Planning application
Dorenell Wind Farm Lower Cabrach Huntly Moray AB54 4ES
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Construct and operate a wind energy generating station of 67 wind turbines with ground to blade tip heights varying of 149.9m to 250m with associated infrastructure and includes a battery energy storage system at
As published by the council, reference 25/01005/S36
Application record
- Reference
- 25/01005/S36
- Type
- Dealt With By Scottish Executive
- Status
- Awaiting decision
- Received
- 14 Aug 2025
- Validated
- 14 Aug 2025
- Ward
- Speyside Glenlivet
- Parish
- Dufftown & District
- Decision by
- Committee - National/Major
- Postcode
- AB54 4ES
Timeline
Dates from the published record
-
14 Aug 2025
Received by Moray
-
27 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 9 October 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Moray took a median of 82 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
268 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Moray for determination, against a statutory target of eight weeks. Over the last year Moray's median decision took 82 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Moray's portal will say. Our guide explains the common types.