Planning application
Hornsea Project Three Offshore Wind Farm
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of (8) Landscape Plan, (10) Ecological Management Plan, (17) Code of Construction Practice, (16) Onshore Written Scheme of Investigation (18) Construction Traffic Management Plan
As published by the council, reference 2022/0972
Application record
- Reference
- 2022/0972
- Type
- Approval of Details Required by DCO
- Status
- Decided
- Decision
- Granted As published: Approval of details - Approved
- Received
- 17 May 2022
- Validated
- 17 May 2022
- Decided
- 23 Dec 2022
- Ward
- Mulbarton And Stoke Holy Cross
- Parish
- Swardeston
- Decision by
- Delegated
Site history
Applications at this address on the South Norfolk register
This site has had 15 applications since 2021: 11 approved, 2 refused.
-
20222020 Withdrawn
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements (13) for Surface and Foul Water Drainage Additional Document
-
20221992 Withdrawn
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements 12 (Fencing)
-
20221792 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Onshore 18 (Construction Traffic Management Plan)
-
2022/2089 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (condition) for Provision of (10) Onshore Cable Corridor Ecological Management Plan
-
2022/2082 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial Discharge of requirements (condition) for Provision of (10) Onshore Converter Station Ecological Management Plan
-
2022/2069 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Cable Corridor
-
2022/2070 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Converter Station
-
2022/1962 Refused
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) - Hedgerow removal notice
-
20221614 Refused
Hornsea Project Three Offshore Wind Farm
Hedgerow removal notice regarding works to be undertaken by Hornsea Project Three within Broadland District
-
20220835 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Code of Construction Practice (17), Ecological Management Plan (10) and Landscape Plan (8)
Timeline
Dates from the published record
-
17 May 2022
Received by South Norfolk
-
23 Dec 2022
Decision issued: Approval of details - Approved
-
27 Sep 2026
Added to PlanIndex
Documents
54 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What this grant of permission means
South Norfolk granted permission on 23 December 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (condition) for Provision of (10) Onshore Cable Corridor Ecological Management Plan
Granted Conditions 19 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 15 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial Discharge of requirements (condition) for Provision of (10) Onshore Converter Station Ecological Management Plan
Granted Conditions 21 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Cable Corridor
Granted Conditions 11 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Converter Station
Granted Conditions 12 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 15 docs
Other condition discharge and variation applications
In South Norfolk
-
2026/3419 Awaiting decision
Forest School For Life Silfield Street Silfield Norfolk NR18 9NL
Details reserved by condition 5- Surface water drainage, of existing application 2026/2124
-
2026/3402 Awaiting decision
Land South Of The Mere Park Road Diss Norfolk
Details of the Statutory Biodiversity Gain Plan condition and details of condition 16 (Habitat Management and Monitoring Plan) of planning permission 2025/3866
-
2026/3403 Awaiting decision
New Barn Cross Lane Surlingham Norfolk NR14 7DD
Details of condition 4 (surface water), 6 (boundary treatments), 7 (visability splay), 9 (ecology) and 14 (window and door materials) of orignal planning application 2026/0604
-
2026/3401 Awaiting decision
Home Farm Holt Road Horsford Norfolk NR10 3AG
Details of condition 6 (lighting), 9 (details of habitats credits), 12 (enhancement strategy biodiversity) and 16 (landscaping) of orignal planning application (2026/0837)
-
2026/3386 Awaiting decision
The Griffin 212 Yarmouth Road Thorpe St Andrew Norfolk NR7 0SN
Details of condition 22 (Ecological Design Strategy) of planning application 20211741