Burgar Hill Turbines, Georth Road, Evie, Orkney

Awaiting decision Orkney Islands 25/188/SCO Scoping

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Scoping opinion request to erect four wind turbines (maximum height 200 metres) (total generating capacity 30MW)

As published by the council, reference 25/188/SCO

Application record

Reference
25/188/SCO
Type
Scoping
Status
Awaiting decision
Received
26 May 2025
Validated
29 May 2025
Ward
West Mainland
Parish
Evie & Rendall Community Council

Timeline

Dates from the published record

  1. 26 May 2025

    Received by Orkney Islands

  2. 29 May 2025

    Validated

    Checked as complete and ready for consideration.

  3. 5 Aug 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 24 July 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Orkney Islands took a median of 99 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Applicant on file, registered in Roslin

1 application on PlanIndex

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

41 documents on file for this application

  • Environmental Health Consultation Response · 07 Apr 2026
  • NatureScot Consultation Response · 26 Jan 2026
  • Islands archaeologist Consultation Response · 10 Sep 2025
  • Historic Environment Scotland Consultation Response · 03 Sep 2025
  • Developer Correspondence - Archaelogy Correspondence · 25 Aug 2025
  • Background Noise Monitoring Methodology Supporting Document · 05 Aug 2025
  • HES - Extension Correspondence · 29 Jul 2025
  • Roads Services Consultation Response · 15 Jul 2025
  • MoD (Ministry of Defence) Consultation Response · 07 Jul 2025
  • Islands archaeologist Consultation Response · 01 Jul 2025
  • HIAL (Highlands & Islands Airports Ltd) Consultation Response · 30 Jun 2025
  • SEPA (Scottish Environment Protection Agency) Consultation Response · 23 Jun 2025
  • Scottish Water Consultation Response · 23 Jun 2025
  • Arqiva Services Ltd Consultation Response · 23 Jun 2025
  • Kirkwall Airport ? Senior Pilot Consultation Response · 09 Jun 2025
  • NATS (National Air Traffic Services) Consultation Response · 09 Jun 2025
  • JRC (Joint Radio Company) Consultation Response · 09 Jun 2025
  • Invalid Letter Correspondence · 29 May 2025
  • Turbine Coordinates Supporting Document · 29 May 2025
  • Scoping Request Application Form · 27 May 2025
  • Scoping Report Supporting Document · 27 May 2025
  • Gazetteer of Heritage Assets and Events Supporting Document · 27 May 2025
  • Location Plan Supporting Document · 27 May 2025
  • Constraints Plan Supporting Document · 27 May 2025
  • Site Plan Supporting Document · 27 May 2025
  • 45km Study Area Supporting Document · 27 May 2025
  • Cumulative Basemap Supporting Document · 27 May 2025
  • 200m Tip ZTV Supporting Document · 27 May 2025
  • 119m Hub ZTV Supporting Document · 27 May 2025
  • Landscape Character Types Supporting Document · 27 May 2025
  • Landscape Planning Designations Supporting Document · 27 May 2025
  • Residential Amenity Assessment Supporting Document · 27 May 2025
  • Non-designated Assets 1km Supporting Document · 27 May 2025
  • Designated Assets 10km Supporting Document · 27 May 2025
  • Noise Study Area Supporting Document · 27 May 2025
  • Hydrological Context Map Supporting Document · 27 May 2025
  • Shadow Flicker Study Area Supporting Document · 27 May 2025
  • Cumulative Shadow Flicker Study Area Supporting Document · 27 May 2025
  • Tourist Receptors with 200m Tip ZTV Supporting Document · 27 May 2025
  • Accomodation Receptors with 200m Tip ZTV Supporting Document · 27 May 2025
  • Recreation Receptors with 200m Tip ZTV Supporting Document · 27 May 2025

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Orkney Islands for determination, against a statutory target of eight weeks. Over the last year Orkney Islands decided outline applications in a median of 127 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

In Orkney Islands

  • 25/442/PIP Granted

    Tormiston (Land Near), Stenness, Orkney ,

    Siting of a house (one for one)

    22 Dec 2025 Outline
  • 26/214/PIP Awaiting decision

    Hillside (Land Near), Otterswick Road, Sanday, Orkney

    Siting of a house and a detached garage (change of use of land from agricultural to domestic)

    20 Jul 2026 Outline
  • 26/084/SCR Decided

    Castles, Eday, Orkney

    Screening opinion request to erect three wind turbines (maximum height 15 metres)

    10 Mar 2026 Outline
  • 26/051/PIP Granted

    Bonnie Brae, Tankerness Hall Road, Tankerness, St Andrews, Orkney KW17 2QS

    Siting of a house and create an access (subdivision of curtilage)

    23 Feb 2026 Outline
  • 25/441/PIP Granted

    Brekka (Land Near), Cruan Road, Firth Orkney KW15 1TT

    Siting of a house and create an access (subdivision of curtilage) (including amendment to 23/059/PIP)

    22 Dec 2025 Outline