Planning application
20/00388/FULPP
139 Grosvenor Road Aldershot Hampshire GU11 3EF
Proposal
Retention and completion of a first-floor rear extension with external stairs to garden level
As published by the council, reference 20/00388/FULPP
Timeline
Dates from the published record
-
12 Jun 2020
Received by Rushmoor
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Rushmoor for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
20/00365/CONDPP Granted
69 Gordon Road Aldershot Hampshire GU11 1NG
Submission of details pursuant to Condition Nos.5 (communal aerial/satellite dish system) and 8 (external lighting) of planning permission 18/00400/FULPP dated 13th July 2018
-
20/00359/NMAPP Granted
69 Gordon Road Aldershot Hampshire GU11 1NG
NON-MATERIAL AMENDMENTS: Amendments to development approved with planning permission 18/00400/FULPP dated 13 July 2018 comprising (a) change to roof design of new-build section to rear; (b) replacement of lift with staircase; (c) changes to window sizes; and (d) consequential internal layout alterations including to bin and bicycle stores
-
20/00200/FULPP Granted
54 Grosvenor Road Aldershot Hampshire GU11 3DY
Change of use of ground floor from photographic studio to 1no. 1-bed flat (C3)
-
26/00037/FULPP Refused
Development Site At 1 - 7 Elms Road Aldershot Hampshire
Demolition of remaining fire damaged vehicle repair workshop, construction of 3 storey building containing 6 no. 2 bedroom apartments with private balconies, private parking, communal garden and bike / bin store
-
26/00257/FULPP Awaiting decision
Tiffanys 38 - 40 Grosvenor Road Aldershot Hampshire GU11 3DY
Change of use of former nightclub (Sui Generis) to a mixed-use kitchen, bathroom and tiles showroom (Class E), together with associated parking, access from Laburnum Road and ancillary works
-
21/00375/FULPP Granted
21 Cargate Avenue Aldershot Hampshire GU11 3EP
Replace front wall, replace and relocate pier and improve hard-standing
Other full applications applications
In Rushmoor
-
26/00429/FULPP Awaiting decision
27A Woburn Avenue Farnborough Hampshire GU14 7EQ
Proposed conversion of the existing integral garage into habitable accommodation, erection of a first-floor extension over the existing garage, and extension of the front garage wall by approximately 1.15m to facilitate the first-floor accommodation
-
26/00424/FULPP Awaiting decision
160 Alexandra Road Farnborough Hampshire GU14 6RY
Erection of a two storey rear/side extension
-
26/00420/FULPP Awaiting decision
50 Sidlaws Road Farnborough Hampshire GU14 9JN
Erection of a single storey side and rear extension, convert garage to habitable accommodation and new pitched roof over porch
-
26/00417/FULPP Awaiting decision
61 Queensmead Farnborough Hampshire GU14 7RL
External alterations including replacement of existing windows and insertion of new windows in front, side and rear elevations and insertion of new door in front elevation
-
26/00407/FULPP Awaiting decision
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Installation of an EV charging hub comprising electrical upstands, a substation, an LV switchgear pillar, line markings and associated electrical infrastructure