Planning application

Hornsea Project Three Offshore Wind Farm

Granted South Norfolk 2022/2069 Approval of Details Required by DCO

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Cable Corridor

As published by the council, reference 2022/2069

Application record

Reference
2022/2069
Type
Approval of Details Required by DCO
Status
Decided
Decision
Granted As published: Approval of details - Approved
Received
3 Nov 2022
Validated
3 Nov 2022
Decided
8 Feb 2023
Ward
Mulbarton And Stoke Holy Cross
Parish
Swardeston
Decision by
Delegated

Site history

Applications at this address on the South Norfolk register

This site has had 13 applications since 2021: 9 approved, 2 refused.

  • 20222020 Withdrawn

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements (13) for Surface and Foul Water Drainage Additional Document

    Decided 19 Dec 2022 Conditions
  • 20221992 Withdrawn

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference EN010080) Full discharge requirements 12 (Fencing)

    Decided 11 Jan 2023 Conditions
  • 20221792 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Onshore 18 (Construction Traffic Management Plan)

    Decided 16 Dec 2022 Conditions
  • 2022/2089 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (condition) for Provision of (10) Onshore Cable Corridor Ecological Management Plan

    Decided 8 Feb 2023 Conditions
  • 2022/2082 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial Discharge of requirements (condition) for Provision of (10) Onshore Converter Station Ecological Management Plan

    Decided 8 Feb 2023 Conditions
  • 2022/2070 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Converter Station

    Decided 8 Feb 2023 Conditions
  • 2022/1962 Refused

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) - Hedgerow removal notice

    Decided 23 Nov 2022 Trees
  • 20221614 Refused

    Hornsea Project Three Offshore Wind Farm

    Hedgerow removal notice regarding works to be undertaken by Hornsea Project Three within Broadland District

    Decided 21 Nov 2022 Trees
  • 2021/2573 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17): for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys

    Decided 17 Mar 2022 Conditions
  • 20212144 Granted

    Hornsea Project Three Offshore Wind Farm

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17) : for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys

    Decided 17 Mar 2022 Conditions

Timeline

Dates from the published record

  1. 3 Nov 2022

    Received by South Norfolk

  2. 8 Feb 2023

    Decision issued: Approval of details - Approved

  3. 23 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

11 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

South Norfolk granted permission on 8 February 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Hornsea Project Three Offshore Wind Farm

    2022/2089 Submitted 7 Nov 2022 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (condition) for Provision of (10) Onshore Cable Corridor Ecological Management Plan

    Granted Conditions 19 docs
  • Hornsea Project Three Offshore Wind Farm

    2021/2223 Submitted 5 Oct 2021 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations

    Granted Conditions 15 docs
  • Hornsea Project Three Offshore Wind Farm

    2022/2082 Submitted 4 Nov 2022 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial Discharge of requirements (condition) for Provision of (10) Onshore Converter Station Ecological Management Plan

    Granted Conditions 21 docs
  • Hornsea Project Three Offshore Wind Farm

    2022/2070 Submitted 3 Nov 2022 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Full discharge of requirements (condition) for Provision of (16) Onshore Archaeology for the Onshore Converter Station

    Granted Conditions 12 docs
  • Hornsea Project Three Offshore Wind Farm

    2021/2223 Submitted 5 Oct 2021 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations

    Granted Conditions 15 docs
  • Hornsea Project Three Offshore Wind Farm

    2021/2573 Submitted 25 Nov 2021 50 yards away

    National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17): for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys

    Granted Conditions 13 docs

In South Norfolk

  • 2026/2519 Granted

    Grain Store North Arminghall Lane Arminghall Norfolk

    Details of condition 5 (Precautionary Method of Works (PMoW) for Great Crested Newts) of 2026/0908

    Received 25 Aug, published by the council 31 Aug 2026 Conditions
  • 2026/2206 Granted

    The School Room North Walsham Road Crostwick Norfolk NR12 7BG

    Details for condition 5 of 20230020 - (5) Surface Water Drainage

    Received 29 Jul, published by the council 9 Aug 2026 Conditions
  • 2026/2058 Granted

    Church Of St Remigius Norwich Road Hethersett Norfolk

    Details of condition 3 (March) of original planning application 2025/2839 (Installation of 6 x 4m tall black lighting columns and 2 x car charging points)

    Received 15 Jul, published by the council 29 Jul 2026 Conditions
  • 2026/2295 Granted

    Old Hall Farm Fakenham Road Attlebridge Norfolk NR9 5TQ

    Details of conditions 5A and 5B (Archaeological Written Scheme of Investigation) of 2026/0771

    Received 6 Aug, published by the council 21 Aug 2026 Conditions
  • 2026/2195 Granted

    Land North East Of Hackford Road Wicklewood Norfolk

    Details reserved by condition 3 of 2026/0412 - highways vehicular access

    Received 28 Jul, published by the council 9 Aug 2026 Conditions