Land Adjacent To Electricity Substation Westerton Road Keith Moray

Granted Moray 22/01488/APP Application for Planning Permission

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Proposed battery energy storage system and associated Infrastructure on

As published by the council, reference 22/01488/APP

Application record

Reference
22/01488/APP
Type
Application for Planning Permission
Status
Decided
Decision
Granted As published: Permitted
Received
13 Oct 2022
Validated
13 Oct 2022
Decided
15 Mar 2023
Ward
Keith And Cullen
Parish
Keith
Decision by
Committee - National/Major

Site history

Applications at this address on the Moray register

This site has had 4 applications since 2022: 2 approved, 0 refused.

  • 24/01479/APP Granted

    Land Adjacent To Electricity Substation Westerton Road Keith Moray

    Section 42 application to vary conditions 3, 12, 13, 14, 16, 18 and 19 of 22/01488/APP at

    Decided 18 Dec 2024 Full applications
  • 22/00837/SCN Decided

    Land Adjacent To Electricity Substation Westerton Road Keith Moray

    Proposed cable sealing end compound (T362R) on

    Decided 22 Jul 2022 Outline
  • 22/00798/SCN Decided

    Land Adjacent To Electricity Substation Westerton Road Keith Moray

    Proposed cable sealing end compound (T113R) on

    Decided 22 Jul 2022 Outline

Timeline

Dates from the published record

  1. 13 Oct 2022

    Received by Moray

  2. 15 Mar 2023

    Decision issued: Permitted

  3. 5 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

1 later application on the register refers to this one:

  • 24/01479/APP Granted

    Land Adjacent To Electricity Substation Westerton Road Keith Moray

    Section 42 application to vary conditions 3, 12, 13, 14, 16, 18 and 19 of 22/01488/APP at

    Decided 18 Dec 2024 Full applications

Who's behind it

Company information only, from the register and Companies House

Arcus Consultancy Service Ltd Agent

5 applications on PlanIndex · across 4 councils

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Keith Renewables Limited Applicant

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

25 documents on file for this application

  • 24/01481/DICON - DISCHARGE OF COND 4 - ACCEPTED Correspondence from Council · 21 Nov 2024
  • 23/02033/NMV - NON MATERIAL VARIATION - ACCEPTED Correspondence from Council · 13 Dec 2023
  • 23/02033/NMV - LANDSCAPE MITIGATION - ACCEPTED Amended Drawing · 08 Dec 2023
  • 23/02033/NMV - SITE LAYOUT PLAN - ACCEPTED Amended Drawing · 17 Nov 2023
  • DECISION NOTICE - APPROVE Decision · 15 Mar 2023
  • REPORT Committee Report · 15 Feb 2023
  • INFORMATION PACK Committee Report · 15 Feb 2023
  • ACOUSTIC FENCE DETAILS - APPROVED Drawing · 10 Feb 2023
  • WELFARE CABIN ELEVATIONS - APPROVED Drawing · 10 Feb 2023
  • SPARES CONTAINER ELEVATIONS - APPROVED Drawing · 10 Feb 2023
  • SECURITY COLUMN DETAIL - APPROVED Amended Drawing · 10 Feb 2023
  • PALISADE FENCE DETAILS - APPROVED Amended Drawing · 10 Feb 2023
  • CLIENT SWITCHROOM ELEVATIONS - APPROVED Amended Drawing · 10 Feb 2023
  • DNO SWITCHROOM ELEVATIONS - APPROVED Amended Drawing · 10 Feb 2023
  • INDICATIVE INVERTER & TRANSFORMER ELEVATIONS - APPROVED Amended Drawing · 10 Feb 2023
  • INDICATIVE BATTERY CONTAINER ELEVATIONS - APPROVED Amended Drawing · 10 Feb 2023
  • BESS CROSS SECTION - APPROVED Drawing · 10 Feb 2023
  • SITE LAYOUT PLAN - APPROVED Amended Drawing · 10 Feb 2023
  • OVERVIEW PLAN - APPROVED Drawing · 10 Feb 2023
  • PASSING PLACE LAYOUT - APPROVED Drawing · 10 Feb 2023
  • SWEPT PATH ANALYSIS - APPROVED Drawing · 10 Feb 2023
  • SITE ACCESS DETAILS - APPROVED Drawing · 14 Oct 2022
  • LANDSCAPE MITIGATION PLAN - APPROVED Drawing · 13 Oct 2022
  • LOCATION PLAN AERIAL - APPROVED Drawing · 13 Oct 2022
  • LOCATION PLAN - APPROVED Drawing · 13 Oct 2022

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Moray granted permission on 15 March 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land Adjacent To Electricity Substation Westerton Road Keith Moray

    24/01479/APP Submitted 23 Sep 2024 50 yards away

    Section 42 application to vary conditions 3, 12, 13, 14, 16, 18 and 19 of 22/01488/APP at

    Granted Full applications 41 docs
  • Land At Drum Farm Keith Moray

    23/01812/APP Submitted 10 Oct 2023 150 yards away

    Construction of a small section of access track at

    Granted Full applications 5 docs
  • Land At Drum Farm Keith Moray

    22/00715/APP Submitted 12 May 2022 200 yards away

    Installation of an energy storage facility including battery enclosures power conversion units transformer substations grid connection infrastructure vehicular access and associated works at

    Granted Full applications 19 docs
  • Land At Drum Farm Keith Moray

    24/01478/APP Submitted 23 Sep 2024 200 yards away

    Section 42 application to vary conditions 2, 5, 10, 11, 15 , 16 , 17, 18 and 19 of 22/00715/APP at

    Granted Full applications 34 docs
  • Drum Farm Keith Moray AB55 5NP

    24/01318/APP Submitted 22 Aug 2024 250 yards away

    Proposed agricultural building at

    Granted Full applications 11 docs
  • Land At Drum Farm Keith Moray

    21/01786/SCN Submitted 15 Oct 2021 250 yards away

    Development of a battery energy storage system on

    Decided Outline 1 doc

In Moray

  • 26/00863/APP Granted

    30 - 32 Mid Street Keith Moray

    Internal alterations and extensions for two townhouses at

    Received 10 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00898/APP Granted

    4 Seafield Place Cullen Buckie Moray AB56 4TF

    Erect single storey extension at

    Received 20 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00868/APP Granted

    The Breamou Inn 1 Cooper Street Hopeman Elgin Moray IV30 5SD

    Alter and extend existing bar/restaurant at

    Received 13 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00840/APP Granted

    30 Crown Street Portgordon Buckie Moray AB56 5RD

    Single storey rear extension including surface water soakaway at

    Received 3 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00979/APP Granted

    Delnabo Keepers Cottage Tomintoul Ballindalloch Moray AB37 9HT

    Extend dwellinghouse at

    Received 5 Aug, published by the council 16 Aug 2026 Full applications