Planning application
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Discharge of Requirement 6 (Detailed Design Approval) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 1, Highway Works.
As published by the council, reference 2026/0017/MALDIS
Application record
- Reference
- 2026/0017/MALDIS
- Type
- Mallard Pass Discharge of Conditions
- Status
- Registered
- Received
- 6 Jan 2026
- Validated
- 6 Jan 2026
- Ward
- Ryhall And Casterton Ward
- Parish
- Essendine Parish Council
- Decision by
- Delegated Decision
Site history
Applications at this address on the Rutland register
This site has had 19 applications since 2025: 12 approved, 0 refused.
-
2026/0629/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 10 (Archaeology) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0593/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 9 (Surface and Foul Water Drainage) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0592/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 8 (Fencing and Other Means of Enclosure) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0597/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 14 (Soil Management Plan) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0596/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 13 (Construction Traffic Management Plan - CTMP) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0590/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 6 (Detailed Design Approval) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0608/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 7 (Landscape and Ecological Management Plan) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2026/0595/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of requirement 11 (Construction Environmental Management Plan - CEMP) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 2, Main Construction Works.
-
2025/1670/MALDIS Awaiting decision
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement No. 10 1(c) (Archaeology) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 1 - Highway Works.
-
2025/1671/MALDIS Granted
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement No. 17 (Skills, Supply Chain and Employment) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to all phases.
Timeline
Dates from the published record
-
6 Jan 2026
Received by Rutland
-
20 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 3 March 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Rutland took a median of 55 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
Envams Ltd Agent, registered in York
Active · incorporated 2022 · York
41 applications on PlanIndex · across 11 councils · 100% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
The council's own list, drawings first
137 documents on file for this application
Drawings (119)
- Proposed access a-cross sections
- Proposed access b-cross sections
- Access g-proposed cross sections
- Proposed carriageway cross section
- Proposed kerbed carriageway cross section
- Proposed traffic signs & road markings
- Proposed access a-pavement construction & earthworks
- Proposed access a-general arrangement
- Access a-proposed levels and setting out
- Proposed access a-swept path analysis
- Proposed access a-site clearance
- Proposed access b-traffic signs & road markings
- Proposed access b-pavement construction & earthworks
- Proposed access b-site clearance
- Proposed access b-swept path analysis
- Access b-proposed levels and setting out
- Access e-proposed levels and setting out
- Proposed access e-traffic signs & road markings
- Proposed access e-pavement construction & earthworks
- Proposed access f-traffic signs & road markings
- Proposed access f-pavement construction & earthworks
- Access f-proposed levels and setting out
- Proposed access f-site clearance
- Access f-proposed longsections
- Proposed access f-swept path analysis
- Proposed access g-traffic signs & road markings
- Proposed access g-pavement construction & earthworks
- Proposed access g-site clearance
- Proposed access g-swept path analysis
- Proposed access g-swept path analysis
- Proposed access g-swept path analysis
- Access g-proposed longsections
- Proposed access g-general arrangement
- Access g-proposed levels and setting out
- Proposed highway boundary
- Proposed passing place l-pavement construction & earthworks
- Passing place l-proposed levels and setting out
- Proposed passing place l-swept path analysis
- Proposed passing place l-site clearance
