Planning application
P2026/0116
Ffynnon Oer Wind Farm Neath Port Talbot SA13 3ND
Proposal
Section 73 Environmental Impact Assessment application to amend the wording of condition 6 (operational period) of planning permission P2002/1322 determined on 27.05.2003 to extend the operational life of Ffynnon Oer Wind Farm by an additional 10 years, to enable operation to continue until 31st July 2036.
As published by the council, reference P2026/0116
Timeline
Dates from the published record
-
27 Feb 2026
Received by Neath Port Talbot
-
3 Mar 2026
Validated
Checked as complete and ready for consideration.
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Neath Port Talbot for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About amendments applications
How this application type works
An amendment application changes a permission that already exists. Non-material amendments cover small adjustments with no wider effect, while minor material amendments, usually made by varying a condition, allow modest design changes without a fresh application. Anything beyond that needs a new permission, so the scope here is deliberately narrow.
Nearby applications
Within 500 metres
-
P2025/0591 Decided
Ffynnon Oer Wind Farm Between Afan And Neath Valley 2 KM West Of Glyncorrwg
Request for a Scoping Opinion in accordance with Regulation 14(1) of the Environmental Impact Assessment (Wales) Regulations 2017 to extend the operational life of Ffynnon Oer Wind Farm by an additional 10 years.
Other amendments applications
In Neath Port Talbot
-
P2026/0243 Withdrawn
243 Western Avenue Sandfields Neath Port Talbot SA12 7NF
Non-material amendment to planning permission reference P2021/1228 approved on 12.01.2022 to remove rooflights on front slope, installation of first floor north side bedroom window, relocation of first floor rear facing window to the southern side elevation, remove front canopy and ramp, replace garage door with window to serve kitchen and internal reconfiguration to create a 5th bedroom on first floor.
-
P2026/0442 Awaiting decision
280 Margam Road Margam Neath Port Talbot SA13 2DB
Section 73 application to vary conditions 4 (opening times) and 5 (no amplified music) of planning permission P2026/0092 - Installation of 3 cabanas to create an outdoor seating area to the rear of an existing cafe (use class A3) approved on 02.04.2026
-
P2026/0405 Awaiting decision
Land At Port Talbot Docks Sand And Gravel Site, Located West Of Margam Steelworks Margam Neath Port Talbot SA13 1NB
Non-Material Amendment to application P2014/0356 to amend the description of development to include the wording of the description of development of the original host permission and amendments to this wording, plus amendments to the wording of conditions 1, 5, 12, 13 and 24, as well as the removal of condition 21 from the decision notice.
-
P2026/0360 Granted
Upper Ogmore Valley Between Blaengwynfi, Nantymoel & Blaengarw in Bridgend & Neath Port Talbot, CF32 8AH
A Non-material Amendment Application to amend the description of development of application P2023/0559 granted on 06/06/2024 to - A development comprising up to seven horizontal axis wind turbines, improved site entrance, new access tracks, crane hardstanding, control building and substation compound, electricity transformers, underground cabling, energy storage containers, drainage works and upgrades to a forestry track.
-
P2026/0232 Granted
Caewern House Dwr Y Felin Road Caewern Neath Port Talbot SA10 7RH
Non-material amendment to planning permission P2024/0301 (Approved on 11.9.2025) to amend the details approved under condition 04 (contamination assessment), condition 05 (remediation scheme), condition 06 (land instability), condition 07 (broadband provision), condition 09 (road safety audit), condition 10 (refuse/recycling collection) and condition 15 (landscape management plan) - rewording conditions to allow demolition, site clearance, and ground investigation to take place prior to the submission of technical details. Rewording of condition 13 (to implement approved tree protection scheme prior to demolition and site clearance)