Bishops Dal Battery Energy Storage Scheme Land South Of Eccles Substation Coldstream Scottish Borders

Granted Scottish Borders 25/00292/S36 Section 36 Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Battery Energy Storage System (BESS), Substation, Transformers and Associated Infrastructure

As published by the council, reference 25/00292/S36

Application record

Reference
25/00292/S36
Type
Section 36 Application
Status
Decided
Decision
Section 36 No Objection
Received
6 Mar 2025
Validated
11 Mar 2025
Decided
8 Dec 2025
Ward
Mid Berwickshire
Parish
Leitholm, Eccles & Birgham C.C
Decision by
Committee Decision

Timeline

Dates from the published record

  1. 6 Mar 2025

    Received by Scottish Borders

  2. 11 Mar 2025

    Validated

    Checked as complete and ready for consideration.

  3. 8 Dec 2025

    Decision issued: Section 36 No Objection

  4. 5 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

100 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Scottish Borders granted permission on 8 December 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record