Land at FORMER FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

Granted New Forest National Park 23/10050 Full Planning Permission

Works: Demolition

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Site 1: Temporary storage of wind turbine blades on site of demolished Fawley Power Station Boiler House; Site 2: Temporary storage of wind turbine blades on the site of the Fawley Power Station Control Room and the adjoining car park.

As published by the council, reference 23/10050

Application record

Reference
23/10050
Type
Full Planning Permission
Status
Decided
Decision
Grant Temporary Permission
Received
17 Jan 2023
Validated
17 Jan 2023
Decided
3 May 2023
Ward
Fawley, Blackfield, Calshot & Langley
Parish
Fawley
Decision by
Development Control Committee
Postcode
SO45 1TW

Timeline

Dates from the published record

  1. 17 Jan 2023

    Received by New Forest National Park

  2. 3 May 2023

    Decision issued: Grant Temporary Permission

  3. 7 Sep 2026

    Added to PlanIndex

Cases linked to this one on the register

1 later application on the register refers to this one:

  • 25/10972 Granted

    SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026

    Decided 12 Feb 2026 Amendments

Who's behind it

Company information only, from the register and Companies House

Agent on file, a planning consultancy registered in Winchester

1 application on PlanIndex

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

31 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

New Forest National Park granted permission on 3 May 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    25/10809 Submitted 4 Sep 2025 0m away

    Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution

    Decided Outline 5 docs
  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    25/10809 Submitted 4 Sep 2025 0m away

    Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution

    Decided Outline 5 docs
  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    25/10972 Submitted 28 Oct 2025 0m away

    Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026

    Granted Amendments 43 docs
  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    25/10971 Submitted 28 Oct 2025 0m away

    Variation of Condition 1 of Planning Permission 24/10861 to extend the use for storage and distribution (Use Class B8) until 31st December 2026

    Granted Amendments 42 docs
  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW

    25/10970 Submitted 28 Oct 2025 0m away

    Variation of Condition 1 of Planning Permission 24/11096 to extend the mixed use of land for haulage and B8 storage until 31st December 2026

    Granted Amendments 32 docs
  • SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY, SO45 1TW

    26/10719 Submitted 30 Jul 2026 0m away

    Use of land to provide open storage of gravel (use class B8) and associated works including provision of containment bunds, drainage channels and excavation, temporary permission sought for 5 years (Variation of Condition 3 (Timescale) of planning permission 18/11145)

    Granted Other 5 docs

In New Forest National Park

  • 26/00929FULL Awaiting decision

    The Well House, Abbotswell Road, Frogham Fordingbridge SP6 2JD

    Replacement dwelling; 2no. outbuildings; associated landscaping; demolition of e

    4 Sep 2026 Full applications
  • 26/00723FULL Granted

    Deerfold, Brook Green, Bramshaw, Lyndhurst SO43 7JB

    Replacement outbuilding to accommodate annexe & workshop; associated landscaping

    13 Jul 2026 Full applications
  • 26/10849 Awaiting decision

    LONGVIEW, FRYERN COURT ROAD, BURGATE, FORDINGBRIDGE SP6 1NG

    Change of use of agricultural land to form residential garden curtilage

    3 Sep 2026 Full applications
  • 26/10850 Awaiting decision

    FOREST GATE SURGERY, 1 HAZEL FARM ROAD, TOTTON SO40 8WU

    Rear extension to accommodate 5 new clinical rooms

    3 Sep 2026 Full applications
  • 26/10848 Awaiting decision

    LONGVIEW, FRYERN COURT ROAD, BURGATE, FORDINGBRIDGE SP6 1NG

    Conversion and extension to outbuilding for use as home gym

    3 Sep 2026 Full applications