Planning application
Hornsea Project Three Offshore Wind Farm
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Code of Construction Practice (17), Ecological Management Plan (10) and Landscape Plan (8)
As published by the council, reference 20220835
Application record
- Reference
- 20220835
- Type
- Approval of Details Required by DCO
- Status
- Decided
- Decision
- Granted As published: Approval with Conditions
- Received
- 17 May 2022
- Validated
- 17 May 2022
- Decided
- 23 Dec 2022
- Ward
- Reepham
- Parish
- Reepham
- Decision by
- Delegated
Site history
Applications at this address on the South Norfolk register
This site has had 15 applications since 2021: 11 approved, 2 refused.
-
20222020 Withdrawn
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements (13) for Surface and Foul Water Drainage Additional Document
-
20221992 Withdrawn
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements 12 (Fencing)
-
20221792 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Onshore 18 (Construction Traffic Management Plan)
-
2022/2089 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (condition) for Provision of (10) Onshore Cable Corridor Ecological Management Plan
-
2022/2082 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial Discharge of requirements (condition) for Provision of (10) Onshore Converter Station Ecological Management Plan
-
2022/2069 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Cable Corridor
-
2022/2070 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Converter Station
-
2022/1962 Refused
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) - Hedgerow removal notice
-
20221614 Refused
Hornsea Project Three Offshore Wind Farm
Hedgerow removal notice regarding works to be undertaken by Hornsea Project Three within Broadland District
-
2022/0972 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of (8) Landscape Plan, (10) Ecological Management Plan, (17) Code of Construction Practice, (16) Onshore Written Scheme of Investigation (18) Construction Traffic Management Plan
Timeline
Dates from the published record
-
17 May 2022
Received by South Norfolk
-
23 Dec 2022
Decision issued: Approval with Conditions
-
27 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
36 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
South Norfolk granted permission on 23 December 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Onshore 18 (Construction Traffic Management Plan)
Granted Conditions 10 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements 12 (Fencing)
Withdrawn Conditions 2 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17) : for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys
Granted Conditions 12 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17) : for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys
Granted Conditions 12 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 12 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 12 docs
Other condition discharge and variation applications
In South Norfolk
-
2026/1799 Granted
Land East Of 4 Pheasant Walk Plot 5 Pheasant Walk South Walsham Norfolk
Details for conditions 2 - Materials, 3 - Landscaping scheme and 6 -Surface water drainage strategy, of permission 2024/3637
-
2026/2127 Granted
Whitehall Farm Crownthorpe Road Crownthorpe Norfolk NR18 9EP
Discharge of condition 11- Archaeological WSI, condition 12- Surface water drainage and discharge of the statutory BGP condition of existing application 2025/3520
-
2026/2208 Granted
Land North Of Hethersett Village Centre Little Melton Road Hethersett Norfolk
Details of condition 12 (lighting design strategy for biodiversity) of original planning application 2021/0758
-
2026/2519 Granted
Grain Store North Arminghall Lane Arminghall Norfolk
Details of condition 5 (Precautionary Method of Works (PMoW) for Great Crested Newts) of 2026/0908
-
2026/1560 Granted
Land Off Back Lane Wymondham Norfolk
Details for conditions 3 - Air Source Heat Pumps & 5 - Hard and Soft Landscaping, of permission 2024/0998