Planning application
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Variation of Condition 1 of Planning Permission 24/11096 to extend the mixed use of land for haulage and B8 storage until 31st December 2026
As published by the council, reference 25/10970
Application record
- Reference
- 25/10970
- Type
- Variation / Removal of Condition
- Status
- Decided
- Decision
- Granted As published: Grant Temporary Permission
- Received
- 28 Oct 2025
- Validated
- 27 Oct 2025
- Decided
- 12 Feb 2026
- Ward
- Fawley, Blackfield, Calshot & Langley
- Parish
- Fawley
- Decision by
- Development Control Committee
- Postcode
- SO45 1TW
Site history
Applications at this address on the New Forest National Park register
This site has had 6 applications since 2025: 4 approved, 0 refused.
-
26/10719 Granted
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY, SO45 1TW
Use of land to provide open storage of gravel (use class B8) and associated works including provision of containment bunds, drainage channels and excavation, temporary permission sought for 5 years (Variation of Condition 3 (Timescale) of planning permission 18/11145)
-
26/10442 Decided
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Scoping Opinion for the redevelopment of the former Fawley Power Station site for up to 190,000 square metres (Gross External Floor Area) of commercial, industrial and employment related uses, and the provision of associated infrastructure including new coastal flood defences (Scoping Opinion)
-
25/10971 Granted
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Variation of Condition 1 of Planning Permission 24/10861 to extend the use for storage and distribution (Use Class B8) until 31st December 2026
-
25/10972 Granted
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026
-
25/10809 Decided
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution
Timeline
Dates from the published record
-
27 Oct 2025
Validated
Checked as complete and ready for consideration.
-
28 Oct 2025
Received by New Forest National Park
-
12 Feb 2026
Decision issued: Grant Temporary Permission
-
9 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Carter Jonas LLP Agent
1,099 applications on PlanIndex · across 146 councils · 89% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
32 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
New Forest National Park granted permission on 12 February 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About amendment applications
An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution
Decided Outline 5 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution
Decided Outline 5 docs -
Land at FORMER FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Site 1: Temporary storage of wind turbine blades on site of demolished Fawley Power Station Boiler House; Site 2: Temporary storage of wind turbine blades on the site of the Fawley Power Station Control Room and the adjoining car park.
Granted Full applications Demolition 31 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026
Granted Amendments 43 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Variation of Condition 1 of Planning Permission 24/10861 to extend the use for storage and distribution (Use Class B8) until 31st December 2026
Granted Amendments 42 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Variation of Condition 1 of Planning Permission 24/11096 to extend the mixed use of land for haulage and B8 storage until 31st December 2026
Granted Amendments 32 docs
Other amendment applications
In New Forest National Park
-
26/10362 Granted
POULNER FARM HOUSE, 5 BUTLERS LANE, POULNER, RINGWOOD, BH24 1UB
Variation of Condition 2 of application 25/10582 to allow fenestration and material alterations
-
26/10801 Granted
17 ST JOHNS STREET, HYTHE SO45 6BZ
Variation of Condition 1 of Planning Permission 24/10516 to amend and correct inaccurate column placement
-
26/10699 Granted
RINGWOOD SHOPPING CENTRE, 2 MARKET PLACE, RINGWOOD BH24 1AW
Variation of condition 2 of planning permission 24/11105 to allow: fenestration changes to the east elevation and new door to the west elevation; internal layout alterations to ground, first and second floors; associated changes to the external layout.
-
26/01067VAR Awaiting decision
Forest Lodge, HEATH LANE, EAST BOLDRE, BROCKENHURST, SO42 7WF
Application to remove condition 2 of planning approval 35199 (Two storey additio
-
26/10918 Awaiting decision
17 PORT AND MARITIME REGIMENT RLC MCMULLEN BARRACKS, CRACKNORE HARD LANE, MARCHWOOD SO40 4ZG
Variation of Condition 2 of Planning Permission 24/10099 to allow revised road access and finished levels