Skip to content
PlanIndex Get alerts
Menu

Planning application

Battery Storage Facility Coldstream Scottish Borders

Granted Scottish Borders 22/01532/S36 Section 36 Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Battery Electricity Storage System (BESS) and Associated Infrastructure

As published by the council, reference 22/01532/S36

Application record

Reference
22/01532/S36
Type
Section 36 Application
Status
Decided
Decision
Section 36 No Objection
Received
5 Oct 2022
Validated
5 Oct 2022
Decided
6 Feb 2023
Ward
Mid Berwickshire
Parish
Leitholm, Eccles & Birgham C.C
Decision by
Committee Decision

Timeline

Dates from the published record

  1. 5 Oct 2022

    Received by Scottish Borders

  2. 6 Feb 2023

    Decision issued: Section 36 No Objection

  3. 21 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

172 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Scottish Borders granted permission on 6 February 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Scottish Borders's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres