Former Coal Terminal Hunterston West Kilbride Ayrshire

Granted North Ayrshire 23/00744/PP Planning Permission (Full)

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Development and operation of a grid stability facility

As published by the council, reference 23/00744/PP

Application record

Reference
23/00744/PP
Type
Planning Permission (Full)
Status
Approved subject to Conditions
Decision
Granted As published: Approved subject to Conditions
Received
3 Oct 2023
Validated
5 Oct 2023
Decided
4 Dec 2023
Ward
North Coast
Parish
Fairlie Community Council
Decision by
Delegated

Site history

Applications at this address on the North Ayrshire register

This site has had 7 applications since 2021: 5 approved, 0 refused.

  • 23/00131/PP Granted

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    Variation of condition 11 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Decided 24 May 2023 Full applications
  • 23/00070/PP Granted

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    Variation of conditions 9 and 18 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Decided 23 Mar 2023 Full applications
  • 22/00759/PP Withdrawn

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    Variation of conditions 11 and 12 of planning permission N/22/00133/PPPM relating to the construction of a high voltage sub-sea cable manufacturing facility

    Decided 22 Feb 2023 Full applications
  • 22/00712/MSCM Granted

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    Submission of details pertaining to pre-commencement conditions relating to erection of a high voltage cable manufacturing facility

    Decided 24 May 2023 Conditions
  • 22/00133/PPPM Granted

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    Planning permission in principle for the erection of a high voltage cable manufacturing facility, including detailed planning permission for the construction of a 185m high extrusion tower with associated factories, research and testing laboratories, offices with associated stores, transport, access, parking and landscaping with on-site generation and electrical infrastructure and cable delivery system

    Decided 29 Jun 2022 Outline
  • 21/00480/EIA Decided

    Former Coal Terminal Hunterston West Kilbride Ayrshire

    EIA screening request for proposed synchronous compensator

    Decided 1 Jun 2021 Outline

Timeline

Dates from the published record

  1. 3 Oct 2023

    Received by North Ayrshire

  2. 5 Oct 2023

    Validated

    Checked as complete and ready for consideration.

  3. 4 Dec 2023

    Decision issued: Approved subject to Conditions

  4. 1 Sep 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

RSK Environment Ltd Fao Juliet Richards Agent

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Highview Power Ltd Fao Applicant

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

25 documents on file for this application

  • Decision notice Decision · 04 Dec 2023
  • Report of handling Report · 04 Dec 2023
  • Environmental health response Consultation Response · 16 Nov 2023
  • Objection letter Objection Comment · 31 Oct 2023
  • Construction traffic management plan for application for stability island at for Report · 03 Oct 2023
  • Application fees pdf Fees PDF · 03 Oct 2023
  • Flood risk assessment report for application for stability island at former hunt Report · 03 Oct 2023
  • 1:250 site layout of proposed stability island hunterston Approved Drawing · 03 Oct 2023
  • 1:5000 location plan Approved Drawing · 03 Oct 2023
  • 2d elevation drawing for proposed stability island hunterston Approved Drawing · 03 Oct 2023
  • Lva report excluding appendices to accompany application for stability island at Report · 03 Oct 2023
  • Appendix 1 to the landscape and visual appraisal report Report · 03 Oct 2023
  • Appendix 2 to the landscape and visual appraisal report Report · 03 Oct 2023
  • Appendix 3 to the landscape and visual appraisal reeport Report · 03 Oct 2023
  • Appendix 4 to the landscape and visual appraisal report Report · 03 Oct 2023
  • Baseline viewpoint photography part of appendix 5 of the landscape and visual ap Other · 03 Oct 2023
  • Viewpoint figures part of appendix 5 to accompany the landscape and visual appra BackGround Papers · 03 Oct 2023
  • Appendix 5 to the landscape and visual appraisal report Report · 03 Oct 2023
  • Noise assessment report for application for stability island at former huntersto Report · 03 Oct 2023
  • Figure 1 of the preliminary ecological appraisal report BackGround Papers · 03 Oct 2023
  • Figure 2 of the preliminary ecological appraisal report BackGround Papers · 03 Oct 2023
  • Figure 3 of the preliminary ecological appraisal report BackGround Papers · 03 Oct 2023
  • Application for planning permission Application Form · 03 Oct 2023
  • Transport statement report for application for stability island at former hunter Report · 03 Oct 2023
  • 1:1250 location plan Approved Drawing · 03 Oct 2023

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

North Ayrshire granted permission on 4 December 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In North Ayrshire

  • 26/00566/PP Granted

    Croyde Alma Road Brodick Isle Of Arran North Ayrshire KA27 8AZ

    Demolition of existing side extensions with replacement single side extension

    Received 24 Aug, published by the council 14 Sep 2026 Full applications
  • 26/00676/PP Awaiting decision

    Roebank Hotel And Wedding Venue Roebank Road Beith North Ayrshire KA15 2DX

    Part change of use of hotel/wedding venue to form dwellinghouse

    Received 5 Oct, published by the council 7 Oct 2026 Full applications
  • 26/00589/PP Granted

    5 Bowfield Road West Kilbride North Ayrshire KA23 9LB

    Erection of replacement detached double garage to include the demolition of existing timber garage

    Received 31 Aug, published by the council 8 Sep 2026 Full applications
  • 26/00606/PP Granted

    Ayrshire Central Hospital Kilwinning Road Irvine North Ayrshire KA12 8SS

    Erection of 28 dwelling houses for social rent to include the demolition of existing buildings, formation of access roads, parking, open space, landscaping, SuDS and ancillary infrastructure

    Received 4 Sep, published by the council 14 Sep 2026 Full applications
  • 26/00520/PP Granted

    Overtoun Of Broadstone Gateside Beith North Ayrshire KA15 1HF

    Siting of residential caravan for a temporary period of up to 5 years

    Received 31 Jul, published by the council 11 Aug 2026 Full applications