Skip to content
PlanIndex Get alerts
Menu

Planning application

Clydeport Authority Fairlie Largs North Ayrshire KA29 0AZ

Granted North Ayrshire 26/00007/PP Planning Permission (Full)

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Installation of three replacement electricity sub-stations

As published by the council, reference 26/00007/PP

Application record

Reference
26/00007/PP
Type
Planning Permission (Full)
Status
Approved with no Conditions
Decision
Approved with no Conditions
Received
7 Jan 2026
Validated
27 Jan 2026
Decided
27 Feb 2026
Ward
North Coast
Parish
Fairlie Community Council
Decision by
Delegated
Postcode
KA29 0AZ

Timeline

Dates from the published record

  1. 7 Jan 2026

    Received by North Ayrshire

  2. 27 Jan 2026

    Validated

    Checked as complete and ready for consideration.

  3. 27 Feb 2026

    Decision issued: Approved with no Conditions

  4. 27 Jul 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Cameron Planning F.a.o Steven Cameron Agent, a planning consultancy

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Clydeport Operations Ltd Applicant, registered in Glasgow

Active · incorporated 1991 · Glasgow

2 applications on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

16 documents on file for this application

  • Decision notice Decision · 27 Feb 2026
  • Report of handling Report · 27 Feb 2026
  • Neighbour notification Neighbour Notification List · 02 Feb 2026
  • Excavation and pathway for substation 1 Approved Drawing · 07 Jan 2026
  • Proposed site plan Approved Drawing · 07 Jan 2026
  • Location plan Approved Drawing · 07 Jan 2026
  • Planning statement Report · 07 Jan 2026
  • Application for planning permission Application Form · 07 Jan 2026
  • Substation 1 civils and ducting Approved Drawing · 07 Jan 2026
  • Substation 1 fencing layout Approved Drawing · 07 Jan 2026
  • Substation 1 plans and elevations Approved Drawing · 07 Jan 2026
  • Substation 2 civils and ducting Approved Drawing · 07 Jan 2026
  • Substation 2 plans and elevations Approved Drawing · 07 Jan 2026
  • Substation 3 civils and ducting sht 2 of 2 Approved Drawing · 07 Jan 2026
  • Substation 3 civils and ducting sht 1 of 2 Approved Drawing · 07 Jan 2026
  • Substation 3 plans and elevations Approved Drawing · 07 Jan 2026

Trade members open them from here.

Open the documents

What this grant of permission means

North Ayrshire granted permission on 27 February 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Former Coal Terminal Hunterston West Kilbride Ayrshire

    23/00131/PP Submitted 22 Feb 2023 367m away

    Variation of condition 11 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Granted Full applications 7 docs
  • Former Coal Terminal Hunterston West Kilbride Ayrshire

    22/00759/PP Submitted 4 Oct 2022 367m away

    Variation of conditions 11 and 12 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Withdrawn Full applications 5 docs
  • Former Coal Terminal Hunterston West Kilbride Ayrshire

    22/00133/PPPM Submitted 18 Feb 2022 371m away

    Planning permission in principle for the erection of a high voltage cable manufacturing facility, including detailed planning permission for the construction of a 185m high extrusion tower with associated factories, research and testing laboratories, offices with associated stores, transport, access, parking and landscaping with on-site generation and electrical infrastructure and cable delivery system

    Granted Outline 114 docs
    Major scheme
  • Former Coal Terminal Hunterston West Kilbride Ayrshire

    23/00070/PP Submitted 30 Jan 2023 371m away

    Variation of conditions 9 and 18 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Granted Full applications 9 docs

In North Ayrshire

  • 26/00447/PP Granted

    Site To South Of Arran Heritage Museum Brodick Isle Of Arran North Ayrshire

    Formation of new foot path

    26 Jun 2026 Full applications
  • 26/00324/PP Refused

    Site To South East Of Farm Cottage Corriecravie Brodick Isle Of Arran North Ayrshire

    Erection of detached dwelling house and formation of access

    6 May 2026 Full applications
  • 26/00477/PP Granted

    Hunterston East 400kv Power Station West Kilbride North Ayrshire KA23 9QX

    Substation security upgrades

    10 Jul 2026 Full applications
  • 26/00607/PP Awaiting decision

    Boathouse Brodick Isle Of Arran North Ayrshire KA27 8AJ

    Change of use to Class 3 (cafe)

    4 Sep 2026 Full applications
  • 26/00606/PP Awaiting decision

    Ayrshire Central Hospital Kilwinning Road Irvine North Ayrshire KA12 8SS

    Erection of 28 dwelling houses for social rent to include the demolition of existing buildings, formation of access roads, parking, open space, landscaping, SuDS and ancillary infrastructure

    4 Sep 2026 Full applications