- Proposed passing place n-pavement construction & earthworks
- Proposed passing place n-site clearance
- Proposed passing place n-swept path analysis
- Passing place n-proposed levels and setting out
- Proposed passing place n-general arrangement
- Proposed passing place o-pavement construction & earthworks
- Proposed passing place o-general arrangement
- Proposed passing place o-swept path analysis
- Proposed passing place p-general arrangement
- Passing place p-proposed levels and setting out
- Proposed passing place p-pavement construction & earthworks
- Proposed passing place p-swept path analysis
- Proposed passing place q-general arrangement
- Passing place q-proposed levels and setting out
- Proposed passing place q-swept path analysis
- Proposed passing place q-pavement construction & earthworks
- Proposed passing place r-pavement construction & earthworks
- Proposed passing place r-site clearance
- Proposed passing place r-swept path analysis
- Proposed passing place r-general arrangement
- Passing place r-proposed levels and setting out
- Proposed passing place s-pavement construction & earthworks
- Proposed passing place s-site clearance
- Proposed passing place s-swept path analysis
- Passing place s-proposed levels and setting out
- Proposed passing place s-general arrangement
- Proposed stepped carriageway construction detail
- Proposed standard details
- Proposed indicative primary construction compound layout
- Proposed underground cable ducting locations
- Proposed widening k-traffic signs & road marking
- Proposed widening k-pavement construction & earthworks
- Proposed widening k-site clearance
- Proposed widening k-swept path analysis
- Proposed widening k-general arrangement
- Widening k-proposed levels and setting out
- Widening k-proposed levels and setting out
- Proposed widening m-traffic signs & road markings
- Proposed widening m-pavement construction & earthworks
- Proposed widening m-site clearance
- Proposed widening m-swept path analysis
- Widening m-proposed levels and setting out
- Proposed widening m-general arrangemen
- Passing place l-cross sections
- Passing place n-cross sections
- Passing place o-cross sections
- Passing place p-cross sections
- Passing place q-cross sections
- Passing place r-cross sections
- Passing place s-cross sections
- Widening k-cross sections
- Widening k-cross sections
- Widening k-cross sections
- Widening k-cross sections
- Widening k-cross sections
- Widening m-cross sections
- Access e-general arrangement
- Access a-existing statutory undertakers apparatus
- Existing highway boundary
- Access b-existing statutory undertakers apparatus
- Existing access b-general arrangement
- Access e-existing statutory undertakers apparatus
- Existing access e-swept path analysis
- Existing access e-longsections
- Existing access e-longsections
- Access f-existing statutory undertakers apparatus
- Existing access f-general arrangement
- Access g-existing statutory undertakers apparatus
- Passing place l-existing statutory undertakers apparatus
- Existing passing place l-general arrangement
- Passing place n-existing statutory undertakers apparatus
- Passing place o-existing statutory undertakers apparatus
- Passing place o-existing statutory undertakers apparatus
- Passing place p-existing statutory undertakers apparatus
- Passing place q-existing statutory undertakers apparatus
- Passing place r-existing statutory undertakers apparatus
- Passing place s-existing statutory undertakers apparatus
- Widening k-existing statutory undertakers apparatus
- Widening m-existing statutory undertakers apparatus
- Existing site location plan
Everything on file (136)
- EOT REQUEST BY APPLICANT
- EOT REQUEST BY APPLICANT
- CONSULTEE - HIGHWAYS
- CONSULTEE - LEAD LOCAL FLOOD AUTHORITY OFFICER
- APPLICANT EOT REQUEST
- CONSULTEE - LEAD LOCAL FLOOD AUTHORITY
- INTERESTED PARTY - MRS JO GRESTY
- INTERESTED PARTY - MRS JO GRESTY
- COVERING LETTER - ADDITIONAL INFORMATION
- CONSULTEE - HIGHWAYS
- CONSULTEE - MALLARD PASS ACTION GROUP
- INTERESTED PARTY - HEATH COTTAGE, THE DRIFT, RYHALL HEATH, STAMFORD
- INTERESTED PARTY - MRS JO GRESTY
- CONSULTEE - GREAT CASTERTON PARRISH COUNCIL
- COVERING LETTER
- DESIGN PARAMETERS CONFIRMATION STATEMENT
- EMAIL FROM AGENT
- TRAFFIC SIGNS & ROAD MARKINGS
- ACCESS A-PAVEMENT CONSTRUCTION & EARTHWORKS
- ACCESS A-GENERAL ARRANGEMENT
- ACCESS A-PROPOSED LEVELS AND SETTING OUT
- ACCESS A-EXISTING STATUTORY UNDERTAKERS APPARATUS
- ACCESS A-CROSS SECTIONS
- ACCESS A-SWEPT PATH ANALYSIS
- ACCESS A-SITE CLEARANCE
- HIGHWAY BOUNDARY
