P2025/0591
Ffynnon Oer Wind Farm Between Afan And Neath Valley 2 KM West Of Glyncorrwg
Proposal
Request for a Scoping Opinion in accordance with Regulation 14(1) of the Environmental Impact Assessment (Wales) Regulations 2017 to extend the operational life of Ffynnon Oer Wind Farm by an additional 10 years.
As published by the council, reference P2025/0591
Timeline
Dates from the published record
-
12 Aug 2025
Received by Neath Port Talbot
-
13 Oct 2025
Decision issued: Scoping Opinion
-
28 Jul 2026
Added to PlanIndex
After the decision
The process from here
The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.
If permission was granted, work must normally begin within five years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Nearby applications
Within 500 metres
-
P2026/0116 Awaiting decision
Ffynnon Oer Wind Farm Neath Port Talbot SA13 3ND
Section 73 Environmental Impact Assessment application to amend the wording of condition 6 (operational period) of planning permission P2002/1322 determined on 27.05.2003 to extend the operational life of Ffynnon Oer Wind Farm by an additional 10 years, to enable operation to continue until 31st July 2036.
Other outline applications
In Neath Port Talbot
-
P2026/0421 Decided
42km Off SW Coast Of Pembrokeshire
DNS EIA scoping consultation: Gwynt Glas Offshore Wind Farm a large-scale floating offshore wind energy project
-
P2026/0426 Awaiting decision
Cryddan Brook Flood Alleviation Scheme Melyn Neath
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environment Impact Assessment) (Wales) Regulations 2017 for a proposed Flood Alleviation Scheme
-
P2025/0792 Granted
Land East Of Minyrawel Pen Yr Alltwen Rhos Pontardawe Neath Port Talbot
Outline application for residential development for up to 8 dwellings with approval sought for access, and all other matters reserved
-
P2026/0410 Awaiting decision
Abernant Colliery Pontardawe SA8 4SX
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environment Impact Assessment) (Wales) Regulations 2017 for a proposed biomass gasification Combined Heat and Power (CHP) waste-to-hydrogen production facility
-
P2026/0328 Decided
Cymmer Port Talbot
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2017, for the Proposed Cymmer Carriageway Realignment Works.