, lighting and other associated fixed items for a period of two years.(See related planning application ref. 2025/4019.)

    Submitted 29 Jun 2026

Timeline

Dates from the published record

  1. 29 Jun 2026

    Received by Wandsworth

  2. 29 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 24 August 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Wandsworth took a median of 61 days over the applications it decided in the last year.

Cases linked to this one on the register

  • 2025/4021 Awaiting decision

    Battersea Power Station Kirtling Street SW8 5BX

    Listed building consent application for the retention of decking, balustrades, two bridges, lighting and other associated fixed items for a period of two years.(See related planning application ref. 2025/4019.)

    Submitted 29 Jun 2026

1 later application on the register refers to this one:

  • 2025/4021 Awaiting decision

    Battersea Power Station Kirtling Street SW8 5BX

    Listed building consent application for the retention of decking, balustrades, two bridges, lighting and other associated fixed items for a period of two years.(See related planning application ref. 2025/4019.)

    Submitted 29 Jun 2026

What happens while it is decided

This application is with Wandsworth for determination, against a statutory target of eight weeks. Over the last year Wandsworth's median decision took 61 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Wandsworth's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Battersea Power Station Kirtling Street SW8 5BX

    2025/4021 Submitted 29 Jun 2026 50 yards away

    89% historically approved · decision due ~24 Aug

    Listed building consent application for the retention of decking, balustrades, two bridges, lighting and other associated fixed items for a period of two years.(See related planning application ref. 2025/4019.)

    Awaiting decision
  • Phase 6: Battersea Power Station Cringle Street SW11 8BX

    2025/3203 Submitted 12 Sep 2025 50 yards away

    Application under S96a of the Town and Country Planning Act 1990 for amendments to conditions 2 (approved drawings) and 8 (opening hours) planning permission 2023/4015 dated 02/04/2024 (for "Installation of temporary structures for 5 years comprising an indoor leisure and recreation facility (Class E(d)) and an exhibition hall (Class F1(e)), provision of a temporary structure for use as a cafe (Class E(b)) alongside a temporary sub-station and use of the existing shipping containers as a toilet and changing facilities and a cafe (Class E(b)) in association with the indoor leisure and recreation facility (Class E(d)) as well as other associated and enabling works to include external landscaping, lighting, fencing, servicing and access arrangements.") (The proposed amendments comprise extensions to the opening hours of Plot 1 and Plot 2; and alterations to Plot 1 including a new self-contained timber building to be used as an office, replacement of fabric roller shutters with sliding doors, and installation of a pergola.)

    Granted Amendments Extension 16 docs
  • Battersea Power Station Phase 6 Cringle Street SW11 8BX

    2022/4485 Submitted 2 Nov 2022 50 yards away

    Application for temporary soft landscaping including provision of Class B8 (storage) floorspace within shipping containers on part of Phase 6 of the Battersea Power Station masterplan development for a period of 5 years.

    Granted 19 docs
  • BPS Kirtling Street Phase 5A SW8 5BN

    2026/3169 Submitted 7 Sep 2026 50 yards away

    89% historically approved · decision due ~2 Nov

    Submission of details pursuant to Condition 45 (archaeological investigation) for Phase 5A only of planning permission 2021/0414 dated 28/02/2022 for the Battersea Power Station masterplan.

    Awaiting decision
  • Battersea Power Station Phase 3b Kirtling Street SW8 5BN

    2026/2944 Submitted 26 Aug 2026 50 yards away

    89% historically approved · decision due ~21 Oct

    Application under Section 96A of the Town and Country Planning Act 1990 for 'non-material' amendments to conditions 8 (floorspace restrictions), 10 (distribution of uses) and 11 (maximum floorspace per development zone) of planning permission 2020/0579 dated 05/09/2020. The amendments relate to the change of use of unit UG-14 within Phase 3B of the development from retail / professional and financial services (class A1/A2) to food and beverage (class A3/A4/A5).

    Awaiting decision
  • Phase 5A Battersea Power Station SW8 5BN

    2026/3200 Submitted 9 Sep 2026 50 yards away

    89% historically approved · decision due ~4 Nov

    Submission of details pursuant to Condition 43 (ground investigations) for Phase 5A only of planning permission 2021/0414 dated 28/02/2022 for the Battersea Power Station masterplan.

    Awaiting decision