Planning application
26/02561/FUL
29 Cambridge Science Park Milton Road Cambridge Cambridgeshire CB4 0DW
Proposal
Installation of an external roof top plant, replacement glazing with solid panels and externally applied vinyls to first floor
As published by the council, reference 26/02561/FUL
Timeline
Dates from the published record
-
6 Jul 2026
Received by South Cambridgeshire
-
23 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with South Cambridgeshire for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
25/05050/FUL Granted
80 And 82 Lovell Road Cambridge Cambridgeshire CB4 2QP
Demolition of an existing commercial greenhouse, erection of a 1.5 storey, four-bedroom self-build dwelling together with 2 No. new parking spaces for the proposed dwelling (with EV charging), Repurposing of shared private drive between 80 and 82 Lovell Road, New vehicle turning head enabling forward-gear exit, Relocated entrances for 80 and 82 Lovell Road to the front of the properties, New dropped kerb for 82 Lovell Road driveway, Retention of one parking space each for 80 and 82 Lovell Road (accessed from Lovell Road) and Planting a new line of trees to improve shielding of views of the Science Park together with Enhanced landscaping including native hedgerows, addition of biodiversity enhancements, including provision for protected species.
-
26/01902/OUT Awaiting decision
Cambridge Science Park Milton Road Cambridge Cambridgeshire
Outline planning application with all matters reserved for a mixed-use redevelopment of Cambridge Science Park in separate and severable components each representing severable permitted areas comprising: Flexible employment uses including research and development, office, and workspace, industrial and storage (including data) uses (Use Classes E(g), B2, B8 and sui generis), Flexible Class E, Class F1 and F2, C1 (hotel) and Sui Generis (bar and hot food takeaway) uses to support the operation of the wider Science Park, Highway works, including new vehicular, cyclist and pedestrian roads and paths, and car and cycle parking facilities including mobility hubs with associated electric vehicle charging infrastructure, Landscape and public realm, including areas for sustainable urban drainage systems, biodiversity areas, outdoor play and sports facilities (Use Class F2(c)), Utility, energy, and water facilities and infrastructure, together with enabling, site clearance, demolition and associated works, including temporary meanwhile uses (this includes application ref: 26/01872/OUT).
-
24/04575/FUL Awaiting decision
210-240 Cambridge Science Park Milton Road Cambridge Cambridgeshire CB4 0WA
Demolition of existing units 210, 211, 214, 220, 230, 240 and redevelopment with Use Class E(g) floorspace (office) (E(g)(i)), research and development (E(g)(ii)) with complementary floorspace (Use Class E (a-g)) along with access, landscaping and supporting infrastructure. Retention of Unit 216.
-
26/01786/FUL Granted
Land North West Of 379 To 381 Milton Road Cambridge Cambridgeshire
Construction of a substation compound, to incorporate 3 primary transformers and a switch house building (with associated basement) to accommodate the required 33kV and 11kV switchgear and associated fencing.
-
20/04766/HFUL Granted
66 Kings Hedges Road Cambridge Cambridgeshire CB4 2PA
Single storey rear extension following removal of existing conservatory.
-
26/02403/CL2PD Awaiting decision
119 Kings Hedges Road Cambridge Cambridgeshire CB4 2PL
Certificate of lawfulness under S192 for a proposed rear roof extension including a dormer and installation of 3no rooflights to front elevation.
Other full applications applications
In South Cambridgeshire
-
26/02779/FUL Awaiting decision
3 Royston Road Whittlesford Cambridgeshire CB22 4NW
3 bedroom replacement self build dwelling following demolition of existing bungalow.
-
26/02151/FUL Granted
3 Comberton Road Barton Cambridgeshire CB23 7BA
Installation of a Solar PV system to the roof pitches of the detached garage outbuilding.
-
26/01627/FUL Granted
Valley Farm House Valley Farm Road West Wratting Cambridgeshire CB21 4HH
Change of use of an agricultural building to uses falling within classes B8 storage/distribution or E(g)(iii) light industrial use.
-
26/02708/FUL Awaiting decision
Rectory Farm Middle Street Thriplow Cambridge Cambridgeshire SG8 7RD
Partial demolition of existing collapsed wall and erection of a new wall.
-
25/02739/FUL Granted
Land To The South Of Munceys Farm London Way Melbourn Cambridgeshire SG8 6DJ
Construction and operation of a 25MW solar photovoltaic farm and a 25MW Battery Energy Storage System (BESS) including access, fencing, CCTV, internal service tracks, ancillary equipment and scheme of landscaping for an operational lifespan of 40 years.