- ACCESS B-TRAFFIC SIGNS & ROAD MARKINGS
- ACCESS B-PAVEMENT CONSTRUCTION & EARTHWORKS
- ACCESS B-EXISTING STATUTORY UNDERTAKERS APPARATUS
- ACCESS B-SITE CLEARANCE
- ACCESS B-SWEPT PATH ANALYSIS
- ACCESS B-GENERAL ARRANGEMENT
- ACCESS B-PROPOSED LEVELS AND SETTING OUT
- ACCESS B-CROSS SECTIONS
- ACCESS E-GENERAL ARRANGEMENT
- ACCESS E-PROPOSED LEVELS AND SETTING OUT
- ACCESS E-TRAFFIC SIGNS & ROAD MARKINGS
- ACCESS E-PAVEMENT CONSTRUCTION & EARTHWORKS
- ACCESS E-EXISTING STATUTORY UNDERTAKERS APPARATUS
- ACCESS E-SWEPT PATH ANALYSIS
- ACCESS E-LONGSECTIONS
- ACCESS E-LONGSECTIONS
- ACCESS F-TRAFFIC SIGNS & ROAD MARKINGS
- ACCESS F-PAVEMENT CONSTRUCTION & EARTHWORKS
- ACCESS F-EXISTING STATUTORY UNDERTAKERS APPARATUS
- ACCESS F-GENERAL ARRANGEMENT
- ACCESS F-PROPOSED LEVELS AND SETTING OUT
- ACCESS F-SITE CLEARANCE
- ACCESS F-PROPOSED LONGSECTIONS
- ACCESS F-SWEPT PATH ANALYSIS
- ACCESS G-TRAFFIC SIGNS & ROAD MARKINGS
- ACCESS G-PAVEMENT CONSTRUCTION & EARTHWORKS
- ACCESS G-EXISTING STATUTORY UNDERTAKERS APPARATUS
- ACCESS G-SITE CLEARANCE
- ACCESS G-SWEPT PATH ANALYSIS
- ACCESS G-SWEPT PATH ANALYSIS
- ACCESS G-SWEPT PATH ANALYSIS
- ACCESS G-PROPOSED LONGSECTIONS
- ACCESS G-PROPOSED CROSS SECTIONS
- ACCESS G-GENERAL ARRANGEMENT
- ACCESS G-PROPOSED LEVELS AND SETTING OUT
- HIGHWAY BOUNDARY
- SITE LOCATION PLAN
- PASSING PLACE L-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE L-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE L-GENERAL ARRANGEMENT
- PASSING PLACE L-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE L-CROSS SECTIONS
- PASSING PLACE L-SWEPT PATH ANALYSIS
- PASSING PLACE L-SITE CLEARANCE
- PASSING PLACE N-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE N-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE N-SITE CLEARANCE
- PASSING PLACE N-SWEPT PATH ANALYSIS
- PASSING PLACE N-CROSS SECTIONS
- PASSING PLACE N-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE N-GENERAL ARRANGEMENT
- PASSING PLACE O-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE O-GENERAL ARRANGEMENT
- PASSING PLACE O-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE O-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE O-CROSS SECTIONS
- PASSING PLACE O-SWEPT PATH ANALYSIS
- PASSING PLACE P-GENERAL ARRANGEMENT
- PASSING PLACE P-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE P-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE P-CROSS SECTIONS
- PASSING PLACE P-SWEPT PATH ANALYSIS
- PASSING PLACE P-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE Q-GENERAL ARRANGEMENT
- PASSING PLACE Q-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE Q-CROSS SECTIONS
- PASSING PLACE Q-SWEPT PATH ANALYSIS
- PASSING PLACE Q-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE Q-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE R-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE R-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE R-SITE CLEARANCE
- PASSING PLACE R-SWEPT PATH ANALYSIS
- PASSING PLACE R-CROSS SECTIONS
- PASSING PLACE R-GENERAL ARRANGEMENT
- PASSING PLACE R-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE S-PAVEMENT CONSTRUCTION & EARTHWORKS
- PASSING PLACE S-EXISTING STATUTORY UNDERTAKERS APPARATUS
- PASSING PLACE S-SITE CLEARANCE
- PASSING PLACE S-SWEPT PATH ANALYSIS
- PASSING PLACE S-CROSS SECTIONS
- PASSING PLACE S-PROPOSED LEVELS AND SETTING OUT
- PASSING PLACE S-GENERAL ARRANGEMENT
- STEPPED CARRIAGEWAY CONSTRUCTION DETAIL
- CARRIAGEWAY CROSS SECTION
- KERBED CARRIAGEWAY CROSS SECTION
- STANDARD DETAILS - KERBING AND EDGING
- INDICATIVE PRIMARY CONSTRUCTION COMPOUND LAYOUT R1.0
- UNDERGROUND CABLE DUCTING LOCATIONS R2.0
- WIDENING K-TRAFFIC SIGNS & ROAD MARKING
- WIDENING K-PAVEMENT CONSTRUCTION & EARTHWORKS
- WIDENING K-EXISTING STATUTORY UNDERTAKERS APPARATUS
- WIDENING K-SITE CLEARANCE
- WIDENING K-SWEPT PATH ANALYSIS
- WIDENING K-CROSS SECTIONS
- WIDENING K-GENERAL ARRANGEMENT
- WIDENING K-PROPOSED LEVELS AND SETTING OUT
- WIDENING K-PROPOSED LEVELS AND SETTING OUT
- WIDENING K-CROSS SECTIONS
- WIDENING K-CROSS SECTIONS
- WIDENING K-CROSS SECTIONS
- WIDENING K-CROSS SECTIONS
- WIDENING M-TRAFFIC SIGNS & ROAD MARKINGS
- WIDENING M-PAVEMENT CONSTRUCTION & EARTHWORKS
- WIDENING M-EXISTING STATUTORY UNDERTAKERS APPARATUS
- WIDENING M-SITE CLEARANCE
- WIDENING M-SWEPT PATH ANALYSIS
- WIDENING M-PROPOSED LEVELS AND SETTING OUT
- WIDENING M-GENERAL ARRANGEMEN
- WIDENING M-CROSS SECTIONS
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you the drawings on every job in your area. 14 days free.
