Skip to content
PlanIndex Get alerts
Menu

Planning application

Land At Drum Farm Keith Moray

Granted Moray 22/00715/APP Application for Planning Permission

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Installation of an energy storage facility including battery enclosures power conversion units transformer substations grid connection infrastructure vehicular access and associated works at

As published by the council, reference 22/00715/APP

Application record

Reference
22/00715/APP
Type
Application for Planning Permission
Status
Decided
Decision
Granted As published: Permitted
Received
12 May 2022
Validated
12 May 2022
Decided
25 Oct 2022
Ward
Keith And Cullen
Parish
Strathisla
Decision by
Committee - National/Major

Site history

Applications at this address on the Moray register

This site has had 4 applications since 2021: 3 approved, 0 refused.

  • 24/01478/APP Granted

    Land At Drum Farm Keith Moray

    Section 42 application to vary conditions 2, 5, 10, 11, 15 , 16 , 17, 18 and 19 of 22/00715/APP at

    Decided 18 Dec 2024 Full applications
  • 23/01812/APP Granted

    Land At Drum Farm Keith Moray

    Construction of a small section of access track at

    Decided 20 Nov 2023 Full applications
  • 21/01786/SCN Decided

    Land At Drum Farm Keith Moray

    Development of a battery energy storage system on

    Decided 11 Nov 2021 Outline

Timeline

Dates from the published record

  1. 12 May 2022

    Received by Moray

  2. 25 Oct 2022

    Decision issued: Permitted

  3. 11 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

1 later application on the register refers to this one:

  • 24/01478/APP Granted

    Land At Drum Farm Keith Moray

    Section 42 application to vary conditions 2, 5, 10, 11, 15 , 16 , 17, 18 and 19 of 22/00715/APP at

    Decided 18 Dec 2024 Full applications

Documents

Plans, drawings, consultee responses and the officer's report

19 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Moray granted permission on 25 October 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Moray

  • 26/00863/APP Granted

    30 - 32 Mid Street Keith Moray

    Internal alterations and extensions for two townhouses at

    Received 10 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00898/APP Granted

    4 Seafield Place Cullen Buckie Moray AB56 4TF

    Erect single storey extension at

    Received 20 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00868/APP Granted

    The Breamou Inn 1 Cooper Street Hopeman Elgin Moray IV30 5SD

    Alter and extend existing bar/restaurant at

    Received 13 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00840/APP Granted

    30 Crown Street Portgordon Buckie Moray AB56 5RD

    Single storey rear extension including surface water soakaway at

    Received 3 Jul, published by the council 27 Jul 2026 Full applications
  • 26/00979/APP Granted

    Delnabo Keepers Cottage Tomintoul Ballindalloch Moray AB37 9HT

    Extend dwellinghouse at