Construction and operation of an unmanned Battery Energy Storage System ('BESS') with a power capacity of up to 550 megawatt ('MW') with associated works including control and protection systems, power conversion systems (and associated transformers), temperature regulation systems, a main step-up transformer(s) and switchgear, welfare facilities, electrical cabling and electrical connection, and other associated works - Approved under H16-1327-21. Modification of Conditions 4, 5, 6 & 7 to allow amendments to previously approved/submitted plans
As published by the council, reference H16-0622-26
Application record
- Reference
- H16-0622-26
- Type
- SEC 73 MODIFICATION
- Status
- Undecided
- Received
- 3 Jul 2026
- Validated
- 7 Jul 2026
- Postcode
- PE11 2BB
Timeline
Dates from the published record
-
3 Jul 2026
Received by South Holland
-
7 Jul 2026
Validated
Checked as complete and ready for consideration.
-
22 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 1 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
South Holland took a median of 56 days over the applications it decided in the last year.
What happens while it is decided
This application is with South Holland for determination, against a statutory target of eight weeks. Over the last year South Holland's median decision took 56 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on South Holland's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
BAKKAVOR WEST MARSH ROAD SPALDING PE11 2BB
Two portable cold stores and connecting lobbies
Granted Lawful development 8 docs -
FOWLER WELCH LTD WEST MARSH ROAD SPALDING PE11 2BB
The erection of a vehicle maintenance unit (VMU) together with associated external hard-standing, footpath, staircase and lighting
Granted Full applications 14 docs -
BAKKAVOR WEST MARSH ROAD SPALDING PE11 2BB
Siting of single storey portakabin to be used as a locker room for a period of 52 weeks - retrospective
Granted Full applications 6 docsSmall domestic -
Spalding Energy Expansion Site West Marsh Road Spalding PE11 2BB
Non-material amendment to the conditions of the deemed planning permission associated with the Section 36 consent for the construction and operation of an electricity generating station of up to 945MW (H16-0835-17). Amendments to condition 1 (definitions), condition 6 (removal and/or reprofiling of the Mound), conditions 21 & 22 (construction traffic management plan & access route), condition 43 (biodiversity enhancement measures and condition 45 (surface water drainage) in order to allow for removal and/or reprofiling of the mound as part of the permitted preliminary works and to omit the permitted preliminary works from triggering certain requirements under conditions that would be more appropriately dealt with as part of future development proposals.
Granted Amendments 6 docs -
Land off West Marsh Road Spalding PE11 2BB
Proposed LNG Refuelling Station
Withdrawn Full applications 14 docs -