Planning application
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Formal Submission to discharge of Requirement 20 (Removal of temporary bridges and culverts for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016
As published by the council, reference 22/P/2194/DCO
Application record
- Reference
- 22/P/2194/DCO
- Type
- Development Consent Order - Minor
- Status
- Decided
- Decision
- Approve
- Received
- 9 Sep 2022
- Validated
- 9 Sep 2022
- Decided
- 15 Mar 2023
- Parish
- Unparished
- Decision by
- Delegated Decision
Site history
Applications at this address on the North Somerset register
This site has had 30 applications since 2019: 29 approved, 0 refused.
-
26/P/1813/DCM Awaiting decision
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 10 (Replacement Planting) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
26/P/1284/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to extend the time for discharge of Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
26/P/0912/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to extend the time to discharge Requirements 15 (Reinstatement schemes) and 20 (Removal of temporary bridges and culverts) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/2633/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1772/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 15 (Reinstatement schemes) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1750/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Formal submission to discharge Requirement 22 (Highway Works (Bellmouth Design)) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
25/P/1749/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 5(2)(d) (Construction Traffic Management Plan Addendum) for Stage 7.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
23/P/0407/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission to discharge of Requirement 6(1)(f) (Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as amended)
-
23/P/0240/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 5(2)(b) (Biodiversity Mitigation Strategy for Stage 10.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
-
22/P/2976/DCM Granted
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal submission to discharge Requirement 10 (Scheme of Replacement Planting for Stage 8 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended).
Timeline
Dates from the published record
-
9 Sep 2022
Received by North Somerset
-
15 Mar 2023
Decision issued: Approve
-
31 Jul 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Arup Agent, registered in London
Active · incorporated 1990 · London
205 applications on PlanIndex · across 47 councils · 98% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
17 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
North Somerset granted permission on 15 March 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on North Somerset's portal will say. Our guide explains the common types.