What happens while it is decided
This application is with Rutland for determination, against a statutory target of eight weeks. Over the last year Rutland decided condition discharge and variation applications in a median of 56 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement Number 3 (Phasing) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended).
-
Mallard Pass Solar Farm Stamford Road Essendine Rutland
92% historically approved · decision due ~13 Feb
Discharge of Requirement No. 10 1(c) (Archaeology) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to Phase 1 - Highway Works.
Awaiting decision Conditions 14 docs -
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement No. 17 (Skills, Supply Chain and Employment) of Schedule 2 of The Mallard Pass Solar Farm Order 2024 (as amended) in relation to all phases.
Granted Conditions 6 docs -
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement 15 (Ground Conditions) of Schedule 2 of The Mallard Pass Solar Farm order 2024 (as amended) in relation to all phases.
Granted Conditions 6 docs -
Mallard Pass Solar Farm Stamford Road Essendine Rutland
Discharge of Requirement No. 9 (surface and foul water drainage) of schedule 2 of the Mallard Pass Solar Farm Order 2024 (as amended) in relation to phase 1 - Highways Works.
Granted Conditions 16 docs -
Mallard Pass Solar Farm Stamford Road Essendine Rutland
92% historically approved · decision due ~13 Feb
Discharge of requirement No. 14 (Soil Management Plan) of schedule 2 of the Mallard Pass Solar Farm Order 2024 (as amended) in relation to phase 1 - Highways Works.
Awaiting decision Conditions 18 docs
Other condition discharge and variation applications
In Rutland
-
2026/1280/DIS Awaiting decision
Old Hall Cottage Lyndon Road Hambleton Rutland LE15 8BG
Discharge of Condition No. 8 (Landscaping), Condition No. 11 (Boundary Fence Details) and Condition No. 18 (Tree Works) on planning permission ref: 2025/0892/FUL (Erection of a Replacement Dwelling).
-
2026/0869/DIS Granted
Grange Farm Ryhall Road Great Casterton Rutland
Discharge of Condition No. 3 (Written Scheme of Investigation), Condition No. 5 (Materials), Condition No. 8 (Tree Protection), Condition No. 14 (Construction Management Plan), Condition No. 16 (Construction Environment Management Plan for Biodiversity), Condition No. 17 (Habitat Management and Monitoring Plan) and Condition No. 18 (Off Site Biodiversity Net Gain Units) on planning permission ref: 2025/1179/FUL (Alterations to existing buildings and the construction of new general industrial use buildings in conjunction with vehicular access improvements, car parking improvements and enhancement / improvements to landscaping and the biodiversity on the site. The retention of the B8 Storage units to the rear of the site. Associated works to include the installation of PV cells and EV car charging points. New site signage to be installed. Use Class B2 remain unchanged for the site).
-
2026/0857/DIS Granted
Swan House 36 Main Street Lyddington Rutland LE15 9LT
Discharge of Condition 3 (Materials) in relation to application 2024/1363/FUL - Construction of new entrance porch. Two storey extension to the North East elevation. New sun room to the South East elevation. Proposed garage.
-
2026/1054/DIS Awaiting decision
Pheasants Roost Lyndon Road Manton Rutland LE15 8RN
Discharge of Condition 3 (Materials), 4 (Cycle Store Details), 7 and 8 (Construction Management Plan), 12 and 13 (Package Treatment Details and Drainage Field Details), 15 (Ecological and Biodiversity Mitigation Plan), 17 (Landscaping), 21 (External Levels), 28 (Acoustic Barrier Details), 29 (Dust Extraction Details) and 40 (Waste Material Storage) of application 2022/1111/MAF - Change of use from agricultural to E(g)(iii) business to facilitate relocation of Willowbrook Education Ltd. Conversion of existing buildings, adaption and new build elements including new yard and parking areas with access improvements.
-
2026/0962/DIS Awaiting decision
Land Off Park Road Ketton Rutland PE9 3SL
Discharge of condition 7 (Surface Water Drainage Scheme) in relation to 2020/0942/OUT - Outline application with all matters reserved except for means of access, for residential development of up to 75 no. dwellings with associated public open space, landscaping and infrastructure.